Semantic search
Jump to navigation
Jump to search
Issue date | From | Title | Project stage | |
---|---|---|---|---|
ML060380017 | 9 February 2006 | Stephen Monarque Plant Licensing Branch III-2 | RAI, Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized-Water Reactors. | RAI |
ML072970605 | 24 October 2007 | Dominion Bischof G T | Exigent License Amendment Request Re Alternative Containment Analysis Methodology Supporting Information - Gothic Model Input Files | Other |
ML073190553 | 15 November 2007 | Dominion Dominion Resources Services Dominion Nuclear Connecticut Dominion Energy Kewaunee Matthews W R | North Anna, Units 1 and 2, and Surry, Units 1& 2, Request for Extension of Completion Dates for Corrective Actions Regarding NRC Generic Letter 2004-02 | Request |
ML073450594 | 13 December 2007 | Siva Lingam NRC/NRR/ADRO/DORL/LPLII-1 | Approval of Extension of Completion Dates for Corrective Actions of Generic Letter 2004-02 | Other |
ML080650563 | 29 February 2008 | Dominion Bischof G T | Supplemental Response to NRC GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | Request |
ML080650562 | 29 February 2008 | Dominion Bischof G T | Supplemental Response to NRC GL-2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | Request |
ML080650314 | 29 February 2008 | Dominion Bischof G T Dominion Energy Kewaunee | Kewaunee, NRC Generic Letter 2004-02 Supplemental Response, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | Request |
ML081420793 | 21 May 2008 | Dominion Dominion Resources Services Dominion Nuclear Connecticut Bischof G T Dominion Energy Kewaunee | North Anna, Units 1 and 2, and Surry, Units 1 & 2, NRC Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Request.. | Request |
ML081430612 | 22 May 2008 | Dominion Dominion Resources Services Dominion Nuclear Connecticut Gerald Bichof | Units 1 & 2 - NRC Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-water Reactors Request for Interim. | Request |
ML081490572 | 29 May 2008 | Siva Lingam NRC/NRR/ADRO/DORL/LPLII-1 | Request for Extension of Completion Dates for Generic Letter 2004-02 Corrective Actions | Other |
ML081830247 | 1 July 2008 | Siva Lingam NRC/NRR/ADRO/DORL/LPLII-1 | Request for Extension of Completion Dates for Generic Letter 2004-02 Corrective Actions | Other |
ML082540495 | 5 September 2008 | Dominion Matthews W R | North Anna and Surry Power Station, Units 1 and 2, NRC Generic Letter (GL) 2004-02, Potential Impact of Debris Accidents at Pressurized-water Reactors Request for Extension of Completion Dates for Corrective Actions | Request |
ML082730022 | 29 September 2008 | Stang J Plant Licensing Branch II | Request for Extension of Completion Dates for Generic Letter 2004-02 Corrective Actions | Other |
ML091540954 | 18 June 2009 | Stang J Plant Licensing Branch II | Request for Additional Information Regarding Generic Letter 2004-02 Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors: Extension Approval for Surry 1 & 2 | RAI |