Exelon Generation0 RA-17-058 June 20, 2017 U.S. Nuclear Regulatory Commission A TIN: Document Control Desk Washington, DC 20555-0001 Three Mile Island Nuclear Station, Unit I Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 J. Bradley Fewell Senior Vice President, Regulatory Affairs &

General Counsel 4300 Winfield Road Warrenville, IL 60555 630.657.3752 Office 630.657.4335 Fax www.exeloncorp.com bradley.fewell@exeloncorp.com 10 CFR 50.82

Subject:

Certification of Permanent Cessation of Power Operations for Thn.:e Mile Island Nuclear Station, Unit I On May 30, 2017, Exelon Generation Company, LLC (Exelon) announced that it plans to prematurely retire the Three Mile Island Nuclear Station (TMI), Unit I due to severe economic challenges.

Therefore, pursuant to JO CFR 50.82(a)(l)(i) and 10 CFR 50.4(b)(8), Exelon certifies to the U.S. Nuclear Regulatory Commission that it has decided to permanently cease power operations at TMI, Unit I on or about September 30, 2019.

There are no regulatory commitments contained in this submittal.

If you have any questions regarding this submittal, please contact F. Paul Bonnett at (610) 765-5264.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 20'h day of June 2017.

cc:

NRC Regional Administrator, Region I NRC Project Manager, TMI-1 NRC Senior Resident Inspector - TMI-1 Director, Bureau of Radiation Protection - PA Department of Environmental Resources