|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span ML20217M5711999-10-20020 October 1999 Forwards Insp Repts 50-445/99-15 & 50-446/99-15 on 990822- 1002.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20212L2891999-10-0101 October 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 ML20212F7481999-09-24024 September 1999 Forwards SER Authorizing Relief from Exam Requirement of 1986 Edition ASME Code,Section XI Pursuant to 10CFR50.55a(a)(3)(ii) for Relief Request A-3 & 10CFR50.55a(g)(6)(i) for Relief Requests B15,16,17 & C-4 ML20212F1041999-09-23023 September 1999 Requests That NRC Be Informed of Any Changes in Scope of Y2K System Deficiencies Listed or Util Projected Completion Schedule for Comanche Peak Steam Electric Station,Units 1 & 2 ML20212E6661999-09-21021 September 1999 Advises That Info Contained in Application & Affidavit, (CAW-99-1342) Re WCAP-15009,Rev 0, Comache Peak Unit 1 Evaluation for Tube Vibration Induced Fatigue, Will Be Withheld from Public Disclosure ML20212D9111999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of CPSES & Did Not Identify Any Areas in Which Performance Warranted Insp Beyond Core Insp Program.Core Insp Plan at Facility Over Next 7 Months.Insp Plan Through March 2000 Encl ML20212A7601999-09-14014 September 1999 Forwards Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Conduct of Activities Was Generally Characterized by safety-conscious Operations & Sound Radiological Controls TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211P3761999-09-0707 September 1999 Ack Receipt of Ltr Dtd 990615,transmitting Rev 30 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211J3801999-08-27027 August 1999 Forwards Corrected TS Page 3.8-26 to Amend 66 to Licenses NPF-87 & NPF-89,respectively.Footnote on TS Page 3.8-26 Incorrectly Deleted ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20211B2861999-08-18018 August 1999 Forwards Insp Repts 50-445/99-13 & 50-446/99-13 on 990720- 23.No Violations Noted.Insp Included Implementation of Licensee Emergency Plan & Procedures During Util Biennial Emergency Preparedness Exercise ML20211C4661999-08-18018 August 1999 Discusses Proprietary Info Re Thermo-Lag.NRC Treated Bisco Test Rept 748-105 as Proprietary & Withheld It from Public Disclosure,Iaw 10CFR2.790 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety ML20211C4571999-08-16016 August 1999 Forwards Omitted Subj Page of Contractor TER TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210R2221999-08-12012 August 1999 Forwards Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628.Violations Noted & Being Treated as Ncvs, Consistent with App C of Enforcement Policy ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210K2321999-07-29029 July 1999 Forwards Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210D8231999-07-23023 July 1999 Forwards Safety Evaluation of Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20210C3331999-07-16016 July 1999 Forwards Exam Repts 50-445/99-301 & 50-446/99-301 on 990618- 24.Exam Included Evaluation of Six Applicants for Senior Operator Licenses ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 1999-09-07
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20209G0721999-07-13013 July 1999 Forwards Monthly Operating Repts for June 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs of SV Occurred During Reporting Period ML20209F0681999-07-0909 July 1999 Informs That Effective 990514,TU Electric Formally Changed Name to Txu Electric.Change All Refs of TU Electric to Txu Electric on Correspondence Distribution Lists ML20209E0421999-07-0909 July 1999 Forwards Response to NRC Request for Addl Info on LAR 98-010.Attachment 1 Is Affidavit for Info Supporting LAR 98-010 ML20209B6021999-06-30030 June 1999 Submits Second Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Readiness Disclosure for Reporting Status of Facility Y2K Readiness Encl ML20195J6981999-06-15015 June 1999 Provides Addl Info Related to Open Issue,Discussed in 990610 Conference Call with D Jaffe Re ISI Program Relief Request L-1 Submitted by Util on 980220 ML20196A4921999-06-15015 June 1999 Forwards Rev 30 to Physical Security Plan.Rev Withheld,Per 10CFR73.21 ML20195J0491999-06-14014 June 1999 Submits Response to RAI Re Implementation of 1.0 Volt Repair Criteria ML20195J0651999-06-14014 June 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves 05000445/LER-1999-001, Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 11999-06-0808 June 1999 Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 1 ML20195F0091999-06-0808 June 1999 Forwards Response to RAI Re Units 1 & 2 ISI Program for Relief Requests E-1 & L-1.Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20207E1921999-05-28028 May 1999 Submits Updated Request for NRC Staff to Review & Approve Certain Changes to CPSES Emergency Plan Submitted in 981015 & s Prior to Changes Being Implemented at CPSES ML20207E1711999-05-28028 May 1999 Supplements 990526 LAR 99-004 as TU Electric Believes Extingency Exists in That Proposed Amend Was Result of NOED Granted to Prevent Shudown of CPSES Unit 1 ML20207D9841999-05-26026 May 1999 Requests That NRC Exercise Enforcement Discretion to Allow Cpses,Unit 1 to Remain in Mode 1,power Operation,Without Having Performed Svc Test,Per SR 4.8.2.1d on Unit 1 Battery BT1ED2 ML20195B6351999-05-25025 May 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves TXX-9912, Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise1999-05-21021 May 1999 Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise ML20206U1981999-05-20020 May 1999 Forwards Form 10K Annual Rept,Per 10CFR50.71(b). Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20196L1931999-05-20020 May 1999 Forwards MOR for Apr 1999 for Cpses,Units 1 & 2.During Reporting Period There Have Been No Failures or Challenges to Power Operated Relief Valves or Safety Valves TXX-9911, Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld1999-05-14014 May 1999 Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059K6141990-09-17017 September 1990 Submits Documentation of 900906 Telcon Re Addl Util Candidate for Licensed Operator Generic Fundamentals Exam Section ML20059G8761990-09-10010 September 1990 Forwards Rev 8 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21) ML20059F8461990-09-0404 September 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-22 & 50-446/90-22 on 900606-0705.Corrective action:OPT-467A Changed to Provide Addl Prerequisite Info Re Solid State Protection Sys Switch Lineup During Testing ML20059E4981990-08-31031 August 1990 Forwards Revised Radial Peaking Factor Limit Rept for Cycle 1 Per Tech Specs Through Amend 1 & ML20059E4201990-08-30030 August 1990 Forwards Objectives & Guidelines for 1990 Emergency Preparedness Exercise Scheduled for 901113 ML20028G8281990-08-29029 August 1990 Forwards Comanche Peak Unit 1 Semiannual Radioactive Effluent Release Rept,900403-0630 & ODCM TXX-9030, Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-1311990-08-27027 August 1990 Forwards Endorsements 40 & 4 to Nelia Policy NF-274 & Maelu Policy M-90,respectively & Endorsements 10,11,12,13,14 & 15 to Maelu Policy MF-131 ML20059F4381990-08-23023 August 1990 Forwards Public Version of Revised Emergency Plan & Corporate Emergency Response Procedures,Consisting of Rev 1 to EPP-313,Rev 7 to CERP-101,Rev 7 to CERP-102 & Revised Forms.W/Dh Grimsley 900906 Release Memo TXX-9029, Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents1990-08-20020 August 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/89-57 & 50-446/89-57.Corrective Actions:Storage Facilities for Instrumentation & Control Work Packages Improved to Provide Acceptable Protection for Documents ML20058P0571990-08-13013 August 1990 Forwards, Comanche Peak Steam Electric Station Unit 1 Control Room Simulator 10CFR55 Certification Initial Rept ML20058N2311990-08-0909 August 1990 Forwards First Half 1990 fitness-for-duty Program Performance Data,Per 10CFR26.71(d).Point of Contact for Personnel,Random Testing Program Results & Confirmed Positive Tests Summary & Mgt Summary Included in Data ML20059A5831990-08-0404 August 1990 Responds to Info Request Made During 900802 Meeting Re Inadvertent Safety Injections on 900726 & 30 & Results of 100% Power Plateau Testing TXX-9024, Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel1990-08-0303 August 1990 Provides Status of Exam Activity & Revised Completion Schedule for Portion of Exam.Util Deferred Preoperational Testing of Facility Spent Fuel Pool Cooling & Cleanup Sys Until Prior to First Off Loading of Spent Fuel TXX-9022, Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station1990-07-31031 July 1990 Forwards Detailed Descriptions of Changes in Amend 79 to FSAR for Comanche Peak Steam Electric Station TXX-9027, Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required1990-07-30030 July 1990 Responds to NRC Re Violations Noted in Insp Repts 50-445/90-19 & 50-446/90-19.Corrective Action:Specific Activity within Tech Spec Limits.No Further Corrective Action Required ML20055J1571990-07-27027 July 1990 Submits Info Re Replacement of Borg-Warner/Intl Pump,Inc Check Valve Swing Arms,Per .Swing Arms in ASME Code Class 2 Check Valves Will Be Replaced During First Refueling Outage ML20056A0461990-07-24024 July 1990 Requests Regional Waiver of Compliance for Containment Pressure Transmitter 1-PT-934 During Coming Outage TXX-9023, Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility1990-07-18018 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. No Subj Transmitters in Existence at Facility ML20055G6351990-07-17017 July 1990 Submits Results of Remote Shutdown Panel Environ Survey ML20055F9391990-07-13013 July 1990 Advises That Operators Have Gained Significant Experience in Operating Plant Under Wide Range of Conditions & Have Demonstrated Necessary Proficiency to Safely Operate Unit ML20055F9371990-07-13013 July 1990 Submits Info Re Revised Acceptance Criteria for THERMO-LAG Fire Barrier,Per 900705 Telcon.On Exposure to Heat Flux at Surface of Barrier,Listed Mechanisms Activated.Fire Testing Demonstrates That Panels Qualified W/Variation in Thickness ML20044A7001990-06-26026 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Util Will Implement for Unit 2 Activities Performed for Unit 1 ML20044A1411990-06-20020 June 1990 Forwards Endorsements 4 & 5 to Nelia Certificate N-90, Endorsements 5 & 6 to Maelu Certificate M-90 & Endorsements 34,35,36,37,38 & 39 to Nelia Policy NF-274 ML20043H7031990-06-18018 June 1990 Discusses Mod/Rework to Auxiliary Feedwater Sys Check Valves Mfg by Bw/Ip Intl,Inc.All But One Affected Check Valve modified.Motor-driven Auxiliary Feedwater Pump Discharge Valve Check Valve Body Replaced ML20043H2181990-06-15015 June 1990 Forwards Response to 900515 Request for Addl Info on Emergency Preparedness.Ongoing Emergency Preparedness Programs Address Concerns Raised by Citizens for Fair Util Regulation ML20043G3131990-06-15015 June 1990 Forwards Addl Info Re Pressurizer Surge Line Thermal Stratification & leak-before-break Evaluation & Nonproprietary Suppl 3 to WCAP-12247, Supplementary Assessment... & Proprietary Suppl 3 to WCAP-12248 ML20043C5671990-06-0101 June 1990 Discusses Identification of Slave Relays Tested Using Alternative Methodology,Per 900402 Commitment.Encl Tabulation Identifies Test Type,Applicable Procedures & Equipment & Impact of Improper Documentation ML20043E7131990-06-0101 June 1990 Responds to NRC 900517 Notice of Violation & Imposition of Civil Penalty in Amount of $25,000.Corrective Action:Qc Mgt Counseled Level III Inspector & QC Supervisor on Importance of Good Communications W/Receipt Inspectors ML20043C4501990-05-31031 May 1990 Advises That Util Revised FSAR Section 15.1.2 & Question/ Response 32.108,per 10CFR50.59 ML20043B5471990-05-25025 May 1990 Provides Status of Facility Design & Const Activities,Per Request.Detailed Design Work Will Resume in June 1990.Const Activities Expected to Increase Signficantly by Jan 1991 ML20043B5481990-05-23023 May 1990 Provides Clarification of 890710 Commitment Re Power Ascension Program.Cooldown Portion of Remote Shutdown Test Performed During Preoperational Testing,Per FSAR & Reg Guide 1.68.2 ML20043D1711990-05-21021 May 1990 Forwards Public Version of Revised Emergency Plan Procedures,Including Rev 8 to EPP-109,Rev 7 to EPP-112,Rev 4 to EPP-116 & Rev 6 to EPP-121.W/DH Grimsley 900604 Release Memo TXX-9018, Advises of Completion of Implementation of Requirements of Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety- Related Equipment1990-05-21021 May 1990 Advises of Completion of Implementation of Requirements of Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety- Related Equipment ML20043B0981990-05-15015 May 1990 Forwards Radial Peaking Factor Limit Rept for Cycle 1, Containing F(Xy) Limits for All Core Planes Containing Bank D Control Rods & All Unrodded Core Planes ML20042F2851990-05-0303 May 1990 Supplemental Response to Generic Ltr 90-01, Request for Voluntary Participation in NRC Regulatory Impact Survey. ML20042F3861990-05-0303 May 1990 Responds to NRC 900410 Ltr Re Violations Noted in Insp Repts 50-445/90-10 & 50-446/90-10 on 900206-07 & 0226-0302. Corrective Action:Memo Issued Emphasizing That Discrepancies Should Be Brought to Attention of Site Organizations ML20042F3021990-05-0202 May 1990 Responds to NRC 900402 Ltr Re Violations Noted in Insp Repts 50-445/89-23 & 50-446/89-23.Util Does Not Believe That Circumstances Described in 900402 Ltr Constitutes Violation of 10CFR50.9(a) ML20042F3051990-05-0202 May 1990 Provides Revised Response to Generic Ltr 88-17 Re Loss of DHR ML20042E4581990-04-12012 April 1990 Responds to Inconsistencies in Terminology & Labelling Identified During NRC 890118 & 19 Audit of Facility Dcrdr. Util Believes Control Room Inventory Requirement of Suppl 1 to NUREG-0737,satisfied ML20042E0701990-04-10010 April 1990 Discusses 900305 Meeting W/Nrc in Rockville,Md Re Offsite Power Availability for Automatic Switch Co Solenoids for MSIV in Event of Nonmechanistic Main Steam Line Crack in Superpipe Region ML20012F5011990-04-0303 April 1990 Forwards Corrections to 891016 Response to Emergency Diesel Generator Engine Requirements.Lengths of Two Pairs of Bolts Above Crankpin Shall Be Measured Ultrasonically Before Detensioning & Disassembly of Bolts ML20012F3221990-04-0202 April 1990 Discusses ESF Sys Slave Relay Alternate Test Methodology. Implementation Schedule for Design Mods to Relay Will Be Submitted by 900601 ML20042D8081990-03-29029 March 1990 Forwards Proposed Change to FSAR Section 13.4 Re Station Operations Review Committee.Similar Change Submitted in 900328 Ltr for Chapter 6 of Facility Tech Specs ML20012F0411990-03-28028 March 1990 Forwards marked-up Pages of Facility Draft Tech Specs & Bases (NUREG-1381) Provided W/Low Power OL ML20012E6051990-03-27027 March 1990 Forwards Endorsements 1-4 to Maelu Certificate M-90, Endorsements 1-9 to Maelu Policy MF-131,Endorsements 29-33 to Nelia Policy NF-274 & Endorsements 1-3 to Nelia Certificate N-90 ML20012E6531990-03-27027 March 1990 Provides Final Response to Reporting Requirement 2 of NRC Bulletin 88-008, Thermal Stresses in Piping Connected to RCS, for Unit.Nde Requirements of Action 2 Not Considered Applicable to Unit ML20012E1911990-03-23023 March 1990 Forwards Comanche Peak Steam Electric Station Unit 1 Cycle 1 Startup Physics Tests Control Rod Worth Predictions Utilizing TU Electric Control Rod Swap Methodology. ML20012E1581990-03-23023 March 1990 Clarifies 880624 Response to NRC Generic Ltr 88-05, Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary Components in PWR Plants. ML20012D0201990-03-19019 March 1990 Advises That Allegations Provided to NRC by Former Util Employee Unsubstantiated,Based on Investigation by Util Safeteam Organization ML20012E2181990-03-19019 March 1990 Responds to Generic Ltr 89-19 Re USI A-47, Safety Implication of Control Sys in LWR Nuclear Power Plants. Util Determined That Loss of safety-related Inverters 1 or 2 Would Involve Coincidental Opening of Main Feedwater Valves 1990-09-04
[Table view] |
Text
-.
o M Log # TXX-6631 F9 File # 10004
~~
=
NELECTRIC August 20, 1987 WWism G Counsil Executsve Vice Presuk'est U. S. Nuclear-Regulatory Commission ATTN: Document Control Desk j Washington, D.C. 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) l DOCKET NOS. 50-445 AND 50-446' COMANCHE PEAK PROGRAMS Gentlemen:
TV Electric hereby provides, in the attachments to this letter, a description of the Comanche Peak Response Team (CPRT) and Corrective Action Program (CAP),
and TU. Electric's position on how the two programs interrelate. The two programs will collectively be referred to as the Comanche Peak Programs {
throughout this letter.
Attachment I provides a written description of the Comanche Peak Programs to be used with the illustration of these Programs provided in Attachment 2. The ;
drawing in Attachment 2 is simplified for illustration purposes and does not i show each individual feedback loop between CPRT and CAP.
Very truly yours,
().G. w W. G. Counsil
~
By: me-< %
87082 PDR g g[$$$k45 L. D. Nace A
PDR Vice President, Engineering and Construction RSB/grr Attachments c - Mr. C. I. Grimes (1 letter w/ 1 figure attached) i Mr..H. E. Schierling (1 letter w/ 20 figures attached) i Mr. R. D. Martin, Region IV Resident Inspectors CPSES (3 letters w/10 figures attached)
A 9 ') \
j 400 North Olive Street LB 81 Dallas, Texas 75201
. Attachment I to TXX-6631 August 20, 1987 Page 1 of 6 i
COMANCHE PEAK PROGRAMS The genesis of the current Comanche Peak Programs was the external source issues identified by the following:
o NRC Staff Special Review Team (NRC-SRT) o NRC Staff Special Inspection Team (SIT) o NRC Staff Construction Appraisal Team (CAT) o Citizens Association for Sound Energy (CASE) o Atomic Safety & Licensing Board (ASLB) o NRC Region IV Inspection Reports (RIV-IR) o NRC Staff Technical Review Team (TRT) [SSER 7-11]
o Cygna Independent Assessment Program (IAP)
These external source issues, particularly those identified by the TRT, resulted in TU Electric's initiation of the Comanche Peak Response Team (CPRT). The Comanche Peak Response Team consisted of two basic elements:
o Design Adequacy Program (DAP); and o Quality of Construction (QOC) Program, including Issue Specific Action Plans (ISAPs) for each discrete TRT issue.
These two elements investigated and evaluated both design-related and construction /QA-related issues.
Desian Adeauacy Procram The Design Adequacy Program o conducted investigations of the adequacy of design; o identified individual deviations in the form of Discrepancy Issue Reports (DIRs) for project resolution; 3 o grouped related DIRs into Issue Resolution Reports (IRRs) for project evaluation; and o provided overview of project corrective action for the identified deficiencies in the pipe and pipe support, cable tray hanger and conduit support programs at CPSES.
A qualitative and quantitative review by TV Electric of the preliminary results of the DAP investigative phase revealed that the findings identified were very broad in scope and included most disciplines. The significance of these preliminary findings prompted TU Electric to initiate a comprehensive ,
Corrective Action Program (CAP). DAP findings, in the form of IRRs and DIRs, were inputs to the CAP. The CAP utilized industry recognized architect-engineering firms to conduct a complete validation of all safety-related and selected non-safety related design aspects of CPSES with the following exceptions:
o NSSS System (~nterface being validated) o Vendor hardware design (Interface being validated)
)
> Attachment I to TXX-6631 August 20, 1987 Page 2 of 6 This complete design validation is being conducted in eleven disciplines as will be further discussed later in this submittal. TU Electric's commitment to conduct this complete validation of the safety-related design obviated the necessity to continue the evaluation phase of the CPRT Design Adequacy '
Program. In particular, this early TV Electric decision obviated the need for the DAP evaluation'of identified design discrepancies per the CPRT Program Plan, Appendix E. However, the DAP continued its overview activities for certain project corrective actions. The DAP overview activities will be documented in the following three Discipline Specific Action Plan (DSAP)
Results Reports which are scheduled to be submitted to the NRC Staff by October 1987:
o Large Bore Pipe Supports; o Cable Tray Hangers; and o Conduit Supports.
The r, significance of the findings identified by the DAP and the effectiveness of the TV Electric CAP in resolving those findings will be addressed in the CPRI Senior Review Team Collective Significance Report which is scheduled to be submitted to the NRC Staff in December 1987.
Quality of Construction Proaram The CPRT Quality of Construction (Q0C) Program was conducted in two parts:
o investigation and evaluation of Issue Specific Action Plans which addressed discrete NRC Staff Technical Review Team (TRT) issues; and o a self-initiated investigation and evaluation of the quality of construction of the completed hardware.
During the investigation phase, CPRT, through its sampling reinspection program, identified findings to the project in the form of Deviation Reports (DRs) and Out of Scope Observations (00S0s). These DRs and 00S0s were converted to project Nonconformance Reports (NCRs) for project resolution.
Separately and in parallel, findings from the QOC Program were evaluated by )
CPRT in accordance with the CPRT Program Plan, Appendix E, for: I o Safety Significance Evaluation as defined in the CPRT Program Plan (to determine the necessity for sample expansion);
l o Trend Evaluation; i o Root Cause Analysis; and '
o Generic Implications.
The results of the investigation and evaluation will be published in 46 Issue Specific Action Plan Results Reports. All of these reports are scheduled for submittal to the NRC Staff by October 1987. In addition, the ISAP VII.c Results Report for the self-initiated evaluation of construction quality is scheduled for submittal to the NRC Staff by October 1987.
Additionally, the results of the QOC program are inputs to the CPRT QA/QC Program Collective. Evaluation Report and the CPRT Senior Review Team Collective Significance Report, scheduled for submittal to the NRC Staff by October 1987 and December 1987, respectively.
Attachment 1 to TXX-6631 August 20, 1987 Page 3 of.6 Deficiencies and recommendations identified in the QOC results reports and Collective Evaluation Report are provided to the project in the form of:
o Results Report Recommendations (RRRs); and o Program Deficiency Reports (PDRs).
Those RRRs'and PDRs resulting from deficiencies which CPRT determined to be
" safety significant" (as defined in the CPRT Program Plan) are addressed in project Corrective Action Reports (CARS). The CPRT must concur with project resolution of those recommendations. Other recommendations, RRRs resultinc from deficiencies determined by CPRT to be not safety significant, are provided as direct input to the project for. consideration in the post-construction hardware validation phase to be discussed later in this letter.
At this time, the CPRT investigation and evaluation is essentially complete and has identified those issues which must be resolved by the project. This i investigation and evaluation of findings was a necessary step to determine the nature and extent of corrective actions at CPSES, and it served as a vital input to the formulation of the CAP.
TV Electric Corrective Action Proaram TV Electric evaluated the early results coming out of the CPRT program, as discussed earlier, and made a decision to initiate the CAP. The CAP includes a complete design and hardware validation program of the safety-related and selected non-safety related portions of CPSES (with exceptions noted earlier) and provides a planned, integrated resolution of identified problems rather than attempting to resolve each issue individually. This methodology assures that all issues are appropriately addressed. TU Electric contracted Stone &
Webster Engineering Corporation, Ebasco, and Impe11 to conduct the CAP.
CAP Scope The CAP. scope was divided into eleven disciplines as follows-DISCIPLINE RESPONSIBLE CONTRACTOR Mechanical SWEC Systems Interaction EBASCO Fire Protection IMPELL Civil / Structural SWEC Electrical SWEC Instruments > ion & Control SWEC Large Bore Pipe Supports SWEC PSAS Cable Tray Hangers EBASC0/IMPELL Conduit Supports Trains A, B, and C > 2" EBASCO l Conduit Supports Train C s 2" IMPELL I Small Bore Pipe Supports SWEC PSAS HVAC EBASCO Equipment Qualification IMPELL
Attachment I to TXX-6631 August 20, 1987 Page 4 of 6 Generic Issue Reports All external issues known at the time of issuance, including DIRs and IRRs issued from the DAP, were collected in Generic Issue Reports (GIRs). A GIR was developed for each of the 11 disciplines by the responsible CAP contractor. All of the GIRs have been submitted to the NRC Staff. These GIRs collected known issues and identified the planned approach to resolve these issues. The GIRs are not being updated for additional input data, but are being revised as the methodology to resolve issues changes. Additional data are input directly to the CAP design and hardware validation phases where they are evaluated and resolved.
Desian Validation The GIRs, as well as available, applicable historical design data such as calculations, drawings, specifications, change documentation, deficiency paper, licensing commitments, FSAR commitments, and correspondence were reviewed by the responsible contractor. Design-related licensing commitments are captured in Design Basis Documents (DBDs) which were developed to clearly identify the bases for the Design Validation effort. Design documentation, and identified design problems, are then reviewed to the design bases to ensure that the design satisfies the licensing commitments. The design documentation is either validated as being acceptable, or it is revised to be acceptable. The design validation effort within each of the eleven CAP disciplines is being accomplished and documented in smaller workable packages, design validation packages (DVPs). The Design Validation provides assurance that the design meets all licensing commitments. One of the major activities in the design validation effort is to revise the Engineering specifications to reflect the validated design, and to include hardware inspection requirements in the specification. This validated design, with required changes identified, is the " final design" with respect to the CPRT program, in that it resolves all CPRT design issues.
Post Construction Hardware Validation The Post Construction Hardware Validation Program (PCHVP) is a complete validation of final acceptance inspection attributes for safety-related and selected non-safety related hardware. The revised (validated) erection specifications include hardware inspection requirements for new installations and form the bases for the PCHVP Attribute Matrix. Using input from the QOC program in the form of CARS, NCRs, and CPRT recommendations, and changes identified as a result of the CAP design validation activities, the Engineers will challenge (i.e., evaluate) each final acceptance attribute for acceptability and determine the method to be used to validate that attribute.
This evaluation is procedurally controlled, and if the disposition is
" acceptable", the results will be clearly documented. If the technical assessment of the attribute is dispositioned "not acceptable" (or cannot be dispositioned based on available information), then measures such as !
inspection, walkdown, or alternative testing to validate the attribute will be !
performed. As mentioned at our public meeting the procedures to guide the !
Engineer on these evaluations should be completed by the end of August.
l I
L ,
i Attachment 1 to TXX-6631 q August 20, 1987 '
Page 5 of 6 Physical validation of an attribute by quality control reinspection or engineering walkdown will be performed, for accessible components, when any of j the following pertains:
o CPRT recommendation to reinspect; o Design Validation results in change to design or acceptance attribute; or o Design Validation results in new work, including modification to existing hardware.
The PCHVP provides assurance that the as-installed hardware meets the validated design.
Desian Reconciliation The as-installed condition is compared to the validated design and any design data which have been identified as subject to confirmation are confirmed, thereby ensuring that the final installation satisfies final design requirements. The design reconciliation provides the documented data base which establishes that the as-constructed plant meets the design basis. The documentation is then vaulted.
Proiect Status Reports The results of the CAP are reported in eleven Project Status Reports (PSRs),
one for each of the eleven disciplines. The PSRs identify and describe the resolution of issues (including IRRs, IAP findings, SDARs), describe the design and hardware validation activities, and report how the issues were resolved such that licensing commitments have been satisfied. The methodology and results of the corrective action taken are discussed in detail.
Appendices to the PSR specifically address:
Appendix A - External Source and CPRT Issue Specific Resolution; Appendix B - Self-initiated Issue Specific Resolutions; and Appendix C - Preventive Action Taken.
Overview ,
I The CPRT has essentially completed its investigation and evaluation phases, as )
described earlier, and is now preparing their results reports and conducting l overview of the corrective action phase. The overview is the responsibility '
of the CPRT Senior Review Team. The Senior Review Team exercises their overview through the following methods:
1 o selected CPRT overview; o monitoring of the implementation and results of the TU Electric QA Program Technical Audit Program; and o monitoring of the implementation and results of the Engineering Functional Evaluation.
(More details on the Technical Audit Program and the Engineering Functional Evaluation program will be provided in separate submittals.)
i
. Attachment I to TXX-6631 August 20, 1987 Page 6 of 6 The implementation and results of these overviews will be discussed in the CPRT Collective Significance Report.
Summary .
The CPRT investigation of issues and evaluation of findings is essentially
- complete, and has identified those issues which must be resolved by the project. This investigation and evaluation of findings was a necessary step to determine the nature and extent of problems at CPSES, and it served as vital input to the formulation of the CAP.
The CAP was formulated to address CPRT and other open external source issues. ,
The CAP has three elements; validation of design to licensing commitments, '
validation of hardware to the validated design, and design reconciliation.
TV Electric is confident that the CAP, when implemented, will provide assurance that the design satisfies licensing commitments, and the hardware complies with the validated design. This in turn provides assurance that structures, systems and components with a safety-related function will perform satisfactorily in service.
jji l l;l! ll !
(
o A
m v
1 Q
/
o 3 PET Ar 6
6 TE2 X , ,
X T s
+
3 r
+
o7 t8 m
r
,llIIi'Ii3liII!IEIJ ,
9 rR S EN _ _
21 sE VI O I
,3 G i CAT TT _ _
t E N isn -
m EiR l
n0f rA u LLO l
e2 o S eH F F LAP m T Y ECE p E OVE R CER _ -
ht1 m VN cs P aRAW cT T I
TA
aue E CCT S C u ST t 9g F tE1 f EnR L O 4 TT LRO
[
- xTm -
P cL0 TLHP )
t ua nBt psp t oAP AAP A D
aAO ROKE SCSR A EE T
N - 1 R1t 1 rss _
tCC 5 RR A 1
C I - -
m" >> -
I )
T F
N G
I
+. -
N S -
A C Y I
F T E
W F
A - _
S S S T
M Y T
E R
P C
n _
A F A
S
(
R A
u C
V I
L U
R T R
D P -
n.
o sm A
V _
G P C &
R -
EE oR _
O T O
N R
R R (
R R
T C
I -
P R 4 V OR RA PC _
K - _-
A _
y -
E J N
0 s _ -
P I
E5 1 S _
YN y H -
CN NAnAT NLO o
_ +
I AP1 C TP 4
A T
CE a
I X A AC uRA E M FEU IL m4i.
fA EP S
- T m.m A o
H A R
G N
n i
!I CV UI TEACC M
yV C
E M R Tso SnRu OoAA C O R
P T
A U
YM TLD TER I
0 5
(
RC PN PCNv _
N C L
A V
ELN FAE AVROE SETRG ON 0 0
- m-A C C
E
R - 6 M &
P N
O D
t O 2 A
5 1
l T
A - m CA _
G TT C M A
I T
5 E -
_ sA uD s _
R C
t T I V 4 A _
PO S.
t - c AR DP P F
,- a s
R
- s t 4 o _
l e _ 5 g s _
_ D s .
p rV C I
R EEm h T y o _
y - i
.. V NL r E 5 E CIG R " _
M*
5 Sg I
E DV E
U T D -
u 5 5
1 C
a r
1 1
- I R EV -
E R .. TT C E u P 5 CT A _
A m 5 EC N R c 0 5 y n1 - LE ER 0 c -
a L pT T
-TP Rno rA vR i A - UOCR TCAP -
T A ssC RTl R N - - A iIIgIIIt P R _ - - jgIII,II,I' E EB 4 C T eeCSLCCG RAS RT X
E mmNCAmNC lli il (ll' i , , 1 w_
.- Attachment 2 to TXX-6631 August 20, 1987 Page 2 of 3 l
FOOTNOTES:
LEGEND:
BLUE - Raw Data Input I GREEN - CPRT Program BLACK - Corrective Action Program RED - End Product Reports Arrows indicate the flow of information. Double ended arrow head means CPRT concurrence is required on corrective actions that CPSES Project takes to resolve CPRT Results Report Recommendations and Program Deviation Reports which stemmed from CPRT Safety Significant findings.
Similiary, the double ended arrow between the Corrective Action Program Block and the Overview Block means that the appropriate Overview Group must concur with resolution of identified concerns.
- 1) IRRs are a grouping of related DIRs.
- 2) DAP did not perform evaluations of findings per CPRT Program Plan, Appendix E, because of TV Electric decision to conduct CAP.
- 3) The DAP Discipline Specific Action Plan Results Reports document CPRT overview of TV Electric Corrective Action Programs for these topics.
- 4) ISAPs address discrete TRT issues.
- 5) At time of issuance GIRs input raw data and describe approach to resolve related issues. GIRs are not being updated for additional input data.
They are being updated as methodology to resolve the issues changes.
- 6) Includes, but is not limited to, applicable calculations, drawings, specifications, change documentation, deficiency paper, licensing commitments, FSAR commitments, procedures, records, correspondence.
I
4 Attachment 2 to TXX-6631 l August 20, 1987 l Page 3 of 3 i ACRONYMS: l ASLB Atomic Safety and Licensing Board CAT Construction Appraisal Team CAR Corrective Action Request CASE Citizens Association for Sound Energy CPRT Comanche Peak Response Team )
DAP Design Adequacy Program DIR Discrepancy Issue Report DR Deviation (CPRT)/ Deficiency (TV) Report DSAP Discipline Specific Action Plan DVP Design Validation Program EFE Engineering Functional Evaluation (SWEC) l FSAR Final Safety Analysis Report 1 GIR Generic Issues Report IAP Independent Assessment Program (CYGNA) i IRR Issue Resolution Report ISAP Issue Specific Action Plan NCR Nonconformance Report NRC-SRT NRC Special Review Team 00S0 Out-of-Scope Observation PDR Program Deviation Report PSR Project Status Report QOC Quality of Construction (ERC)
RIV-IR Region IV Inspection Report RRR Results Report Recommendation SDAR Significant Deficiency Analysis Report SIT Special Inspection Team SRT Special Review Team TAP Technical Audit Program (TV)
TRT Technical Review Team (SSERs 7-11)