UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 12, 2023 IN RESPONSE, PLEASE REFER TO: M231212A MEMORANDUM FOR: Jody C. Martin, Director Office of Commission Appellate Adjudication FROM: Tomas E. Herrera, Acting Secretary ~ ~ [ _~

SUBJECT:

STAFF REQUIREMENTS -AFFIRMATION SESSION, 9:55 A.M.,

TUESDAY, DECEMBER 12, 2023, COMMISSIONERS' CONFERENCE ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE)

I. SECY-23-0097 - KAIROS POWER LLC (HERMES TEST REACTOR CONSTRUCTION PERMIT APPLICATION), DOCKET NO. 50-7513-CP, MANDATORY HEARING DECISION The Commission approved a Memorandum and Order addressing the required findings of 10 C.F.R. §§ 50.35, 50.40 and 51.105(a) and the issues discussed at the uncontested hearing concerning the application of Kairos Power, LLC to construct a non-power test reactor facility at the East Tennessee Technology Park in Oak Ridge, Tennessee. The Memorandum and Order authorizes issuance of the construction permit.

(Subsequently, on December 12, 2023, the Secretary signed the Memorandum and Order.)

cc: Chair Hanson Commissioner Wright Commissioner Caputo Commissioner Crowell EDO OGC CFO OCAA OCA OIG OPA ODs, RAs, ACRS, ASLBP PDR