TXX-4624, Forwards 3-D Response Spectrum Analysis & Verification of Multimode Response Multiplier Equal to 1.25, Per Request During NRC 851025 Audit of Cable Tray Hanger Design Verification Program
| ML20136A684 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 11/14/1985 |
| From: | Counsil W TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | Noonan V NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM), Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML20136A689 | List: |
| References | |
| CPPA-47-527, TXX-4624, NUDOCS 8511200007 | |
| Download: ML20136A684 (1) | |
Text
I CPPA-47,527 TEXAS UTILITIES GENERATING COMPANY FN!lIhhig624 RKYWAY TOWER. 400 NORT,5 OIJVE NTREET. I.R at. DAI.LAN, TEXAN 78308 November 14, 1985 wauAM O CoWNSIL EEECuflVE VICE P4E$lOENT Director of Nuclear Reactor Regulation Attention:
Mr. Vincent S. Noonan, Director Comanche Peak Project Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.
20555
SUBJECT:
COMANCllE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 CABLE TRAY HANGER DESIGN ADEQUACY
Dear Mr. Noonan:
Enclosed is a copy of EBASCO's study on the multi-mode response multiplier used in cable tray hanger design verification activities.
This information was requested by Messrs. L. Shao and D. Jeng of your staff during the NRC audit of CPSES cable tray hanger design verification program held in EBASCO's New York office on October 25, 1985.
If there are any questions regarding the study, please contact H. A. Harrison at extension (817) 897-8691.
Very truly yours, s
W. G. Counsil WGC/
/JMD/gh cc J. W. Beck J. T. Merritt R. E. Camp C. R. Hooton (w/ attachment)
R. M. Kissinger T. Tyler (w/ attachment)
ARMS 8511200007 851114