INFORMATION REPORT April 4, 2018 SECY-18-0043 FOR: The Commissioners FROM: Robert J. Lewis Assistant for Operations Office of the Executive Director for Operations

SUBJECT:

WEEKLY INFORMATION REPORT - WEEK ENDING MARCH 30, 2018 CONTENTS Enclosure Office of Administration A Office of the Chief Information Officer B Office of Nuclear Reactor Regulation C Office of the Secretary D

/RA/

Robert J. Lewis Assistant for Operations, OEDO

Contact:

A. Barnes, OEDO 301-415-1720

ML18093A610 OFFICE OEDO OEDO/AO NAME ABarnes RLewis DATE 04/03/18 04/04/18 Office of Administration (ADM)

Items of Interest Week Ending March 30, 2018 Microsoft Savings The Office of Administrations Acquisition Management Division competed and awarded a Blanket Purchase Agreement (BPA) valued at up to $15 million over 5 years for Microsoft software licenses, software subscriptions and cloud services for the NRC. The BPA, which is effective on April 1, 2018, consolidated Microsoft requirements from several current NRC contracts into one vehicle. The BPA resulted in savings of $226k per year for current NRC Microsoft requirements based on what an independent industry group indicated was fair market pricing for federal agencies. The BPA also allows the NRC to purchase renewals of its investments and new Microsoft investments at a discounted rate and in a very efficient manner. As a result of this BPA, the NRC can also better track and manage its Microsoft investments.

MARCH 30, 2018 ENCLOSURE A

Office of the Chief Information Officer (OCIO)

Items of Interest Week Ending March 30, 2018 Freedom of Information Act (FOIA) and Privacy Act (PA) Requests and Appeals Received During the Period of March 26- March 30, 2018, as submitted by requester ML042650352, ML050280428, ML080440139, and ML080440144 NRC-2018-000467 Names of NRC approved Authorized Derivative classifier NRC-2018-000468 White House memo dated January 20, 2017, Final COS (Chief of Staff)

NRC-2018-000469 Regulatory Freeze Memo Memo dated February 2, 2017, and email dated January 21, 2017, to NRC from named individual; all memos to/from NRC and named NRC-2018-000470 individual; all memos from named individual to NRC, 2017-current; and emails to NRC from named individual on January 31, 2017 Organizational chart, job duties/purpose and cell number assigned to NRC-2018-000471 named NRC staff "Biological consequences of lake recovery," by Sabourin, T. D., R. S.

NRC-2018-000472 Hayward, B. Cornaby, and R. L. Faulk. 1986 Appeal the denial of information based on FOIA exemption 7(C), in NRC-2018-000473 response to NRC-2018-000287 All plutonium inventory reports, and all reports and communications dealing with or discussing any and all Material Unaccounted for (MUF)

NRC-2018-000474 from the now defunct Kerr-McGee Cimarron nuclear facility in Crescent, Oklahoma Records referred from the U.S. Department of State pertaining to named individual's tour of duty at the American Embassy in Managua, NRC-2018-000475 Nicaragua, and their involvement in a security case from August 1976 to December 1977 All speeches made by the NRC Chairman and Commissioners on and NRC-2018-000477 after January 1, 2017 Any documentation on what materials are, or have been utilized or stored at: Construction Services Associates, 20 East Clementon Road, Block NRC-2018-000478 8.01 Lot 3.02, Gibbsboro, Camden County, New Jersey 08026 All background and supporting documentation including correspondence regarding the NRC Confirmatory Order (3.12.18 attached) for Entergy Nuclear Operations, Inc. and Entergy Operations, Inc. NRC-2018-000479 https://www.nrc.gov/reading-rm/doc-collections/news/2018/18-002.iv.pdf and https://www.nrc.gov/docs/ML1807/ML18072A191.pdf Any MLTS information on the following site: Photon Field Inspection Inc.;

NRC-2018-000480 1705 Boxwood, Saginaw, Michigan (License Number: 21-21010-01)

MARCH 30, 2018 ENCLOSURE B

Office of Nuclear Reactor Regulation (NRR)

Items of Interest Week Ending March 30, 2018 Differing Professional Opinion Regarding Closing Out Peer Review Facts and Observations On February 22, 2018, the Executive Director for Operations (EDO) issued a decision on the appeal of Differing Professional Opinion (DPO) 2017-004, submitted on May 15, 2017, regarding the agencys endorsement of Nuclear Energy Institute guidance on closing out Probabilistic Risk Assessment (PRA) peer review facts and observations. Specifically, the DPO raised concerns that the NRC has endorsed a weakened version of the process for closing out PRA Peer Review Facts and Observations/Findings (F&Os), thereby yielding much of its responsibility to ensure technical adequacy of industry PRAs. On September 8, 2017, an Ad Hoc Panel (Panel) provided the results of its independent review of the DPO to the Acting Director, Office of Nuclear Reactor Regulation (NRR). The Panel concluded the independent review process is an acceptable method for closure of F&Os. The Panel also concluded the independence of team members implementing the process was appropriate for the task.

Finally, the Panel concluded that various methods for F&O closure, including by an independent NRC review team, were considered. The Panel recommended appropriate resources be applied to conducting audits of the independent F&O closure process until a time when the NRC has established adequate confidence in the process implementation. The NRC and industry should reach agreement on what F&O closures constitute a PRA upgrade or new method that would require a focused peer review. The expectation that documentation of why closed F&Os did not require an upgrade or new method needs to be highlighted to the industry, and management should consider providing clarifying guidance to the level of NRC staff review expected for a peer-reviewed PRAs where the F&O's have been closed under the lndependent Review Process. The Acting Director, NRR agreed with the Panel on its conclusions and recommendations. The public records for this DPO can be found at ML18078A786.

Open Phase Condition Inspection at Palo Verde During the week of March 19, 2018, the staff completed the second open phase condition (OPC) temporary instruction (TI) inspection at Palo Verde Generating Station resulting in no findings. Palo Verde Generating Station is the second of an initial set of inspections conducted under the OPC TI to determine whether licensees implemented the industry voluntary initiative to identify OPC vulnerabilities and update their licensing basis. The staff expects to complete this initial set of OPC TI inspections by the end of June.

Audit of Alkali-Silica Methodology at Seabrook During the week of March 19, 2018, the staff conducted a joint license amendment request and license renewal audit at Seabrook Station to review the proposed methodology for analyzing structures impacted by alkali-silica reaction (ASR) and the associated aging management program (AMP). The intent of the audit was to sample completed structural evaluations to confirm the adequacy of the licensee proposed methodology and verify proper implementation to produce reasonable monitoring parameters and acceptance criteria. The staffs observations will be captured in an audit report.

MARCH 30, 2018 ENCLOSURE C

Operating Reactors Dashboard of NRC Performance Now Available on Public Website The Operating Reactors Dashboard of NRC Performance is now available on the NRCs public website. A prototype was published on the website in January, and the final version was published on March 23. The graphs and data will be updated monthly with the data from the NRCs metrics on timeliness and activities completed. A poster session at the RIC and discussions during meetings with industry stakeholders were used to advertise the availability of the web page. The page can be found here: https://www.nrc.gov/reactors/operating/nrc-performance-dashboard.html.

MARCH 30, 2018 ENCLOSURE C

Office of the Secretary (SECY)

Items of Interest Week Ending March 30, 2018 Document Released to Public Date of Subject Document Information Papers

1. SECY-18-0037 03/09/208 Review of the Emerging Medical Technologies Program (w/o Enclosure)
2. SECY-18-0040 03/22/2018 Weekly Information Report - Week Ending March 16, 2018
3. SECY-18-0041 03/27/2018 Weekly Information Report - Week Ending March 23, 2018 Commission Correspondence
1. Letter to the Honorable Lamar Alexander and Mike Simpson, submits the NRCs monthly Congressional status report for February 2018, dated March 19, 2018.
2. Letter to the Honorable Elizabeth Warren, Edward Markey and William Keating, responds to their letter regarding safety concerns at Pilgrim Nuclear Power Station, dated March 19, 2018.
3. Letter to the Honorable Greg Walden, et al., submits the February 2018 monthly status report on the NRCs activities and use of unobligated carryover funds appropriated from the Nuclear Waste Fund, dated March 19, 2018.
4. Letter to the Honorable Greg Walden, Fred Upton, John Shimkus, responds to their letter regarding the transformation initiative under development at the NRC, dated March 19, 2018.
5. Letter to the Honorable Dean Heller, responds to his letter which poses several questions regarding licensing activities associated with the Yucca Mountain construction authorization application, dated March 20, 2018.

Federal Register Notices Issued

1. Meeting of the Advisory Committee on Reactor Safeguards (ACRS) Subcommittee on Planning and Procedures - Notice of Meeting - April 4, 2018.
2. Meeting of the ACRS Subcommittee on Reliability and PRA - Notice of Meeting - April 4, 2018.
3. Meeting of the ACRS Subcommittee on Radiation Protection and Nuclear Materials - Notice of Meeting - April 4, 2018.

MARCH 30, 2018 ENCLOSURE D