Pages that link to "05000530/LER-2014-001"
Jump to navigation
Jump to search
The following pages link to 05000530/LER-2014-001:
Displaying 50 items.
- 05000530/LER-2015-002, Condition Prohibited by Technical Specification 3.0.4 Due to an Inoperable Atmospheric Dump Valve (ADV) (← links)
- 05000530/LER-2015-003, Damaged High Pressure Safety Injection Pump Motor Journal Bearing (← links)
- 05000530/LER-2015-004, Condition Prohibited by Technical Specifications 3.0.4 and 3.7.2 Due to an Inoperable Main Steam Isolation Valve (← links)
- 05000530/LER-2010-001 (← links)
- 05000530/LER-1998-001 (← links)
- 05000530/LER-1999-001 (← links)
- 05000530/LER-1996-001 (← links)
- 05000530/LER-1995-001 (← links)
- 05000530/LER-2001-002 (← links)
- 05000530/LER-2001-001 (← links)
- 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation (← links)
- 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation (← links)
- 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator (← links)
- 05000530/LER-2021-001-01, Reactor Trip During Control Element Assembly Alignment Activities (← links)
- 05000530/LER-2021-001, Reactor Trip During Control Element Assembly Alignment Activities (← links)
- 05000530/LER-1989-008, :on 890630,maint Personnel Identified Sixth Trip Lever Arm on 10-ton Fuel Handling Crane Rails Instead of Only Five Trip Lever Arms for Crane Interlocks.Cause Under Investigation.Sixth Level Arm Removed (← links)
- 05000530/LER-1989-006-01, :on 890606,operations Personnel Discovered That Two Required Dayshift,Shiftly Surveillances Not Performed within Required Interval.Caused by Personnel Error. Personnel Counseled (← links)
- 05000530/LER-1987-002-02, :on 870615,control Room Essential Filtration Actuation Signals & Containment Purge Isolation Actuation Signals Received on Both Channels of balance-of-plant Esfas. Cause Under Investigation (← links)
- 05000530/LER-1997-001, :on 970306,initiated Manual Fuel Bldg Essential Ventilation Actuation.Caused by Loss of Spent Fuel Pool (SPF) Level.Restored Air Pressure to Gate Seal & SPF Level Proceeded to Increase (← links)
- 05000530/LER-2020-001, Condition Prohibited by Technical Specifications Due to Inoperable Spray Pond Pump (← links)
- 05000530/LER-2018-001-01, Reactor Trip on Low Steam Generator Level (← links)
- 05000530/LER-2018-001, Reactor Trip on Low Steam Generator Level (← links)
- 05000530/LER-1998-003-02, :on 980902,discovered That MSSV as-found Lift Pressures Were Outside TS Limits.Caused by Bonding of Valve Disc to Nozzle Seat.Affected Valves Were Adjusted,Retested & Returned to Svc (← links)
- 05000530/LER-1998-003-01, Forwards LER 98-003-01 Re MSSV as-found Lift Pressures out- Side of TS Limits.Ler Suppl Provides Evaluation Findings from Unit 3 out-of-tolerance MSSVs Conditions Which Were Discovered During pre-outage Testing (← links)
- 05000530/LER-1998-002-01, Forwards LER 98-002-01,re Discovery & Correction of cross- Wired Power Supply Receptacle for B Train H Recombiner,Per 10CFR50.73 (← links)
- 05000530/LER-1998-004, Forwards LER 98-004-00 Prepared & Submitted Pursuant to 10CFR50.73.LER Reports TS Violation Due to non-compliance with TS 3.9.3 for Not Establishing Containment Penetration Isolation During Core Alterations (← links)
- 05000530/LER-1998-003, Forwards LER 98-003-00 Prepared & Submitted Per 10CFR50.73.LER Repts out-of-tolerance Condition of Several MSSV Which Were Discovered During pre-outage Testing (← links)
- 05000530/LER-1998-002-02, :on 980814,B Train H Recombiner Was Noted Inoperable Due to cross-wired Power Receptacle.Cause of Event Is Under investigation.Cross-wired Power Supply Receptacle for B Train H Recombiner Was re-wired (← links)
- 05000530/LER-1998-002, Forwards LER 98-002-00,re Discovery & Correction of cross- Wired Power Supply Receptacle for B Train H Recombiner. No New Commitments Made by Util (← links)
- 05000530/LER-1998-001-02, :on 980730,entered TS 3.0.3 Due to Safety Injection Flow Instruments Being Removed from Svc.Caused by Personnel Error.Transmitters Were Unisolated & Returned to Svc (← links)
- 05000530/LER-1993-005-02, :on 930309,CR Personnel Discovered Missed TS LCO Action & Subsequently Performed Surveillance Satisfactorily.Caused by Personnel Error.Appropriate Disciplinary Action Issued (← links)
- 05000530/LER-1997-003, :on 970215,seven Main Steam Safety Valves Were Found Out of Tolerance Prior to Refueling Outage.Safety Analysis Performed Based Upon as-found MSSV Data Which Demonstrated That MSSVs Would Perform Safety Functions (← links)
- 05000530/LER-1997-003-01, Forwards LER 97-003-01,reporting Test Results of Main Steam Safety Valve as-found Lift Settings That Were Out of Tolerance Limits Specified in TS Limiting Condition for Operation 3.7.1.1 (← links)
- 05000530/LER-1997-002-01, :on 970531,RT Occurred.Caused by Spurious Opening of All Four RT Switchgear Breakers.Independent Investigation of Event Being Conducted in Accordance W/Util Corrective Action Program (← links)
- 05000530/LER-1997-002, Forwards LER 97-002-00 Re Automatic Reactor Trip Following Spurious Opening of All Four RT Switchgear Breakers (← links)
- 05000530/LER-1996-001-02, :on 960621,inaccurate Gas Calculations for Post Accident Sampling Sys Occurred.Caused by Surveillance Test Worksheet Errors.Independent Investigation of Event Being Conducted (← links)
- 05000530/LER-1995-002-02, :on 950924,identified That Abnormal Blowdown Valves to Blowdown Flash Tank (Bft) Isolated,Resulting in Reactor Core Power Exceeding 3,800 Mwt Due to Personnel Error.Procedure for Aligning Blowdown to Bft Revised (← links)
- 05000530/LER-1995-002, Forwards LER 95-002-00 Re Condition Where Max Power Level of Facility OL Exceeded for Nine H.Highest Rolling 12 H Average 100.97 Percent Power (← links)
- 05000530/LER-1995-001-01, :on 950412,leak Identified Through Cracked Weld in Piping Near Charging Pump Suction Drain Valve.Caused by Defective Weld.Pump Weld Repaired & Returned to Svc (← links)
- 05000530/LER-1994-008, Forwards LER 94-008-00,eight Incore Instruments Found cross- Wired (← links)
- 05000530/LER-1994-007, :on 940830,reactor Trip Occurred When Steam Generator 2 Water Level Reached RPS Trip Setpoint.Caused by Component failure.FWCS-2 Master Controller Was Replaced (← links)
- 05000530/LER-1994-006, :on 940823,shutdown Cooling Loop Rendered Inoperable Due to Pump Breaker Racked Down & in Test Position.Training Provided to Licensed Operators on Procedure 40DP-9OP26, Operability. (← links)
- 05000530/LER-1994-005-01, :on 940819,reactor Trip Occurred Following Degradation of Mf Flow.Fwcs cabinets,SG-1 Economizer & MFW Pumps Quarantined & FWCS-1 Master Controller Replaced.W/ (← links)
- 05000530/LER-1994-002-01, :on 940318,13 of 20 MSSVs Setpoints Found to Be Out of Tolerance.Most Valves Exhibited Seat Wear.Valves Replaced w/pre-tested Spares & Approval to Amend TS LCO 3.7.1.1,MSSV Setpoints Received (← links)
- 05000530/LER-1994-004-01, :on 940530,LCO 3.0.3 Entered Following Determination That Secondary Pressure Boundary Leakage Existed.Caused by Defective Weld.Control Room Personnel Returned to Mode 5 & Exited LCO 3.0.3 (← links)
- 05000530/LER-1994-003, Corrected Ltr Forwarding LER 94-003-00,changing Ltr Number to 192-00892-JML/AKK/RKR.W/o LER (← links)
- 05000530/LER-1994-002, :on 940317,main Steam Safety Valve Setpoints Found Out of Tolerance.Valves Adjusted,Certified & Returned to Svc (← links)
- 05000530/LER-1993-004-01, :on 931103,reactor Manually Tripped After Recognizing That Subgroup 5 of CEA Regulating Group 4 Slipped Into Reactor Core During Reactor Power Reduction. CEA Regulating Group 4 Will Be Monitored (← links)
- 05000530/LER-1992-005-02, :on 921023,determined That 11 of 20 Main Steam Safety Valve as-found Relief Setpoints Out of TS 3.7.1.1 Tolerance from 921010-23.Possibly Caused by Setpoint Drift. Valves Will Be Removed & Shipped to Offsite Facility (← links)
- 05000530/LER-1992-005-01, Forwards LER 92-005-01 Re Main Steam Safety Valve as-found Relief Settings Out of Tolerance Limits in TS 3.7.1.1.Suppl Updates Valve Testing Schedule in Section Iii.B & Provides Main Steam & Pressurizer Safety Valve Test Res (← links)