A self-revealing finding was identified beA self-revealing finding was identified because Entergy inadequately planned and controlled work while performing reactor reassembly and reactor cavity decontamination activities during refueling outage (RFO) 30 resulting in excessive unintended occupational collective exposure that exceeded the planned dose exposure established by Radiation Work Permit (RWP) 2013-702. Inadequate work planning and control resulted in unplanned, unintended collective exposure due to conditions that were reasonably within Entergys ability to control. The work activity performance deficiencies resulted in the collective exposure for these activities increasing from the original estimate of 9.950 person-rem to an actual dose of 18.940 person-rem. Entergy entered the issues into their corrective action program. This finding is more than minor because it is associated with the program and process attribute of the Occupational Radiation Safety cornerstone and affected the cornerstone objective to ensure the adequate protection of the worker health and safety from exposure to radiation from radioactive material during routine civilian nuclear reactor operation. Additionally, the performance deficiency was determined to be more than minor based on a similar example (6.i) in Appendix E of IMC 0612, in that the actual collective dose exceeded 5 person-rem and exceeded the planned, intended dose by more than 50 percent. In accordance with IMC 0609, Appendix C, Occupational Radiation Safety Significance Determination Process, the inspectors determined that this finding is of very low safety significance (Green) because the plant\'s current three year rolling average collective dose (142.6 person-rem/reactor years for 2010 through 2012) is less than the criteria of 240 person-rem per boiling water reactor unit. The inspectors determined that this finding has a cross-cutting aspect in the Human Performance area, Work Control component, because Entergy did not implement the planned work as intended, which involved job site activities, and impacted radiological safety.ivities, and impacted radiological safety.  
23:59:59, 30 September 2013  +
05000271  +
23:59:59, 30 September 2013  +
Has query"Has query" is a predefined property that represents meta information (in form of a <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Subobject">subobject</a>) about individual queries and is provided by <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Help:Special_properties">Semantic MediaWiki</a>.
Modification date"Modification date" is a predefined property that corresponds to the date of the last modification of a subject and is provided by <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Help:Special_properties">Semantic MediaWiki</a>.
00:05:23, 21 February 2018  +
23:59:59, 30 September 2013  +
Failure to Maintain Radiation Exposure ALARA During Refueling Activities  +