Issue date | Title | From | To | |
---|---|---|---|---|
NRC Generic Letter 1988-06 | 22 March 1988 | NRC Generic Letter 1988-006: Removal of Organization Charts from Technical Specification Administrative Control Requirements | Miraglia F Office of Nuclear Reactor Regulation | |
NRC Generic Letter 1989-04 | 3 April 1989 | NRC Generic Letter 1989-004: Guidance on Developing Acceptable Inservice Testing Programs | Varga S Office of Nuclear Reactor Regulation | |
ML20246E017 | 4 August 1989 | Change 1 to Rev 6 of Pump & Valve Inservice Test Plan | LOUISIANA POWER & LIGHT CO. | |
ML19325E468 | 31 October 1989 | Summary of Change 2 to Rev 6 to Pump & Valve Inservice Test Plan. | LOUISIANA POWER & LIGHT CO. | |
W3P90-1513, Forwards Supplemental Info for Rev 6,Change 1 to Inservice Testing Program Re Pumps & Valves.Info Revises Relief Requests 2.1.4,2.1.5 & 3.1.56.Relief Request 2.1.4 Has Been Withdrawn | 10 January 1991 | Forwards Supplemental Info for Rev 6,Change 1 to Inservice Testing Program Re Pumps & Valves.Info Revises Relief Requests 2.1.4,2.1.5 & 3.1.56.Relief Request 2.1.4 Has Been Withdrawn | Entergy INC. Burski R | Office of Information Resources Management |
ML20082N371 | 3 September 1991 | Forwards Rev 7,Change 1 of Waterford 3 Pump & Valve Inservice Test (IST) Plan, Per Generic Ltr 89-04.Rev 7, Change 1 of IST Plan Contains Specific Relief Requests for Deviations from ASME Code IST Requirements | Entergy INC. Burski R | Office of Information Resources Management |
ML031140549 | 7 November 1991 | Withdrawn NRC Generic Letter 1991-018: Information to Licensees Regarding Two NRC Inspection Manual Sections on Resolution of Degraded and Nonconforming Conditions and on Operability | Partlow J Office of Nuclear Reactor Regulation | |
ML20086S644 | 26 December 1991 | Responds to NRC Audit Rept of Effectiveness of Licensed Activites Re Performance of safety-related Check Valves. Responses Include Implementation Schedules for Recommended Actions,As Requested in NRC Audit Rept | Entergy INC. Burski R | Office of Information Resources Management |
ML20127D099 | 11 January 1993 | Forwards SE of IST Program Relief Request Re high-pressure Safety Injection Pump Discharge Check Valves at Plant.Util 910903 Proposal Acceptable for Implementation Per 10CFR50.55a(f)(iv) & Relief Not Required | Office of Nuclear Reactor Regulation Wigginton D | Entergy INC. Barkhurst R |
ML20127D136 | 11 January 1993 | Safety Evaluation Re IST Program Request for Relief.Util Proposal Complies W/Requirements of Later Edition of ASME Code.Approval to Use Applicable Portion of Later Edition Acceptable | Office of Nuclear Reactor Regulation | |
Information Notice 1993-13, Undetected Modification of Flow Characteristics in High Pressure Safety Injection System | 16 February 1993 | Undetected Modification of Flow Characteristics in High Pressure Safety Injection System | Grimes B Office of Nuclear Reactor Regulation | |
ML20056F203 | 19 August 1993 | Forwards Rev 7,Change 4 of Waterford Unit 3 IST Plan for Pumps & Valves, Consisting of Revised Relief Requests in Response to NRC SE of Rev 7,Change 1 of IST Plan, | Entergy INC. Burski R | Office of Information Resources Management |
ML20058P449 | 15 December 1993 | Summary of 931206 Meeting W/Entergy Operations,Inc in Rockville,Md Re 931021 Submittal of Proposed Alternative to 10CFR50.55a(f) & (g),10-Year Inservice Insp & Inservice Testing Update. List of Attendees Encl | Office of Nuclear Reactor Regulation Oconner P | Office of Nuclear Reactor Regulation |
ML20096B393 | 5 January 1996 | Responds to NRC 951113 RAI Re Update of Isi/Ist Programs | Entergy INC. Dewease J | Office of Information Resources Management |
ML20107F561 | 17 April 1996 | Safety Evaluation Providing Guidance on Submitting plant- Specific Info W/Respect to IST Program Alternatives Request | Office of Nuclear Reactor Regulation | |
NRC Generic Letter 1996-05 | 18 September 1996 | NRC Generic Letter 1996-005: Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves | Martin T Office of Nuclear Reactor Regulation | |
ML20132G077 | 19 December 1996 | Insp Rept 50-382/96-13 on 961013-1130.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) | |
ML20212A945 | 23 October 1997 | Retracts Relief Request 3.1.73 as Relief Is Not Necessary. Submits Revised Relief Request 3.1.74 in Order to Correct Info for Current 10-year IST Plan & Describe Why Waterford 3 Believes SI-107A(B) Are Currently Acceptable | Entergy INC. Ewing E | Office of Information Resources Management |
ML20202C291 | 1 December 1997 | Rev 0 to Pump & Valve Inservice Test Plan for Second 10-Yr Interval. Page 23 of Incoming Submittal Not Included | Entergy INC. | |
ML20216J794 | 15 April 1998 | Informs of Review Being Conducted of Second 10-yr Interval Inservice Testing Program & Associated Requests for Relief for Facility,Submitted on 971201.Response to Encl RAI Requested within 60 Days | Chandu Patel NRC (Affiliation Not Assigned) | Entergy INC. Dugger C |
ML20249A791 | 15 June 1998 | Forwards Info Re 980415 RAI to Assist in Review of IST Program & Associated Requests for Relief.Suppl Info Will Be Provided Re Item 3 within 30 Days | Entergy INC. Ewing E | Office of Information Resources Management |
ML20236P938 | 15 July 1998 | Submits Response to Item 3 on NRC 980415 RAI Re Second 10 Yr Interval IST Program & Includes Necessary Revisions to Associated Relief Requests | Entergy INC. Ewing E | Office of Information Resources Management |
CNRO-2007-00044, Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan | 30 November 2007 | Unit 1 and Arkansas Nuclear One, Units 1 & 2 - Inservice Testing Plan | Entergy Ford B | Office of Nuclear Reactor Regulation Document Control Desk |
ML080930176 | 10 June 2008 | Approval of Relief Requests for 10 Year Updates to the 120 Month Inservice Testing Intervals | NRC/NRR/ADRO/DORL/LPLIV Hiltz T | Entergy |
W3F1-2017-0075, Submittal of the Inservice Testing Plan for the Fourth 10-Year Interval | 4 December 2017 | Submittal of the Inservice Testing Plan for the Fourth 10-Year Interval | Entergy Jarrell J | Office of Nuclear Reactor Regulation Document Control Desk |