EPID - L-2022-LRO-0065, (CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day Report (Approved, Closed) 5 May 2022 - 15 November 2022 | |
---|---|
Request for: - LRO Approved, Closed | |
Initiation
| |
From: | |
MONTHYEARCP-202200200, (CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day Report2022-05-0505 May 2022
[table view]Title: (CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day Report ML22220A1942022-08-0808 August 2022 Title: NRR E-mail Capture - Comanche Peak Unit 2 - Draft Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing ML22230B1092022-08-17017 August 2022 Title: NRR E-mail Capture - Comanche Peak Unit 2 - Request for Additional Information - 2RE19 Inspection Summary Report for Steam Generator Tubing CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 Title: (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report ML22319A0732022-11-15015 November 2022 Title: Review of the Fall 2021 Steam Generator Tube Inspection Report 2022-08-17 |