ML24032A025 | 5 February 2024 | NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 | |
ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule | 1 February 2024 | Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule | |
PMNS20240140, Notice of Meeting with Southern Nuclear Operating Company | 1 February 2024 | Notice of Meeting with Southern Nuclear Operating Company | |
PMNS20240141, Notice of Meeting with Southern Nuclear Operating Company | 1 February 2024 | Notice of Meeting with Southern Nuclear Operating Company | |
PMNS20240142, Notice of Meeting with Southern Nuclear Operating Company | 1 February 2024 | Notice of Meeting with Southern Nuclear Operating Company | |
PMNS20240143, Notice of Meeting with Southern Nuclear Operating Company | 1 February 2024 | Notice of Meeting with Southern Nuclear Operating Company | |
ML24010A071 | 31 January 2024 | Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) | |
ML24031A050 | 31 January 2024 | COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report | |
ML24031A610 | 31 January 2024 | Cyber Security Inspection Report 05200026/2024401 - Public | Cyber Security |
ML24025A137 | 31 January 2024 | Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 | |
ML24029A059 | 30 January 2024 | Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 | |
ML24016A113 | 30 January 2024 | Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants | |
ML24019A193 | 30 January 2024 | Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 | |
ML24040A032 | 29 January 2024 | FOIA-2024-000044 - Resp 1 - Final | |
NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 | 29 January 2024 | Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 | |
IR 05000424/2024403 | 26 January 2024 | Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 | |
ML24022A119 | 24 January 2024 | Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request | |
NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report | 22 January 2024 | Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report | |
ML23279A004 | 17 January 2024 | Amendment No. 194 to Remove Combined License Appendix C | |
ML23347A209 | 17 January 2024 | Voluntary Requests for Data, Information, And/Or Observation | |
ML24017A112 | 17 January 2024 | NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 | Cyber Security |
ML23325A202 | 16 January 2024 | CFR Part 52 Construction Lessons-Learned Report | |
ML23341A204 | 12 January 2024 | Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) | Exemption Request |
ML24012A130 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/16/2023 | |
ML24012A131 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/23/2023 | |
ML24012A132 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/26/2023 | |
ML24012A133 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/30/2023 | |
ML24012A134 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 12/11/2023 | |
ML24012A135 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/12/2023 | |
ML24012A136 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/16/2023 | |
ML24012A137 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/23/2023 | |
ML24012A138 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 10/25/2023 | |
ML24012A139 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 11/03/2023 | |
ML24012A140 | 12 January 2024 | (50-424; 50-425; 52-025; 52-026), Single Positive Test Form Collected on 12/18/2023 | |
NL-23-0926, Correction of Technical Specification Typographical Error | 12 January 2024 | Correction of Technical Specification Typographical Error | |
ML24004A219 | 8 January 2024 | Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 | |
ML23361A081 | 8 January 2024 | SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR | Incorporated by reference Condition Adverse to Quality Control of Heavy Loads |
ML24004A185 | 4 January 2024 | SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised | Incorporated by reference Condition Adverse to Quality Control of Heavy Loads |
ML23345A131 | 3 January 2024 | Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) | Exemption Request |
ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule | 2 January 2024 | Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule |