TXX-6122, Interim Deficiency Rept CP-86-08 Re Control of Stamps Used to Identify Super Hilti Kwik Bolts.Initially Reported on 860206.Ultrasonic Testing Will Be Completed by 870227.Next Rept Anticipated by 870320

From kanterella
(Redirected from TXX-6122)
Jump to navigation Jump to search
Interim Deficiency Rept CP-86-08 Re Control of Stamps Used to Identify Super Hilti Kwik Bolts.Initially Reported on 860206.Ultrasonic Testing Will Be Completed by 870227.Next Rept Anticipated by 870320
ML20215D661
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/01/1986
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-86-08, CP-86-8, TXX-6122, NUDOCS 8612160441
Download: ML20215D661 (1)


Text

.

Log # TXX-6122 File # 10110 _1 903.9 =

TEXAS UTILITIES GENERATING COMPANY f SKYWAY TOWER . ese NORTH OLIVE STREEr. 3.15. 83 . DALL.AB. TEXAS THOI q December 1, 1986 $

m??,"tff.0:A 3 @IE Mr. Eric H. Johnson, Director DEC - 91986 e E

i Division of Reactor Safety and Projects # [

U. S. Nuclear Regulatory Commission _ __

611 Ryan Plaza Drive, Suite 1000 -

Arlington, TX 76011 -

a

[

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) -

DOCKET NOS. 50-445 AND 50-446 I l

' INSTALLATION OF SUPER HILTI KWIK BOLTS =

SDAR: CP-86-08 (INTERIM REPORT) }

Dear Mr. Johnson:

On February 6,1986, we verbally notified your Mr. T. F. Westerman of a 1 deficiency involving the control of stamps used to identify Super Hilti Kwik 4l Bolts. This is an interim report of a potentially reportable item under the .3 -

provisions of 10CFR50.55(e). Our latest interim report, logged TXX-4963, was e submitted on August 22, 1986. "

l As noted in our previous response, the portion of this deficiency which 5 involves ASME installations has been completed without the identification of conditions adverse to safety. All installations were evaluated and determined $

to be acceptable "as-is". ,

For the portion of this issue involving non-ASME applications (such as cable _

tray supports, structural steel, conduit supports, and electrical equipment y, installations), our evaluation is continuing. This effort, which consists of  ?

ultrasonic testing of a sample of non-ASME installations, must be completed a prior to our assessment of the possible adverse effects of this deficiency. F' These testing activities are currently scheduled for completion on February E_

27, 1987.

4 We anticipate submitting our next report by March 20, 1987. -

Very truly yours,  ;

=

. E s

8612160441 861201 / / 6- -

PDR S

ADOCK 05000445 PDR

/ ,

' ' g

  • 2 l W. G. Counsil ,,'

! GLB/mlh -

c - NRC Region IV (0 + 1 copy)

! Director, Inspection & Enforcement (15 copies) '

U. S. Nuclear Regulatory Commission  %

Washington, D.C. 20555 g A unusum or rms twmas ruernic <<mmr 1

% -1400 i o IEZ7 _p