TXX-4874, Interim Deficiency Rept CP-86-39 Re Dimensional Tolerances for Shims Used w/C-type Clamps on Cable Trays.Initially Reported on 860527.Electrical Raceway Items Will Be Consolidated by Ebasco Svcs.Next Rept Expected by 861021

From kanterella
(Redirected from TXX-4874)
Jump to navigation Jump to search
Interim Deficiency Rept CP-86-39 Re Dimensional Tolerances for Shims Used w/C-type Clamps on Cable Trays.Initially Reported on 860527.Electrical Raceway Items Will Be Consolidated by Ebasco Svcs.Next Rept Expected by 861021
ML20211L121
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 06/26/1986
From: Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-86-39, TXX-4874, NUDOCS 8607010509
Download: ML20211L121 (1)


Text

-

Log # TXX-4874 File # 10110 903.9 TEXAS UTILITIES GENERATING COMPANY SKYWAY MWEst . 400 NORTH OtJVE STREET. I.B. A 8 . DALLAS. TEXAS 75301 June 26, 1986 03^0h?2Y."Oh \ F j

Mr. Eric H. Johnson, Director M Division of Reactor Safety and Projects 1~- -_lUS U. S. Nuclear Regulatory Commission {

611 Ryan Plaza Drive, Suite 1000 ~

Arlington, TX 76012

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 CABLE TRAY C-TYPE CLAMP SHIM DIMENSIONS i

SDAR: CP-86-39 (INTERIM REPORT)

Dear Mr. Johnson:

On May 27, 1986, we verbally notified your Mr. T. F. Westerman of a deficiency ,

involving dimensional tolerances for the shims used in conjunction with C-Type i clamps on cable trays. This is an interim report of a potentially reportable  !

item under the provision of 10CFR50.55(e).

This issue is related to CP-85-19, Conduit Support Spans, and CP-85-34, Conduit Support Design, and these issues are being evaluated under CPRT Program Item VIII. All electrical raceway items (tray, . conduit, supports) have been consolidated under the scope of Ebasco Services. This program plan is scheduled for completion in September,1986. We are continuing our evaluation '

and anticipate submitting our next report by October 21, 1986.

i Very truly yours, )

$ Mid$b W. G. Cou s 1 By: .

G. S. Keeley Manager, NucTeam - ensing JCH/arh l c - NRC Region IV (0 + 1 Copy)