MONTHYEARML20036E9992020-02-0505 February 2020 OEDO-20-00053 - 2.206 Petition - Flooding Likely to Create Radioactive Geysers at SONGS Press Release-19-039, NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants2019-08-21021 August 2019 Press Release-19-039: NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants Press Release-IV-19-014, NRC to Hold Public Meeting to Discuss Oversight Activities at San Onofre Nuclear Generating Station2019-08-0101 August 2019 Press Release-IV-19-014: NRC to Hold Public Meeting to Discuss Oversight Activities at San Onofre Nuclear Generating Station Press Release-IV-19-012, NRC Has Determined Fuel Loading Can Be Safely Resumes at San Onofre Nuclear Generating Station2019-05-21021 May 2019 Press Release-IV-19-012: NRC Has Determined Fuel Loading Can Be Safely Resumes at San Onofre Nuclear Generating Station Press Release-IV-19-005, NRC to Conduct Virtual Public Meeting/Webinar on Fuel Loading at San Onofre Nuclear Generating Station2019-03-0707 March 2019 Press Release-IV-19-005: NRC to Conduct Virtual Public Meeting/Webinar on Fuel Loading at San Onofre Nuclear Generating Station Press Release-IV-19-002, NRC to Conduct Pre-Decisional Enforcement Conference Via Webinar on Special Inspection at San Onofre Nuclear Generating Station2019-01-10010 January 2019 Press Release-IV-19-002: NRC to Conduct Pre-Decisional Enforcement Conference Via Webinar on Special Inspection at San Onofre Nuclear Generating Station Press Release-IV-18-014, NRC to Conduct Virtual Public Meeting/Webinar on Special Inspection at San Onofre Nuclear Generating Station2018-10-29029 October 2018 Press Release-IV-18-014: NRC to Conduct Virtual Public Meeting/Webinar on Special Inspection at San Onofre Nuclear Generating Station Press Release-16-001, NRC Grants Weapons Pre-Emption Authority to Nuclear Facilities in Two States2016-01-0606 January 2016 Press Release-16-001: NRC Grants Weapons Pre-Emption Authority to Nuclear Facilities in Two States Press Release-15-037, NRC Approves Changes to San Onofre Nuclear Plant'S Emergency Planning Requirements2015-06-0505 June 2015 Press Release-15-037: NRC Approves Changes to San Onofre Nuclear Plant'S Emergency Planning Requirements Press Release-IV-13-031, NRC Issues Confirmatory Action Letter Inspection Report for San Onofre Nuclear Generating Station2013-09-23023 September 2013 Press Release-IV-13-031: NRC Issues Confirmatory Action Letter Inspection Report for San Onofre Nuclear Generating Station Press Release-13-076, NRC to Hold Public Meeting Sept. 26 in Carlsbad, Calif., on the Nuclear Power Reactor Decommissioning Process2013-09-12012 September 2013 Press Release-13-076: NRC to Hold Public Meeting Sept. 26 in Carlsbad, Calif., on the Nuclear Power Reactor Decommissioning Process Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-13-047, NRC Issues Order Designating 10 Facilities Eligible for Weapons Pre-Emption Authority2013-06-0505 June 2013 Press Release-13-047: NRC Issues Order Designating 10 Facilities Eligible for Weapons Pre-Emption Authority Press Release-13-038, Statement of NRC Chairman Allison M. Macfarlane on the Atomic Safety and Licensing Board Decision in the San Onofre Confirmatory Action Letter Adjudication2013-05-17017 May 2013 Press Release-13-038: Statement of NRC Chairman Allison M. Macfarlane on the Atomic Safety and Licensing Board Decision in the San Onofre Confirmatory Action Letter Adjudication Press Release-13-035, ASLB: San Onofre Confirmatory Action Letter Process Offers Opportunity for Adjudicatory Hearing2013-05-13013 May 2013 Press Release-13-035: ASLB: San Onofre Confirmatory Action Letter Process Offers Opportunity for Adjudicatory Hearing ML13094A2092013-04-0101 April 2013 LTR-13-0279 - E-mail. Gary Headrick Concerns Keeping the NRC Accountable and No Restart at San Onofre Nuclear Generating Station Press Release-13-019, NRC and So. California Edison to Discuss Potential License Amendment Request for San Onofre 2 in Rockville, Md, on April 32013-03-22022 March 2013 Press Release-13-019: NRC and So. California Edison to Discuss Potential License Amendment Request for San Onofre 2 in Rockville, Md, on April 3 Press Release-13-015, ASLB to Hear Oral Argument March 22 in Rockville, Md, on Petition Challenging San Onofre Oversight2013-03-13013 March 2013 Press Release-13-015: ASLB to Hear Oral Argument March 22 in Rockville, Md, on Petition Challenging San Onofre Oversight Press Release-13-010, NRC to Discuss San Onofre Unit 2 Restart Proposal with Southern California Edison in Rockville, Md, on Feb. 272013-02-21021 February 2013 Press Release-13-010: NRC to Discuss San Onofre Unit 2 Restart Proposal with Southern California Edison in Rockville, Md, on Feb. 27 ML13046A0132013-02-11011 February 2013 LTR-13-0135 - E-mail. Ray Lutz Provides Press Release, NRC to Face Public Rage Over Rattling Reactor, Coverup of Known Steam Generator Defects to Haunt Capistrano Beach Meeting Press Release-IV-13-003, NRC to Meet Public to Discuss San Onofre Nuclear Generating Station Steam Generator Issues2013-01-22022 January 2013 Press Release-IV-13-003: NRC to Meet Public to Discuss San Onofre Nuclear Generating Station Steam Generator Issues ML13024A1382013-01-20020 January 2013 LTR-13-0059 - Don Leichtling and Ace Hoffman E-mail Press Release 13-01-22 Regarding San Onofre Unit 2 ML13023A0862013-01-18018 January 2013 LTR-13-0055 - E-mail Don Leichtling & Ace Hoffman Media Alert 13-01-17 Allegation - NRC Violating Presidential Directive and the Public Trust. San Onofre Unit 2 Restart Decision by NRC Imminent - Sce'S Pr Machine Is Capable of Overcoming Al ML13017A0472013-01-15015 January 2013 LTR-13-0046 - E-Mail Don Leichtling Provides Media Alert 13-01-15 - Allegation - SCE Violated Federal Regulation and the Public Trust. Expert Summation - San Onofre'S Replacement Steam Generators Unsafe ML13017A1152013-01-10010 January 2013 LTR-13-0009 - Don Leichtling E-mail Press Release 13-01-10 Ten Unresolved Items, Requires NRR Investigation ML13003A1842013-01-0202 January 2013 LTR-13-0003 - E-mail Don Leichtling Concerns Press Release - the NRC AIT Team'S Review of San Onofre Nuclear Generating Station'S Original Steam Generators and Their Replacement Steam Generators Require Another Immediate Investigation ML13002A4682012-12-28028 December 2012 LTR-12-0842 - Ltr. Don Leichtling Re Concerns Press Release - the Thirty Unresolved Alarms Recorded by San Onofre Nuclear Generating Station'S Vibration Monitoring System During Eleven Months of Operation, Requires an Immediate NRR Safety I ML12362A0322012-12-21021 December 2012 LTR-12-0828 - E-Mail Don Leichtling Re Press Release on Causes of Destruction of San Onofre Nuclear Generating Station (Song) Replacement Steam Generators, Requires NRR Complete an Investigation Prior to Any SONGS Unit 2 Restart ML12362A0172012-12-20020 December 2012 LTR-12-0825 - E-mail Don Leichtling Re Press Release on Viability of Operator Actions to Prevent Offsite Radiation Releases Prior to Any Restart (San Onofre Nuclear Generating Station) ML12347A1562012-12-10010 December 2012 LTR-12-0776 - Ace Hoffman Email Press Release - Sce'S Claims About SONGS, Unit 2, Operating Pressures Are Erroneous Press Release-12-126, NRC to Discuss San Onofre Unit 2 Restart Proposal with Southern California Edison in Rockville, Md., on Dec. 182012-12-10010 December 2012 Press Release-12-126: NRC to Discuss San Onofre Unit 2 Restart Proposal with Southern California Edison in Rockville, Md., on Dec. 18 ML12340A0252012-11-29029 November 2012 LTR-12-0735 - E-mail Don Leichtling Press Release - San Onofalmost a Level 3 Nuclear Incident, in Both SONGS Unit 2 and Unit 3 ML12335A2962012-11-21021 November 2012 LTR-12-0718 - E-Mail Don Leichtling Restart or Not to Restart - the Trillion Dollar Question for San Onofre Nuclear Generating Station (SONGS) Press Release-IV-12-050, NRC to Meet with Southern California Edison Co. Officials to Discuss San Onofre Nuclear Generating Station Steam Generator Issues2012-11-20020 November 2012 Press Release-IV-12-050: NRC to Meet with Southern California Edison Co. Officials to Discuss San Onofre Nuclear Generating Station Steam Generator Issues Press Release-12-125, ASLB to Hear Oral Arguments Dec. 5 in Rockville, Md., on Request for Hearing on San Onofre License Amendments2012-11-20020 November 2012 Press Release-12-125: ASLB to Hear Oral Arguments Dec. 5 in Rockville, Md., on Request for Hearing on San Onofre License Amendments ML12325A0272012-11-0909 November 2012 LTR-12-0692 - E-mail Gary Headrick San Onofre Officials Investigating Case of Potential Sabotage Press Release-IV-12-047, NRC to Meet with Southern California Edison Co. Officials to Discuss San Onofre Nuclear Plant Steam Generator Issues2012-11-0606 November 2012 Press Release-IV-12-047: NRC to Meet with Southern California Edison Co. Officials to Discuss San Onofre Nuclear Plant Steam Generator Issues Press Release-12-117, NRC Sponsoring National Academy of Sciences Effort to Carry Out Pilot of Cancer Risk Study2012-10-23023 October 2012 Press Release-12-117: NRC Sponsoring National Academy of Sciences Effort to Carry Out Pilot of Cancer Risk Study Press Release-IV-12-043, NRC Names Panelists for Public Meeting to Discuss San Onofre Nuclear Generating Station Issues2012-10-0404 October 2012 Press Release-IV-12-043: NRC Names Panelists for Public Meeting to Discuss San Onofre Nuclear Generating Station Issues Press Release-IV-12-042, NRC Receives Response to Confirmatory Action Letter, Action Plan for San Onofre Unit 2 Proposed NRC Review to Take Months2012-10-0404 October 2012 Press Release-IV-12-042: NRC Receives Response to Confirmatory Action Letter, Action Plan for San Onofre Unit 2 Proposed NRC Review to Take Months Press Release-IV-12-038, NRC to Hold Public Meeting to Discuss San Onofre Nuclear Generating Station Issues2012-09-13013 September 2012 Press Release-IV-12-038: NRC to Hold Public Meeting to Discuss San Onofre Nuclear Generating Station Issues Press Release-12-099, NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants2012-09-0606 September 2012 Press Release-12-099: NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants Press Release-IV-12-028, NRC Issues Augmented Inspection Team Report on San Onofre Nuclear Generating Station Steam Generators2012-07-19019 July 2012 Press Release-IV-12-028: NRC Issues Augmented Inspection Team Report on San Onofre Nuclear Generating Station Steam Generators Press Release-IV-12-021, NRC to Hold Public Meeting to Discuss Status of Augmented Inspection at San Onofre Nuclear Generating Station2012-06-0808 June 2012 Press Release-IV-12-021: NRC to Hold Public Meeting to Discuss Status of Augmented Inspection at San Onofre Nuclear Generating Station Press Release-IV-12-017, Statement from Chairman Gregory Jaczko on San Onofre Restart2012-05-0707 May 2012 Press Release-IV-12-017: Statement from Chairman Gregory Jaczko on San Onofre Restart Press Release-IV-12-011, NRC Issues Confirmatory Action Letter for San Onofre Nuclear Generating Station Restart Preparations2012-03-27027 March 2012 Press Release-IV-12-011: NRC Issues Confirmatory Action Letter for San Onofre Nuclear Generating Station Restart Preparations Press Release-IV-12-008, NRC to Send Augmented Inspection Team to San Onofre Nuclear Generating Station2012-03-15015 March 2012 Press Release-IV-12-008: NRC to Send Augmented Inspection Team to San Onofre Nuclear Generating Station Press Release-IV-11-011, NRC to Discuss 2010 Performance Assessment for San Onofre Nuclear Generating Station2011-04-0707 April 2011 Press Release-IV-11-011: NRC to Discuss 2010 Performance Assessment for San Onofre Nuclear Generating Station Press Release-11-043, NRC Continues to Track Earthquake and Tsunami Issues2011-03-11011 March 2011 Press Release-11-043: NRC Continues to Track Earthquake and Tsunami Issues Press Release-10-154, National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study2010-09-0303 September 2010 Press Release-10-154: National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study 2020-02-05
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region IV 1600 E. Lamar Blvd.
Arlington, TX 76011 - 4125 Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. IV-12-021 June 8, 2012
Contact:
Victor Dricks (817) 200-1128 E-Mail: OPA4.Resource@nrc.gov Lara Uselding (817) 200-1519 NRC TO HOLD PUBLIC MEETING TO DISCUSS STATUS OF AUGMENTED INSPECTION AT SAN ONOFRE NUCLEAR GENERATING STATION The Nuclear Regulatory Commission will hold a public meeting on June 18 to provide a status of the Augmented Inspection conducted at the San Onofre Nuclear Generating Station after several steam generator tubes failed a pressure test. The plant, operated by Southern California Edison Co. is located in San Clemente, Calif. This will be the first in a series of meetings to be held in the area to keep the public informed on the progress of NRC inspection and oversight activities at San Onofre.
The meeting will be held between 6 and 9 p.m. at the San Juan Capistrano Community Center, Community Hall, 25925 Camino Del Avion, in San Juan Capistrano. During the first part of the meeting, which is open to public observation, the NRC staff will provide a summary of the Augmented Inspection Teams observations thus far followed by a response from the licensee.
After a short break the NRC staff will be available to answer questions from the public and accept comments on issues related to San Onofre.
We know there is a great deal of interest in how the NRC is ensuring safety at San Onofre, said NRC Region IV Administrator Elmo E. Collins. We want to provide the public with the status of our inspection of the plants steam generators and talk about the process the NRC will use to ensure that all of our rigorous requirements for operating the facility are met.
Operators shut down Unit 3 on Jan. 31, after a tube leak in one steam generator was identified; Unit 2 had been shut down for a scheduled maintenance outage. Both reactors have remained safely shutdown. On March 27, the NRC issued a Confirmatory Action letter documenting actions that Southern California Edison officials have agreed to take prior to seeking permission to restart the reactors. The NRC has been conducting inspections to determine the extent and cause of the tube degradation. Steam generators do experience some wear during the first year of operation but the level of tube wear at both units is unusual.
Between March 13 and 21, 129 steam generator tubes were pressure tested. Eight tubes failed acceptance criterion - indicating that they could rupture during some operating conditions.
The integrity of steam generator tubes is important because the tubes provide an additional
barrier inside the containment building to prevent a radioactive steam release. Augmented inspections are used by the NRC to review more significant issues such as a tube failure at NRC-licensed facilities.
The team reviewed information associated with the design, construction, shipping, operation, and testing of the steam generators. The team will issue a written report within the next 30 days that will be publicly available. The report will identify areas for further inspection follow-up.
You may access the meeting notice through ADAMS by using accession number ML12160A551.
News releases are available through a free Listserv subscription or by clicking on the EMAIL UPDATES link on the NRC homepage (www.nrc.gov). E-mail notifications are sent to subscribers when news releases are posted to NRC's website. For the latest news, follow the NRC on www.twitter.com/NRCgov.