ML22175A08611 October 2023Preliminary Safety Evaluation Report for the HI-STORM 100 Cask System, Certificate of Compliance No. 1014, Amendment No. 17Aging Management
ML23135A75920 July 2023Shielding Topical Draft SE
ML23068A45529 June 202370. Final Safety Evaluation Report for Renewed Certificate of Compliance No. 1014, Amendment Nos. 0-15Incorporated by reference
Aging Management
License Renewal
Control of Heavy Loads
Fuel cladding
ML22098A30331 January 2023Preliminary Safety Evaluation Report for the HI-STORM 100 Cask System, Certificate of Compliance No. 1014 Renewal, Docket No. 72-1014Incorporated by reference
Aging Management
License Renewal
Control of Heavy Loads
Fuel cladding
ML22217A0177 November 2022Safety Evaluation Report on Exemption Request for Holtec Decommissioning International, LLC Indian Point Energy Center ISFSIExemption Request
ML21118A86313 May 2021Issuance of Certificate of Compliance No. 1014, Amendment No. 15 for the HI-STORM 100 Multipurpose Canister Storage System
ML19295C57626 November 2019Enclosure 6: CoC 1014, Amendment No. 14, Final Safety Evaluation ReportFuel cladding
ML19120A06425 September 2019Reference 6: Preliminary CoC 1014 Amendment No. 14 SER (Memorandum to J. Cai User Need for Rulemaking for the Holtec HI-STORM 100 Cask System, Amendment No. 14)Fuel cladding
ML19099A30115 April 2019Enclosure 6: CoC 1014, A13, Final SER (Letter to K. Manzione Issuance of Certificate of Compliance No. 1014, Amendment No. 13 for the HI-STORM 100 Multipurpose Canister Cask System (Dkt. 72-1014, CAC: 001028, EPID: L-2018-LLA-0202)Fuel cladding
ML18351A17814 February 2019Reference 6: Preliminary CoC 1014 Amendment 13 SERFuel cladding
ML18087A06228 November 2018Enclosure 6: Preliminary CoC 1014 Amendment 12 SER (Memorandum to K. Morgan-Butler User Need for Rulemaking for the Holtec Hi-Storm 100 Cask System, Amendment No. 12)Tornado Missile
Nondestructive Examination
Finite Element Analysis
Fuel cladding
ML18141A56728 November 2018Enclosure 6: Preliminary CoC 1014 Amendment 11 SER (Memorandum to K. Morgan-Butler User Need for Rulemaking for the Holtec HI-STORM 100 Cask System, Amendment No. 11)Control of Heavy Loads
Fuel cladding
ML17298A1352 February 2018Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005)Time to boil
Exemption Request
Fuel cladding
ML18045A08725 January 2018Draft Safety Evaluation for Revised Emergency Plan at Vermont Yankee to Reflect ISFSI-only ConfigurationExemption Request
Earthquake
Fuel cladding
Fire Watch
ML17335A50515 December 2017Enclosusafety Evaluation by the Office of Nuclear Material Safety and Safeguards Entergy Nuclear Operations, Inc. Vermont Yankee Nuclear Power StationCyber Security
ML17054C78826 May 2017Safety Evaluation Report for Exemption Request for Entergy Nuclear Operations, Inc.'S Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage InstallationExemption Request
ML17158B37514 January 2016Safety Evaluation for the Request for 10 CFR 20.2002 Alternate Disposal Approval, Vermont Yankee Nuclear Power StationExemption Request
ML11077049521 March 2011Supplemental Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power StationFire Barrier
Coatings
Nondestructive Examination
Aging Management
EVT-1
ML11059113128 February 2011(Vynp) SER Supplement 2 for ACRS ReviewFire Barrier
Coatings
Nondestructive Examination
Aging Management
EVT-1
ML09274056730 September 2009NUREG-1907, Supp 1, Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power Station.Finite Element Analysis
Aging Management
ML09120016231 May 2009Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power Station Supplement 1Finite Element Analysis
Aging Management
ML0833001297 January 2009Issuance of Amendment Control Rod SystemsShutdown Margin
Anticipated operational occurrence
Scram Discharge Volume
ML08072063929 February 2008Compare Vermont Yankee SER with Hole (Dec 2007) to Vermont Yankee FSER (Feb 2008)
ML07089063830 March 2007Safety Evaluation Report with Confirmatory Items Related to the License Renewal of Vermont Yankee Nuclear Power Station
ML0530101672 November 2005Vermont Yankee Nuclear Power Station - Safety Evaluation Revision 1 - Extended Power UprateSafe Shutdown
High winds
Shutdown Margin
Safety Limit Minimum Critical Power Ratio
Ultimate heat sink
Non-Destructive Examination
Mission time
Fire Barrier
Anticipated operational occurrence
Time to boil
Safe Shutdown Earthquake
Internal Flooding
Hydrostatic
Coatings
Nondestructive Examination
Channel-control blade interference
Significance Determination Process
Feedwater Controller Failure
Large early release frequency
MELLLA
Severe Accident Management Guideline
Earthquake
Power-Operated Valves
Hardened vent
Turbine Missile
Fuel cladding
Liquid penetrant
Fire Protection Program
Flow Induced Vibration
Coast down
GOTHIC
Power Uprate
Overspeed trip