TXX-6856, Advises That Date of Full Compliance Stated in Util 870522 Response to Violations Noted in Insp Repts 50-445/86-15 & 50-446/86-12 Revised to 880301 & 890301 for Units 1 & 2, Respectively
| ML20235Y355 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 10/15/1987 |
| From: | Beck J, Counsil W TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
| References | |
| TXX-6856, NUDOCS 8710200319 | |
| Download: ML20235Y355 (1) | |
Text
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
M llllllll:' =
Log # TXX-6856 File # 10130
~~~
E IR 86-15 O~
1UELECTRIC 1
October 15, 1987 I
Wm'am G. Counsil Exsytive %ce PresMerit i
U. S. Nuclear Regulatory Commission Attn:
Document Control Desk Washington, D. C. 20555 ge
--, en
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
N DOCKET NOS. 50-445 AND 50-446 c>
INSPECTION REPORT NOS. 50-445/86-15 AND 50-446/86-12
> d REVISED DATE OF FULL COMPLIANCE FOR co NOTICE OF VIOLATION (NOV) ITEM C (446/8612-V-03)
[
REF:
- 1) NRC letter from E. H. Johnson to W. G. Counsil dated December 22, 1986.
- 2) TV Electric Letter TXX-6250 from W. 6. Counsil to NRC dated February 2, 1987
- 3) TV Electric Letter TXX-6466 from W. G. Counsil to NRC dated May 22, 1987 Gentlemen:
Reference (3) provided our revised response to Notice of Violation (NOV)
Item C (446/3612-V-03) of Inspection Report 50-445/86-15 and 50-446/86-12.
In that response TV Electric stated that issuance of instructions, examination of enclosures, and resolution of NCRs on NEMA enclosures would be completed by October 15, 1987.
For Unit 1 and Common Systems, these activities have been incorporated in the Post Construction Hardware Validation Program.
For Unit 2 systems, these activities will be accomplished as required to support Unit 2 fuel load.
Accordingly, our date of full compliance is revised as follows.
The issuance of instructions, examination of enclosures, and resolution of NCRs will be completed by March 1, 1988, for Unit 1 and Common Systems and by March 1, 1989, for Unit 2 Systems.
Very truly yours,
/J),C. M W. G. Counsil h 0]p)]g gyjok43 By:
G W. Bec ce President, Nuclear Engineering c-Mr. R. D. Martin, Region IV Resident inspectors, CPSES (3)
/