BYRON 2023-0012, Cycle 26 Core Operating Limits Report | 16 March 2023 | Cycle 26 Core Operating Limits Report | Shutdown Margin |
ML22181A049 | 30 June 2022 | Core Operating Limits Report (COLR) for Byron Unit 1 Cycle 25 | Shutdown Margin |
BYRON 2022-0039, Core Operating Limits Report (COLR) for Byron Unit 2 Cycle 24 | 30 June 2022 | Core Operating Limits Report (COLR) for Byron Unit 2 Cycle 24 | Shutdown Margin |
BYRON 2022-0028, Cycle 24 Core Operating Limits Report | 28 April 2022 | Cycle 24 Core Operating Limits Report | Shutdown Margin |
BYRON 2021-0064, Cycle 25 Core Operating Limits Report | 28 September 2021 | Cycle 25 Core Operating Limits Report | Shutdown Margin |
BYRON 2020-0067, Cycle 22 Core Operating Limits Report | 20 October 2020 | Cycle 22 Core Operating Limits Report | Shutdown Margin |
BYRON 2020-0015, Cycle 24 Core Operating Limits Report | 17 March 2020 | Cycle 24 Core Operating Limits Report | Shutdown Margin |
BYRON 2019-0040, Cycle 22 Core Operating Limits Report | 15 April 2019 | Cycle 22 Core Operating Limits Report | Shutdown Margin |
BYRON 2019-0015, Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report | 7 March 2019 | Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report | Shutdown Margin |
BYRON 2018-0096, Cycle 23 Core Operating Limits Report | 17 September 2018 | Cycle 23 Core Operating Limits Report | Shutdown Margin |
BYRON 2017-0098, Cycle 21 Core Operating Limits Report | 9 October 2017 | Cycle 21 Core Operating Limits Report | Shutdown Margin |
BYRON 2017-0017, Cycle 22 Core Operating Limits Report | 9 March 2017 | Cycle 22 Core Operating Limits Report | Shutdown Margin |
BYRON 2016-0035, Cycle 20 Core Operating Limits Report | 26 April 2016 | Cycle 20 Core Operating Limits Report | Shutdown Margin |
BYRON 2015-0103, Cycle 21 Core Operating Limits Report | 22 September 2015 | Cycle 21 Core Operating Limits Report | Shutdown Margin |
RS-14-118, Annual 1 0 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors | 7 April 2014 | Annual 1 0 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors | |
BYRON 2014-0002, Cycle 19 and Unit 2 Cycle 18 Core Operating Limits Report for Measurement Uncertainty Recapture (Mur) Power Uprate | 13 February 2014 | Cycle 19 and Unit 2 Cycle 18 Core Operating Limits Report for Measurement Uncertainty Recapture (Mur) Power Uprate | Shutdown Margin |
BYRON 2013-0051, Cycle 18 Core Operating Limits Report | 15 April 2013 | Cycle 18 Core Operating Limits Report | Shutdown Margin |
BYRON 2012-0104, Cycle 19 Core Operating Limits Report | 20 September 2012 | Cycle 19 Core Operating Limits Report | Shutdown Margin |
BYRON 2011-0139, Cycle 17 Core Operating Limits Report | 29 September 2011 | Cycle 17 Core Operating Limits Report | Shutdown Margin |
BYRON 2011-0093, Inservice Inspection Summary Report for Refueling Outage 17 | 14 July 2011 | Inservice Inspection Summary Report for Refueling Outage 17 | Nondestructive Examination |
BYRON 2011-0059, Submittal of Cycle 18 Core Operating Limits Report, Revision 7 | 7 April 2011 | Submittal of Cycle 18 Core Operating Limits Report, Revision 7 | Shutdown Margin |
BYRON 2010-0040, Cycle 16 Core Operating Limits Report | 3 May 2010 | Cycle 16 Core Operating Limits Report | Shutdown Margin |
BYRON 2009-0107, Cycle 17 Core Operating Limits Report | 30 September 2009 | Cycle 17 Core Operating Limits Report | Shutdown Margin |
BYRON 2008-0108, Cycle 15 Core Operating Limits Report | 16 October 2008 | Cycle 15 Core Operating Limits Report | Shutdown Margin |
BYRON 2008-0031, Cycle 16 Core Operating Limits Report | 4 April 2008 | Cycle 16 Core Operating Limits Report | Shutdown Margin |
BYRON 2007-0050, Cycle 14 Core Operating Limits Report | 17 April 2007 | Cycle 14 Core Operating Limits Report | Shutdown Margin |
BYRON 2007-0014, Cycle 15 Core Operating Limits Report, Revision 4 | 23 January 2007 | Cycle 15 Core Operating Limits Report, Revision 4 | Shutdown Margin |
BYRON 2006-0108, Cycle 15 Core Operating Limits Report | 20 September 2006 | Cycle 15 Core Operating Limits Report | Shutdown Margin |
ML060050342 | 3 January 2006 | Steam Generator Eddy Current Inspection Report, Cycle 12 Refueling Outage. Attachment C - Attachment D.1, Pages 24 Through 31 | |
BYRON 2006-0007, Steam Generator Eddy Current Inspection Report, Cycle 12 Refueling Outage. Attachment B - Attachment B.5, Pages 17 Through 22 | 3 January 2006 | Steam Generator Eddy Current Inspection Report, Cycle 12 Refueling Outage. Attachment B - Attachment B.5, Pages 17 Through 22 | |
ML060050340 | 3 January 2006 | Steam Generator Eddy Current Inspection Report, Cycle 12 Refueling Outage. Attachment B.6 Page 23 | |
ML060050336 | 5 December 2005 | Steam Generator Eddy Current Inspection Report, Cycle 12 Refueling Outage. Pages 1 Through 16 | |
BYRON 2005-0119, Cycle 13 Core Operating Limits Report | 7 October 2005 | Cycle 13 Core Operating Limits Report | Shutdown Margin |
BYRON 2005-0037, Cycle 14 Core Operating Limits Report | 23 March 2005 | Cycle 14 Core Operating Limits Report | Shutdown Margin |
BYRON 2004-0036, Issuance of Core Operating Limits Report, Cycle 12 | 5 April 2004 | Issuance of Core Operating Limits Report, Cycle 12 | Shutdown Margin |
BYRON 2003-0093, Issuance of Core Operating Limits Report for Byron Unit One Cycle 13 | 7 October 2003 | Issuance of Core Operating Limits Report for Byron Unit One Cycle 13 | Shutdown Margin |
BYRON 2003-0079, to Byron, Unit 1 Cycle 12, Core Operating Limits Report and Revision1 to Byron, Unit 2 Cycle 11, Core Operating Limits Report | 28 August 2003 | to Byron, Unit 1 Cycle 12, Core Operating Limits Report and Revision1 to Byron, Unit 2 Cycle 11, Core Operating Limits Report | Shutdown Margin |
BYRON 2002-0100, Cycle 11 Core Operating Limits Report | 27 September 2002 | Cycle 11 Core Operating Limits Report | Shutdown Margin |
BYRON 2002-0074, Cycle 12 Core Operating Limits Report, Revision 2 | 6 August 2002 | Cycle 12 Core Operating Limits Report, Revision 2 | Shutdown Margin |
BYRON 2002-0023, Revision 3 to Cycle 11A Core Operating Limits Report | 27 February 2002 | Revision 3 to Cycle 11A Core Operating Limits Report | Shutdown Margin |