TXX-1014, Discusses Engineering Contractor & Util Engineering Responsibilities & Organizational Structure

From kanterella
Jump to navigation Jump to search
Discusses Engineering Contractor & Util Engineering Responsibilities & Organizational Structure
ML20151Q302
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/02/1988
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
TXX-10140, NUDOCS 8808110110
Download: ML20151Q302 (2)


Text

..

9 w

i 1

_--- =

Log # TXX-88549 File # 10140 Z

Z 1UELECTRIC August 2, 1988 Wmiam G. Counsil Execusht Yko PrestJem V. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 ENGINEERING CONTRACTOR AND COMANCHE PEAK ENGINEERING (CPE) RESPONSIBILITIES AND ORGANIZATIONAL STRUCTURE Gentlemen:

As we have previously informed the NRC staff verbally, a change has been made in the structure of the SWEC organizations part of the Corrective Action Program (CAP) performing engineering functions as and, in the near future, all the engineering functions being performed by engineering contractors will be consolidated into an integrated organization managed by SWEC.

In addition, most non-safety related production engineering responsibilities have been transferred from CAP engineering contractors to TV Electric Comanche Peak Engineering (CPE). Given the advanced stage of completion of the CAP for Unit I and Common, these changes will facilitate completion of Unit I and will best provide engineering support for Unit I as an operating reactor.

This letter summarizes these changes in engineering responsibilities and organizational structure.

As described in the Project Status Reports (PSRs) and TV Electric correspondence to the NRC, the engineering contractors originally responsible f or performing the CAP for Unit I and Common were SWEC-PSAS, SWEC-CAP, Ebasco and Impell. CPE was responsible for oversight and coordination of the engineering contractor activities as well as for maintenance of the CPE design control procedures and monitoring of engineering contractors to assure that their safety-related engineering and design activities are performed in accordance with these design control procedures.

Earlier this year, SWEC-PSAS and SWEC-CAP were consolidated into a single SWEC organization, in view of the limited remaining effort to be completed within these SWEC disciplines.

The consolidated SWEC organization continues to operate under the same engineering procedures and to ut..ilize the assigned SWEC personnel.

Ih10seogog O

A 5

1

\\ \\\\

k 400 North Olive Street LB81 Dallas. Texas 7H01

s' TXX-88549 August 2, 1988 Page 2 of 2 During the third quarter of 1988, TV Electric intends to achiete a further I

consolidation of the CAP engineering contractors.

SWEC, Ebasco and Impe11 will retain their respective engineering responsibilities under CAP.

However, they will become part of an integrated functional organization nanaged by SWEC for TV Electric.

SWEC's management function will include respunsibility for managing all inter-contractor technical interfaces and for engineering schedule, cost and production support activities. All CAP engineering and I

design functions will continue to be performed utilizing existing procedures and QA programs. Thus, this consolidation will not affect in any way TV Electric's commitments as to technical procedures and methods, corrective and preventive actions or QA programs identified in the PSRs and correspondence to the NRC.

CPE will be responsible for overall design control.

SWEC's assumption of responsibility for routine management of the technical interfaces and safety-related engineering production activities will enable CPE to devote more of its resources to preparation for engineering support of Unit 1 operation.

In addition, CPE has assumed from the engineering contractors responsibility for most of the non-safety related engineering and design, excluding primarily Fire Protection, systems containing both safety related and non-safety related classifications and most Seismic Category 11 supports for systems, structures and components.

Please contact me if any additional information is required concerning these changes in responsibilities and organization.

Very truly yours, 17 1

W. G. Counsil JEK/grr c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) l l