ML22326A121 | 31 October 2022 | 4 to the Updated Final Safety Analysis Report, Chapter 15 (Part 2 of 2), Chapter 16, Chapter 17, Chapter 18, Chapter 19, Table of Contents, Rev 24 Epl |
IR 05000424/2022001 | 12 May 2022 | Integrated Inspection Report 05000424/2022001 and 05000425/2022001 |
ML21102A229 | 30 March 2021 | 3 to Updated Final Safety Analysis Report, Chapter 15, Accident Analyses (Part 2); & Chapters 16, 17, 18, 19; Table of Contents; Revision 23 to List of Effective Pages |
ML20311A344 | 6 November 2017 | 2017 Q1-Q4 ROP Inspection Findings |
ML20311A341 | 6 November 2017 | 2017 Q1-Q4 ROP Inspection Findings |
ML17032A143 | 2 November 2016 | Updated Final Safety Analysis Report, Section 15.2 Decrease in Heat Removal by the Secondary System, Redacted |
NL-16-2280, Vogtle Electric Generating Plant, Units 1 & 2, Updated Final Safety Analysis Report, Section 15.2 Decrease in Heat Removal by the Secondary System, Redacted | 2 November 2016 | Vogtle Electric Generating Plant, Units 1 & 2, Updated Final Safety Analysis Report, Section 15.2 Decrease in Heat Removal by the Secondary System, Redacted |
IR 05000424/2015004 | 29 January 2016 | NRC Integrated Inspection Report 05000424/2015004, 05000425/2015004, and 07201039/2015001, October 01, 2015 Through December 31, 2015 |
IR 05000424/2004004 | 23 July 2004 | IR 05000424-04-004, IR 05000425-04-004, on 03/28/2004 - 06/26/2004, Vogtle Electric Generating Plant; Operator Workarounds, Refueling & Outage Activities, Access Control to Radiologically Significant Areas, Event Followup & Other |
ML20057F547 | 11 October 1993 | Forwards Responses to NRC Request for Addl Info Re Alternate Min Flow Lines in High Head Safety Injection Sys |
ML20056H511 | 26 August 1993 | Forwards Request for Addl Info Re Alternate Min Flow Lines in High Head Safety Injection Sys at Plants |