TXX-6439, Informs That Date for Full Compliance Re Enforcement Action EA-86-009,App B,Item I.B.2 Revised to 871030.Review of Vendor Drawings Being Performed as Part of Corrective Action Taking Longer than Expected

From kanterella
(Redirected from TXX-6439)
Jump to navigation Jump to search
Informs That Date for Full Compliance Re Enforcement Action EA-86-009,App B,Item I.B.2 Revised to 871030.Review of Vendor Drawings Being Performed as Part of Corrective Action Taking Longer than Expected
ML20215L978
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/06/1987
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
EA-86-009, EA-86-9, TXX-6439, NUDOCS 8705130040
Download: ML20215L978 (1)


Text

P9 Log # TXX-6439

. C File # 10118

TUELECTRIC Ref. # 10CFR2.201

%iHiaan G. Ocumil bewriw Ike Newkno May 6, 1987 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 EA N0. 86-09 Gentlemen:

By letter dated August 4, 1986, we provided our response to Enforcement Action No. 86-09. In our response to Appendix B, Item I.B.2, we stated that full compliance would be achieved by April 1, 1987. In a telephone conversation with the CPSES NRC resident inspector, Ian Barnes, on April 15, 1987, we identified this commitment as one of several which was not completed by its due date.

As part of the corrective action associated with this commitment, a complete review of vendor drawings is being performed. This review is taking longer than expected. Accordingly, the date for full compliance for Appendix B, Item I.B.2 is revised to October 30, 1987.

Very truly yours, f, bd W. G. Counsil By: , s 8 /

G'. S. Keeley Manager,NuclearLiknsing BSD:amb c - Mr. E. H. Johnson, Region IV Mr. D. L. Kelley, RI - Region IV Mr. H. S. Phillips, RI - Region IV