Semantic search
Jump to navigation
Jump to search
Start date | Status | Title | Request type | Estimated NRC review hours | Topic | |
---|---|---|---|---|---|---|
EPID:L-2023-LLL-0004 | 18 January 2023 | Approved Closed | Quality Assurance Program Manual Reduction in Commitment | LLL | ||
EPID:L-2021-LLA-0192 | 18 October 2021 | Approved Closed | Propose Change to Eliminate Selected Response Time Testing for Reactor Protection System and Primary Containment Isolation Instrumentation | License Amendment | ||
EPID:L-2021-LLA-0121 | 3 August 2021 | Approved Closed | TSTF-554 | License Amendment | ||
EPID:L-2021-LLA-0169 | 30 June 2021 | Approved Closed | TSTF-541 | License Amendment | ||
EPID:L-2021-LLA-0110 | 12 June 2021 | Approved Closed | Emergency License Amendment Request, One Time Extension of Condition a to TS 3.5.1, TS 3.6.1.9, and TS 3.6.4.1 Completion Time to Support Residual Heat Removal (RHR) Pump Motor Replacement | License Amendment | ||
EPID:L-2021-LLA-0088 | 14 May 2021 | Approved Closed | TSTF-264 | License Amendment | ||
EPID:L-2021-LLA-0076 | 16 April 2021 | Approved Closed | TSTF-582 | License Amendment | ||
EPID:L-2021-LLE-0014 | 3 March 2021 | Withdrawn Closed | Exemption Request | |||
EPID:L-2020-LLA-0269 | 11 December 2020 | Approved Closed | TSTF-457 | License Amendment | ||
EPID:L-2020-LLA-0268 | 11 December 2020 | Approved Closed | TSTF-545 | License Amendment | ||
EPID:L-2020-LLE-0197 | 8 December 2020 | Approved Closed | Exemption Request | |||
EPID:L-2021-LLA-0142 | 24 November 2020 | Approved Closed | TSTF-505 | License Amendment | ||
EPID:2020 | 17 September 2020 | Approved Closed | License Amendment Request - Proposed Changes to Emergency Plan | |||
EPID:L-2020-LLA-0143 | 30 June 2020 | Approved Closed | TSTF-478 | License Amendment | ||
EPID:L-2020-LLA-0145 | 30 June 2020 | Approved Closed | License Amendment Request: Application to Modify Technical Specifications 3.6.1.3, Primary Containment Isolation Valves | License Amendment | ||
EPID:L-2021-LLM-0000 | 22 June 2020 | Approved Closed | Order Extending the Effectiveness of the Approval of the Transfer of the License for the Zion Nuclear Power Station from Zionsolutions, LLC to Exelon Generation Company, LLC | License Transfer | ||
EPID:L-2020-LLA-0077 | 13 April 2020 | Approved Closed | TSTF-566 | License Amendment | ||
EPID:L-2019-LRO-0049 | 11 February 2020 | Approved Closed | LRO | |||
EPID:L-2020-LLR-0011 | 24 January 2020 | Approved Closed | Letters to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI | Relief Request | 80 hours3.333 days <br />0.476 weeks <br />0.11 months <br /> | |
EPID:L-2020-LLA-0008 | 23 January 2020 | Approved Closed | TSTF-568 | License Amendment | ||
EPID:L-2019-LLQ-0003 | 5 December 2019 | Approved Closed | Request for Approval of Change to Quality Assurance Topical Report | LLQ | ||
EPID:L-2019-LLA-0214 | 2 October 2019 | Withdrawn Closed | Emergency License Amendment Request: One Time Extension to the TS 3.8.1 Action A.3 Completion Time for an Inoperable Offsite Source | License Amendment | ||
EPID:L-2019-LLA-0205 | 26 September 2019 | Approved Closed | TSTF-372 | License Amendment | 175 hours7.292 days <br />1.042 weeks <br />0.24 months <br /> | |
EPID:L-2019-LLE-0020 | 10 September 2019 | Approved Closed | Exemption Request | 300 hours12.5 days <br />1.786 weeks <br />0.411 months <br /> | ||
EPID:L-2019-LLA-0197 | 5 September 2019 | Approved Closed | License Amendment Request - Proposed Change to the Technical Specifications to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation | License Amendment | 750 hours31.25 days <br />4.464 weeks <br />1.027 months <br /> | |
EPID:L-2019-LLA-0185 | 28 August 2019 | Approved Closed | License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions | License Amendment | 175 hours7.292 days <br />1.042 weeks <br />0.24 months <br /> | |
EPID:L-2019-LLA-0190 | 13 August 2019 | Withdrawn Closed | JAF-CALC-NBI-00206 Setpoint Calculation for Vessel Lo-Lo Lvl Primary Containment Isolation Function (02-3LT-58A,B and 02-3STU-259A,B) | License Amendment | 975 hours40.625 days <br />5.804 weeks <br />1.336 months <br /> | |
EPID:L-2019-LLA-0171 | 8 August 2019 | Approved Closed | TSTF-551 | License Amendment | 500 hours20.833 days <br />2.976 weeks <br />0.685 months <br /> | |
EPID:L-2019-LLA-0132 | 27 June 2019 | Approved Closed | TSTF-427 | License Amendment | 150 hours6.25 days <br />0.893 weeks <br />0.205 months <br /> | |
EPID:L-2019-LLA-0134 | 26 June 2019 | Approved Closed | Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls | License Amendment | 250 hours10.417 days <br />1.488 weeks <br />0.342 months <br /> | |
EPID:L-2019-LLA-0021 | 1 February 2019 | Approved Closed | TSTF-564 | License Amendment | 280 hours11.667 days <br />1.667 weeks <br />0.384 months <br /> | |
EPID:L-2018-LLA-0483 | 29 November 2018 | Approved Closed | License Amendment Request: Proposed Change to the Technical Specifications to Remove Ultimate Heat Sink Bar Rack Heaters from Technical Specifications | License Amendment | 250 hours10.417 days <br />1.488 weeks <br />0.342 months <br /> | |
EPID:L-2018-LLA-0297 | 1 November 2018 | Approved Closed | TSTF-439 | License Amendment | 225 hours9.375 days <br />1.339 weeks <br />0.308 months <br /> | |
EPID:L-2018-LLA-0266 | 2 October 2018 | Approved Closed | License Amendment Request - Reactivity Anomalies Surveillance | License Amendment | 220 hours9.167 days <br />1.31 weeks <br />0.301 months <br /> | |
EPID:L-2018-LLR-0103 | 26 July 2018 | Approved Closed | End of Interval Relief Request Associated with the Fourth Ten-Year Lnservice Inspection (ISI) Interval | Relief Request | 260 hours10.833 days <br />1.548 weeks <br />0.356 months <br /> | |
EPID:L-2018-LLR-0076 | 10 July 2018 | Withdrawn Closed | ASME Code Case N-879 | Relief Request | ||
EPID:L-2018-LLA-0146 | 17 May 2018 | Approved Closed | James A. Fitzpatrick, Unit 1, License Amendment Request - Safety Limit Minimum Critical Power Ration Change | License Amendment | ||
EPID:L-2018-LLA-0240 | 10 May 2018 | Approved Closed | License Amendment Request for Approval of Changes to Emergency Plan Staffing Requirements | License Amendment | 325 hours13.542 days <br />1.935 weeks <br />0.445 months <br /> | |
EPID:L-2018-LLA-0167 | 14 February 2018 | Approved Closed | TSTF-546, TSTF-546 | License Amendment | ||
EPID:L-2018-LLA-0032 | 31 January 2018 | Approved Closed | License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors | License Amendment | 240 hours10 days <br />1.429 weeks <br />0.329 months <br /> | |
EPID:L-2017-LLA-0237 | 12 December 2017 | Approved Closed | License Amendment | |||
EPID:L-2017-LLR-0134 | 1 November 2017 | Withdrawn Closed | County, Nine Mile Point, Oyster Creek, Quad Cities, Submittal of Relief Request for an Alternative to the ASME Code - Revise Main Steam Isolation Valve Partial Stroke Testing Frequency | Relief Request | 200 hours8.333 days <br />1.19 weeks <br />0.274 months <br /> | |
EPID:L-2017-LLA-0311 | 2 October 2017 | Approved Closed | TSTF-542 | License Amendment | ||
EPID:L-2017-LLA-0313 | 27 September 2017 | Approved Closed | License Amendment Request to Relocate the Reactor Coolant System Pressure Isolation Valve Table from the Technical Specifications to the Technical Requirements Manual | License Amendment | ||
CAC:MG0239 | 14 September 2017 | Approved Closed | 350 hours14.583 days <br />2.083 weeks <br />0.479 months <br /> | |||
CAC:MF7829 | 29 August 2017 | Approved Closed | ||||
CAC:MG0026 | 31 July 2017 | Approved Closed | ||||
CAC:MF9819 | 7 June 2017 | Approved Closed | 120 hours5 days <br />0.714 weeks <br />0.164 months <br /> | |||
CAC:MF9722 | 23 May 2017 | Approved Closed | 40 hours1.667 days <br />0.238 weeks <br />0.0548 months <br /> | |||
CAC:MF9692 | 4 May 2017 | Approved Closed | 100 hours4.167 days <br />0.595 weeks <br />0.137 months <br /> |