 Start dateStatusTitleRequest typeEstimated NRC review hoursTopic
EPID:L-2023-LLA-005820 April 2023OpenLicense Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems RequirementsLicense Amendment
EPID:L-2023-LLA-005719 April 2023OpenTSTF-505License Amendment
EPID:L-2023-LLR-001913 April 2023OpenApplication for Extension Relief Request RV-1 for Thermal Relief ValvesRelief Request
EPID:L-2023-LRM-00236 April 2023OpenApril 6, 2023 Presubmittal Meeting Presentation - Extension Request for Thermal Relief Valves (EPID: L?2023?LRM-0023)LRM
EPID:L-2023-LRM-00159 March 2023OpenSummary of March 28, 2023, Presubmittal Meeting with Vistra Operations Company LLC to Discuss Proposed LAR to Take Exception to RG 1.81, Rev. 1, Shared Emergency and Shutdown Electric Systems for Multi-Unit Nuclear Power Plants,LRM
EPID:L-2022-LLA-017021 November 2022Open(CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical SpecificationsLicense Amendment
EPID:L-2022-LLA-017121 November 2022OpenApplication to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002License Amendment
EPID:L-2022-LRO-01443 November 2022Approved
Closed
(CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day ReportLRO
EPID:L-2022-LLR-005820 July 2022Open(CPNPP) - Relief Request Application P-1, Inservice Testing (IST)Relief Request
EPID:L-2022-LRO-00655 May 2022Approved
Closed
(CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day ReportLRO
EPID:L-2022-LRO-00151 February 2022OpenLRO
EPID:L-2022-LLR-00024 January 2022Open(CPNPP) - ASME OM Inservice Test Program Relief Request SNB-3, Snubber Inservice Program Third Internal ExtensionRelief Request
EPID:L-2021-NFO-001329 September 2021OpenNFO
EPID:L-2021-LLQ-000324 August 2021Approved
Closed
Quality Assurance Program Internal Audit FrequencyLLQ
EPID:L-2021-LLA-013427 July 2021Approved
Closed
TSTF-577License Amendment
EPID:L-2021-LLA-008511 May 2021Approved
Closed
TSTF-505License Amendment
EPID:L-2021-LLR-00254 May 2021OpenRelief Request
EPID:L-2020-LLA-014723 April 2021Approved
Closed
TSTF-569License Amendment
EPID:L-2021-LLE-002821 April 2021Approved
Closed
One-Time Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, IV.F.2.b and IV.F.2.cExemption Request
EPID:L-2021-LLE-002416 April 2021Approved
Closed
Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section VI, Subsection A.7 and Subsection C.3.(L)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 PHEExemption Request
EPID:L-2021-LRM-003525 March 2021OpenLRM
EPID:L-2021-LRM-003925 March 2021OpenLRM
EPID:L-2020-LLA-011624 February 2021Approved
Closed
License Amendment
EPID:L-2020-LLE-023616 December 2020Approved
Closed
Exemption Request
EPID:L-2021-LLE-000911 December 2020Approved
Closed
Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty ProgramsExemption Request
EPID:L-2020-LLE-023510 December 2020Approved
Closed
(CPNPP) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(l) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 PandemicExemption Request
EPID:L-2020-LRM-010028 October 2020OpenLRM
EPID:L-2020-LLR-010631 August 2020Open(CPNPP) - Inservice Test (IST) Program Request to Use Later Code EditionRelief Request
EPID:L-2020-LLA-019631 August 2020Approved
Closed
TSTF-567License Amendment
EPID:L-2020-LLR-010217 August 2020OpenRelief Request
EPID:L-2020-LLR-009611 August 2020Approved
Closed
Relief Request
EPID:L-2020-LRO-00483 August 2020OpenLRO
EPID:L-2020-LLA-02503 August 2020Approved
Closed
TSTF-425License Amendment
EPID:L-2020-LLA-013417 July 2020Approved
Closed
TSTF-577License Amendment
EPID:L-2020-LLR-009214 July 2020Approved
Closed
Relief Request 1A3-2, Inservice Inspection (Isi), Table 1Relief Request
EPID:L-2020-LLR-009514 July 2020Approved
Closed
Relief Request SNB-1, Snubber TestingRelief Request
EPID:L-2020-LLA-013724 June 2020Approved
Closed
TSTF-425License Amendment
EPID:L-2020-LRM-003122 June 2020OpenTSTF-505LRM
EPID:L-2019-LRO-01044 June 2020Approved
Closed
LRO
EPID:L-2020-LLE-006129 May 2020OpenExemption Request
EPID:L-2020-LLA-007213 April 2020Approved
Closed
License Amendment
EPID:L-2020-LLR-006010 April 2020Approved
Closed
Snubber Testing and Snubber Visual Examinations Relief RequestRelief Request
EPID:L-2020-LLR-00639 April 2020Approved
Closed
Reactor Vessel Head, Bottom Mounted Instrumentation, and Hot Leg Ultrasonic Testing Examinations Relief RequestRelief Request
EPID:L-2020-LLR-00629 April 2020Approved
Closed
Relief Request
EPID:L-2020-LLR-00597 April 2020Approved
Closed
Inservice Inspection (ISI) and Inservice Testing (IST) Program Relief RequestsRelief Request
EPID:L-2020-LRM-00286 April 2020OpenLRM
EPID:L-2020-LLA-005930 March 2020Approved
Closed
Revision to Technical Specifications 3.8.1, AC Sources - OperatingLicense Amendment
EPID:L-2020-LLR-009328 March 2020Approved
Closed
Relief Request I4R-23 Associated with Pandemic Related Issues - Examination of Containment Surfaces Requiring Augmented Examination (Category E-C)Relief Request
EPID:L-2017-CRS-006324 March 2020OpenSchedule Change to Open Phase Condition Detection ImplementationCRS
EPID:L-2019-LLA-025914 February 2020Approved
Closed
License Amendment