SBK-L-10147, Incorrect Reference in Submittal Letter
| ML102440025 | |
| Person / Time | |
|---|---|
| Site: | Seabrook |
| Issue date: | 08/20/2010 |
| From: | O'Keefe M NextEra Energy Seabrook |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| SBK-L-10147 | |
| Download: ML102440025 (2) | |
Text
-4' NEXTera T
ENERGYL.,
SB0
~.*1.~~
August 20,.2010._
---'Docket No. 5 0-443 SBK-L-10147 United States Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555-0001 Seabrook Station Incorrect Reference in Submittal Letter
Reference:
SBK-L-10027, Inservice Inspection Examination Report, dated February 9, 2010 In the referenced report, ASME Code Case N-532-1 was incorrectly referenced in the submittal cover letter. The correct reference is ASME Code Case N-532-4. The information contained in the enclosure to SBK-L-10027 was not affected by the incorrect reference.
If you have any questions regarding this information, please contact me at (603) 773-7745.
Sincerely, NextEra Energy Seabrook, LLC Michael O'Keefe Licensing Manager NextEra Energy Seabrook, LLC, P.O. Box 300, Lafayette Road, Seabrook, NH 03874
United States Nuclear Regulatory Commission SBK-L-10147/Page 2 cc:
NRC Region I Administrator G. E. Miller, NRC Project Manager, Project Directorate I-2 W. Raymond, NRC Senior Resident Inspector Wayne Brigham, Boiler Inspector New Hampshire Department of Labor Inspection Division PO Box 2076 Concord, NH 03302-2076