Issue date | From | Title | Project stage | |
---|---|---|---|---|
NRC-13-0009, DTE Electric Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 28 February 2013 | DTE Energy Conner J | DTE Electric Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | Other |
NRC-13-0006, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 February 2013 | DTE Energy Conner J | Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
ML13182A053 | 2 July 2013 | Mahesh Chawla Plant Licensing Branch III | Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 | Approval |
NRC-13-0039, Establishment of Online Reference Portal for Review of Mitigating Strategies Submittal in Response to Order EA-12-049 | 16 July 2013 | DTE Energy Rad Z | Establishment of Online Reference Portal for Review of Mitigating Strategies Submittal in Response to Order EA-12-049 | Other |
ML13210A220 | 29 July 2013 | Scott Wall Plant Licensing Branch III | NRR E-mail Capture - Fermi 2 - Requests for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation | RAI |
NRC-13-0042, Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. | 19 August 2013 | DTE Energy Conner J | Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. | Response to RAI |
NRC-13-0043, DTE Electric Company First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 26 August 2013 | DTE Energy Conner J | DTE Electric Company First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
NRC-13-0044, DTE Electric Company'S First Six Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 26 August 2013 | DTE Energy Conner J | DTE Electric Company'S First Six Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | Other |
ML13317A894 | 20 November 2013 | Mega-Tech Services | Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Fermi Unit 2, TAC No.: MF0770 | Other |
ML13309B129 | 21 November 2013 | Thomas Wengert Plant Licensing Branch III | Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation | RAI |
ML13220A133 | 25 November 2013 | Jeremy Bowen NRC/NRR/MSD | Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies | Acceptance Review |
NRC-14-0059, DTE Electric Company Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 August 2014 | DTE Energy Kaminskas V | DTE Electric Company Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
NRC-14-0060, Third Six Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-0491) | 28 August 2014 | DTE Energy Kaminskas V | Third Six Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-0491) | Other |
NRC-15-0003, DTE Electric Company - Fermi, Unit 2 - Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 23 February 2015 | DTE Energy Kaminskas V | DTE Electric Company - Fermi, Unit 2 - Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
ML15114A445 | 5 May 2015 | Stephen Monarque Japan Lessons-Learned Division | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 | Other |
ML15245A287 | 1 October 2015 | Stephen Monarque Japan Lessons-Learned Division | Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 | Other |
NRC-16-0005, Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 20 January 2016 | DTE Energy Polson K | Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | Other |
NRC-16-0004, Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information | 20 January 2016 | DTE Energy Polson K | Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information | Response to RAI |