RA-20-0304, AP1000 Combined License Application Departure Report Update
ML20268A072 | |
Person / Time | |
---|---|
Site: | 05200022, 05200023 |
Issue date: | 09/24/2020 |
From: | Nolan M Duke Energy Progress |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RA-20-0304 | |
Download: ML20268A072 (1) | |
Text
I DUKE
"--' ENERGY,. M. Christopher Nolan Vice President Nuclear Regulatory Affairs, Policy &
Emergency Preparedness Duke Energy 526 South Church Street, EC07C Charlotte, NC 28202 704-382-7426 Chris.Nolan@duke-energy.com Serial: RA-20-0304 September 24, 2020 10 CFR 52, Appendix D, X.B U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT, UNITS 2 AND 3 DOCKET NOS.52-022 AND 52-023
SUBJECT:
AP1000 Combined License Application Departure Report Update Duke Energy Progress, Inc. (DEP) submitted an application, dated February 18, 2008, for a combined license for two AP1000 advanced pressurized water reactors to be located at the Shearon Harris Nuclear Power Plant Site. Part 7 of the application is entitled "Departures and Exemption Requests." This letter provides an update to the report describing plant-specific departures from the AP1000 Design Control Document (i.e. Departures Report) as required by 10 CFR 52, Appendix D, paragraphs X.B.1 and X.B.3.b.
There have been no new departures or changes to the departures described in the Shearon Harris Nuclear Power Plant (HAR), Units 2 and 3, COLA Part 7, "Departures and Exemption Requests" for the period of April 1, 2020 to September 24, 2020.
This submittal contains no regulatory commitments.
Please address any comments or questions regarding this matter to Art Zaremba, Manager -
Fleet Licensing at (980) 373-2062.
Sincerely~ - ~
M. Christopher Nolan Vice President, Nuclear Regulatory Affairs cc: L. Dudes, U.S. NRC Region II Administrator D. Murray, U.S . NRC Project Manager