ML22131A0955 May 20221 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems
ML20323A12522 October 2020Rev. 20 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems
IR 05000443/20190103 July 2019Design Bases Assurance Inspection Report 05000443/2019010
ML17310A41627 October 2017Seabrook Station Revision 18 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems
IR 05000443/201600714 December 2016Component Design Bases Inspection Report 05000443/2016007
ML16218A4555 August 2016Integrated Inspection Report 05000443/2016002
ML15278A20028 October 2015Report for the Onsite Audit Regarding Implementation of Mitgating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 (TAC Nos. MF0836 and MF0837)
ML14317A63321 October 2014Seabrook Station Updated Final Safety Analysis Report, Revision 16, Chapter 9, Auxiliary Systems
ML14171A40517 June 2014Comment (6) of James M. Petro, on Behalf of Florida Power & Light Company, on Draft Regulatory Issue Summary 2014-XX, Tornado Missile Protection.
ML13134A08526 April 2013Updated Final Safety Analysis Report, Revision 15, Chapter 9 - Auxiliary Systems
ML12102A24523 January 2012E-mail from H. Cruz, NRR to M. Murphy, NRR; Subject: Comment on Seabrook TIA Consolidated for Region I TIA Status Report
ML12102A24417 January 2012E-mail from R. Conte, Region I to H. Cruz, NRR; Subject: Comments on Seabrook TIA Consolidated for Region 1 TIA Status Report
ML12174A08613 January 2012E-mail from R. Conte, Region I to H. Cruz, NRR, Et Al; Subject: Comments on Seabrook TIA Consolidated for Region I TIA Status Report
ML12088A21915 December 2011E-mail from Holly Cruz, NRR to Robert Nelson, NRR, Et Al; Subject: Tia Status Report
ML0913304383 November 2008Seabrook - Updated Final Safety Analysis Report, Revision 12, Chapter 9, Auxiliary Systems
ML0325911459 September 2003Response to Request for Additional Information Regarding License Amendment Requests 02-06 and 02-07
Information Notice 1996-64, Modifications to Containment Blowout Panels Without Appropriate Design Controls10 December 1996Modifications to Containment Blowout Panels Without Appropriate Design Controls
ML20115H76323 October 1992Forwards Response to NRC Concern,Delineated in Re Design of Tornado Barriers & Plant Doors.Results of Review Contained in Encl Confirmed That Plant Design Capable of Withstanding DBT as Defined in Updated FSAR
ML20011D43819 December 1989LER 89-011-01:on 890905,three Unsealed Piping Penetrations in Condensate Storage Tank Encl Identified.Caused by Failure to Transfer Sealing Requirements Into Detail Drawings.Penetrations sealed.W/891219 Ltr
ML20133H90031 July 1985Safety Evaluation Report Related to the Operation of Seabrook Station,Units 1 and 2.Docket Nos. 50-443 and 50-444.(Public Service Company of New Hampshire,Et Al)
ML20070R9621 February 1983Forwards Responses to Power Sys Branch Open Items Discussed at 830110-12 & 15 Meetings.Responses Will Be Included in Amend 49 to OL Application
ML20066G72012 November 1982Forwards Revised Responses to Power Sys Branch 820212 Series 430 Requests for Addl Info.Responses Will Be Included in OL Application,Amend 48
ML20027E5079 November 1982Forwards Revision to FSAR Sections 6.4.2.2 & 9.4.1.2, Incorporating Tornado Missile Protection for Control Room Air Intakes.Revisions Will Be Included in OL Application Amend 48
ML20050D5648 April 1982Forwards Notes from Structural Engineering Branch Design Audit Conducted 820329-0402