RS-05-015, Confirmation of Completion of Actions Authorization Related to Access
| ML050390363 | |
| Person / Time | |
|---|---|
| Site: | Dresden, Peach Bottom, Oyster Creek, Quad Cities, Zion |
| Issue date: | 02/02/2005 |
| From: | Jamie Benjamin AmerGen Energy Co, Exelon Generation Co, Exelon Nuclear |
| To: | Document Control Desk, NRC/FSME |
| References | |
| %dam200604, +KBR1SISP20050614, RS-05-015 | |
| Download: ML050390363 (3) | |
Text
-Amer~e-n, Exelknm An Exelon Company AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555 www.exeloncorp.corn Nuclear Exelon Generation 4300 Winfield Road Warrenville, IL 60555 RS-05-015 February 2, 2005 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 1, 2 and 3 Facility Operating License Nos. DPR-2, DPR-19 and DPR-25 NRC Docket Nos. 50-10. 50-237. 50-249 and 72-37 Oyster Creek Generating Station Facility Operating License No. DPR-16 NRC Docket Nos. 50-219 and 72-15 Peach Bottom Atomic Power Station, Units 2 and 3 Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277. 50-278 and 72-29 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254, 50-265 and 72-53 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304
Subject:
Confirmation of Completion of Actions Authorization Related to Access
References:
(1)
Letter from U. S. NRC, Issuance of Order for Implementation of Additional Security Measures Associated with Access Authorization, Fitness for Duty and Behavior Observation for Zion Nuclear Power Station Units 1 and 2," dated August 18, 2004 (EA-03-099)
(2)
Letter from U. S. NRC, 'Issuance of Order for Implementation of Additional Security Measures Associated with Access Authorization," dated August 18, 2004 (EA-03-097)
,- C5
February 2, 2005 U. S. Nuclear Regulatory Commission Page 2 (3)
Letter from U. S. NRC, "Issuance of Orders for Interim Safeguards and Security Compensatory Measures and for Implementation of Additional Security Measures Associated with Access Authorization for Quad Cities Nuclear Power Station Units 1 and 2," dated November 9, 2004 (EA-04-186)
(4)
Letter from Jeffrey A. Benjamin (EGC) to U. S. NRC, "Response to Issuance of Order to Modify License Associated With Access Authorization, Fitness For Duty, and Behavior Observation," dated September 7, 2004 (5)
Letter from Jeffrey A. Benjamin (EGC/AmerGen) to U. S. NRC, "Response to Issuance of Order to Modify License Associated With Access Authorization,"
dated September 7, 2004 (6)
Letter from Jeffrey A. Benjamin (EGC) to U. S. NRC, "Response to Issuance of Order to Modify License Associated With Access Authorization," dated November 29, 2004 In accordance with 10 CFR 50.4, 10 CFR 72.4, and Condition C.2 of the NRC Orders issued in References 1, 2, and 3, Exelon Generation Company, LLC (Exelon) and AmerGen Energy Company, LLC (AmerGen), report that our actions to achieve full compliance with the requirements described in Attachment 2 of the Orders were completed by January 28, 2005. The manner and method for compliance is as described in References 4 through 6, as applicable.
If you have any questions regarding this submittal, please contact Patrick Simpson at (630) 657-2823.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2nd day of February, 2005.
Respectfully, Benjamin Vice President - Licensing and Regulatory Affairs Exelon Generation Company, LLC AmerGen Energy Company, LLC
February 2, 2005 U. S. Nuclear Regulatory Commission Page 3 cc:
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission ATTN: Mr. Jack R. Strosnider, Director Office of Nuclear Material Safety and Safeguards One White Flint North 11555 Rockville Pike Rockville, MD20852-2738 Office of the Secretary U. S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555-0001 Assistant General Counsel for Materials Litigation and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 Regional Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Regional Administrator - Region IlIl U.S. Nuclear Regulatory Commission 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 N