Issue date | Title | From | To | |
---|---|---|---|---|
NRC Generic Letter 1995-07 | 17 August 1995 | NRC Generic Letter 1995-007: Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves | Crutchfield D Office of Nuclear Reactor Regulation | |
ML20098B299 | 29 September 1995 | Notifies That Util Will Perform Actions & Provide Info as Requested by GL 95-07 | SOUTHERN CALIFORNIA EDISON CO. Marsh W | Office of Information Resources Management |
Information Notice 1996-05, Partial Bypass of Shutdown Cooling Flow from Reactor Vessel | 18 January 1996 | Partial Bypass of Shutdown Cooling Flow from Reactor Vessel | Crutchfield D Office of Nuclear Reactor Regulation | |
Information Notice 1996-08, Thermally Induced Pressure Locking of a High Pressure Coolant Injection Gate Valve | 5 February 1996 | Thermally Induced Pressure Locking of a High Pressure Coolant Injection Gate Valve | Crutchfield D Office of Nuclear Reactor Regulation | |
ML20097F252 | 13 February 1996 | Forwards Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves | SOUTHERN CALIFORNIA EDISON CO. Marsh W | Office of Information Resources Management |
Information Notice 1996-49, Thermally Induced Pressurization of Nuclear Power Facility Piping | 20 August 1996 | Thermally Induced Pressurization of Nuclear Power Facility Piping | Martin T Office of Nuclear Reactor Regulation | |
IR 05000361/1996010 | 13 December 1996 | Insp Repts 50-361/96-10 & 50-362/96-10 on 961021-25, 1104-08 & 1118-21.No Violations Noted.Major Areas Inspected: Licensee motor-operated Valve Program for Closure Under GL 89-10 | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) | |
Information Notice 1997-07, Problems Identified During Generic Letter 89-10 Closeout Inspections | 6 March 1997 | Problems Identified During Generic Letter 89-10 Closeout Inspections | Martin T Office of Nuclear Reactor Regulation | |
ML20205M011 | 13 April 1999 | Forwards Questions to Be Discussed in Upcoming Telcon on GL 95-07.Questions Transmitted by Fax on 990413 to J Rrainsberry of SCE | NRC (Affiliation Not Assigned) Raghavan L | NRC (Affiliation Not Assigned) |
ML20195J644 | 15 June 1999 | Forwards Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Response Requested within 30 Days of Receipt of Ltr | NRC (Affiliation Not Assigned) Raghavan L | SOUTHERN CALIFORNIA EDISON CO. Ray H |
ML20210B245 | 21 July 1999 | Forwards Response to NRC 990615 RAI Re GL 95-07, Pressure Locking & Thermal Bldg of SR Power-Operated Gate Valves, for Songs,Units 2 & 3 | SOUTHERN CALIFORNIA EDISON CO. Rainsberry J | Office of Information Resources Management |
ML032890435 | 10 October 2003 | Revised Relief Requests ASME Code Update for the Third Ten-Year Interval, Inservice Testing Program, San Onofre Nuclear Generating Station Units 2 and 3 | Southern California Edison Scherer A | Office of Nuclear Reactor Regulation Document Control Desk |