TXX-4925, Interim Deficiency Rept CP-86-38 Re Failure of Project Procedures to Address Installation & Insp Criteria for Cable Runs Used as Device Pigtail Extensions.Initially Reported on 860527.Evaluation Underway.Next Rept by 860912
| ML20203G735 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 07/21/1986 |
| From: | Counsil W TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | Johnson E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| CP-86-38, TXX-4925, NUDOCS 8608040035 | |
| Download: ML20203G735 (1) | |
Text
Log # TXX-4925 File # 10110 908.3 TEXAS UTILITIES GENERATING COMPANY NKYWAY TOWER. 400 NORTH OLIVE STREET. L.B. 81
- DALLAS, TEXAS 7520 t July 21, 1986 cM27&ff.fAS l
(
Mr. Eric H. Johnson, Director l
D;/
Division of Reactor Safety and Projects U. S. Nuclear Regulatory Commission
'-+
611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS.
50-445 AND 50-446 i
TRACEABILITY OF 1E PIGTAIL EXTENSIONS SDAR: CP-86-38 (INTERIM REPORT)
Dear Mr. Johnson:
On May 27, 1986, we verbally notified your Mr. T. F. Westerman of a deficiency involving the failure of project procedures to adequately address the installation and inspection criteria for cable runs used as device pigtail extensions. This is an interim report of a potentially reportable item under the provision of 10CFR50.55(e). We have submitted an interim report logged TXX-4873, dated June 26, 1986.
We are continuing our evaluation and anticipate submitting our next report by September 12, 1986.
Very truly yours,
//
l'80 W. G. Counsil JCH/arh c - NRC Region IV (0+ 1 Copy)
Director, Inspection & Enforcement (15 copies)
U. S. Nuclear Regulatory Commission Washington, D.C.
20555 88R'188M"t85lb S
TY 0
QC s unvisms or rexan ununes ru.ecrusc coursur
. - -