U-600262, Forwards Closure Schedule for Open Items Identified in NRC Audit Conducted During Wk of 850826 of Facility Seismic & Dynamic Qualification of Equipment,Per SER Outstanding Issue 7ii

From kanterella
(Redirected from U-600262)
Jump to navigation Jump to search
Forwards Closure Schedule for Open Items Identified in NRC Audit Conducted During Wk of 850826 of Facility Seismic & Dynamic Qualification of Equipment,Per SER Outstanding Issue 7ii
ML20132B708
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/24/1985
From: Spangenberg F
ILLINOIS POWER CO.
To: Butler W
Office of Nuclear Reactor Regulation
References
U-600262, NUDOCS 8509260283
Download: ML20132B708 (5)


Text

-

U-600262 l

L30-85(09 -24 )-L 1A.120

/LLINDIS POWER COMPANY IP CLINTON POWER STATION, P.o. box 678. CLINTON. ILLINOIS 61727 September 24, 1985 Docket No. 50-461 Director of Nuclear Reactor Regulation Attention: Mr. W. R. Butler, Chief Licensing Branch No. 2 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Clinton Power Station Unit 1 SER Outstanding Issue #711 Seismic and Dynamic Qualification of Equipmenc

Dear Mr. Butler:

During the week of August 26, 1985, the NRC Staff and its consultants performed an on-site' audit of the Clinton Power Station Seismic and Dynamic Qualification of Equipment. Twenty pieces of equipment were selected for the audit, including two surprise items, to determine the adequacy of the equipment qualification program.

As a result of the audit. 12 specific open items were identified as well as 7 generic open items. The purpose of this letter is to provide a schedule for closure for each open item as specified by your Staff.

Attached is a description of each open item with a corresponding closure date. Please contact us if you have any questions on this matter.

Sincerely yours, F. A. Sp) g Director - Nuclear Licensing Nuclear Station Engineering JLP/kaf Attachment cc:

B. L. Siegel, NRC Clinton Licensing Project Manager NRC Resident Office Regional Administrator, Region III, USNRC Illinois Department of Nuclear Safety 8509260283 85092 4

DR ADOCK O l

PDR i.\\

i

i 1

CLOSURE SCHEDULE for NRC SQRT AUDIT OPEN ITEMS SCHEDULED OPEN ITEMS CLOSURE DATE Equipment Specific Items 1.

480 V. Unit Substation (BOP-1) a.

IP to install the locking devices for all 4 11-15-85 substations (Re: S&L ECN No.6016) and enter into plant maintenance procedure to ensure such installation, b.

IP is to submit Wyle Test Report of transformer 10-18-85 No. 42686-4 for SQRT review and acceptance.

2.

Rod Action Control Cabinet (NSSS-9) a.

Regarding the difference of as-installed 11-30-85 arrangement of 652 cabinet from as-tested.

IP is to provide for SQRT review and acceptance, additional information based on GE's "Hanford Report" which contains cabinet tests for other projects.

3.

HCU (NSSS-10) a.

The S&L calculation as provided during the audit,.

N/A which accounts for the presence of flaws (cracks) in estimating allowable fatigue cycle, will be further reviewed by SQRT.

4 SLC Pump & Motor (BOP-5) a.

Motor (Reliance) needs to be installed based on 10-18-85 industry's acceptable practice. Need a written confirmation from IP.

5.

Diesel Generator & Electrical Devices (B0P-6) a.

IP is to provide the seismic test report of the 09-30-85 audited AGASTAT Safety Setup relay for the SQRT review and acceptance.

IP is to confirm complete qualification of all remaining devices on Diesel Generator.

b.

IP is to confirm in-place and secure one side of 09-30-85 panel enclosure.

c.

IP is to address the oil leakage in engine sump 09-30-85 "0" ring in relation to NCMR 02-0431.

L

)

CLOSURE SCHEDULE for NRC SQRT AUDIT OPEN ITEMS SCHEDULED OPEN ITEMS CLOSURE DATE Equipment Specific Items (Cont'd) 6.

20" Recirculation Suction' Motor Operated Gate Valve _

(NSSS-3)

No review performed, because it was classified N/A as passive (see generic concern).

7.

Housing Cabinet (NSSS-1) a.

IP is to complete panel bolting.

11-15-85 b.

IP is to secure the doo'r panel.

11-15-85 c.

IP is to document the demonstration of 11-15-85 dynamic similarity between the tested panel and as-installed ene.

8.

RHR Suction Cooling.MOV (NSSS-2) a.

Revise valve specification which permits 11-15-85 qualification of active valve by analysis alone (see generic concern).

b.

IP is to complete the qualification by testing 11-15-85 (see generic concern).

c.

Revise valve specification (Form 350-B) 10-18-85 regarding definition of active valve.

9.

Metal Enclosed Switchgear (NSSS-8) a.

IP is to provide correlation and justification 11-01-85 of field modifications responding to the modifications made during the Wyle test.

b.

IP is to confirm that all NCRs have been 11-15-85

-complied.

c.

IP is to justify the use of wall response 10-18-85 spectra instead of floor response spectra in qualification (see generic concern).

CLOSURE SCHEDULE for NRC SQRT AUDIT OPEN ITEMS SCHEDULED OPEN ITEMS CLOSURE DATE Equipment Specific Items (Cont'd) 10.. Control Room Chiller-(B0P-2) a.

IP is to complete the installation of 11-15-85 transmitter connections.

b.

IP is to ensure that the panel door is 11-15-85 secured and closed.

11.

6900 V. Switchgear (BOP-3) a.

IP is to ensure that the screw of panel 09-30-85 door is tightened.

12.

14" 150 lb. Butterfly Valve (BOP-8) a.

IP is to complete qualification by testing 11-15-85 (see generic concern).

Generic Items 1.

IP is to revise valve specification to reflect 11-15-85 correct' definition of active valve.

2.

IP is to revise valve specification and FSAR 10-18-85 to reflect correct qualification requirement of active valves.

3.

IP is to provide a list of active valves for 10-01-85 the Clinton project.

4.

IP is to perform more sample tests for active 11-15-85 valve operability (not actuator) to supplement the analyses already performed for the valves.

This could be done based on categorization of

~

valves by size,-type, configuration and safety function requirements, etc.

IP is to confirm the completion of such program and submit some representative packages for the SQRT review and acceptance.

I L

CLOSURE SCHEDULE for NRC SQRT AUDIT OPEN ITEMS SCHEDULED OPEN ITEMS CLOSURE DATE Generic Items (Cont'd) 5.

IP is to submit monthly update of the 10-04-85 equipment master list which reficcts correct qualification status of each equipment item (including documentation and installation).

6.

IP is to demonstrate that the impact between 10-25-85 closely adjacent cabinets is addressed, by bolting the cabinets together, or by other justifiable approaches.

7.

IP is to verify and confirm that floor response 10-18-85 spectra were used for the qualification floor mounted equipment, or provide justification otherwise.