Category:Letter type:PNP
MONTHYEARPNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations PNP 2024-031, Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-07-18018 July 2024 Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations PNP 2024-027, Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2024-07-0909 July 2024 Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2024-003, License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis2024-05-24024 May 2024 License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis PNP 2024-025, Supplement to Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments, Proposed Power Operations Quality Assurance Program Manual, Revision 02024-05-23023 May 2024 Supplement to Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments, Proposed Power Operations Quality Assurance Program Manual, Revision 0 PNP 2024-023, Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis2024-05-0909 May 2024 Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis PNP 2024-005, License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-05-0101 May 2024 License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations PNP 2024-008, Annual Radioactive Effluent Release Report2024-04-23023 April 2024 Annual Radioactive Effluent Release Report PNP 2024-009, Annual Radiological Environmental Operating Report2024-04-23023 April 2024 Annual Radiological Environmental Operating Report PNP 2024-017, 2023 Annual Non-Radiological Environmental Operating Report2024-04-23023 April 2024 2023 Annual Non-Radiological Environmental Operating Report PNP 2024-016, Notice of Intent to Pursue Subsequent License Renewal2024-04-18018 April 2024 Notice of Intent to Pursue Subsequent License Renewal PNP 2024-006, Notification of Changes in Accordance with 10 CFR 50.82(a)(7)2024-04-0909 April 2024 Notification of Changes in Accordance with 10 CFR 50.82(a)(7) PNP 2024-001, License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-02-0909 February 2024 License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments PNP 2023-033, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-021, Ventilated Storage Cask Inspection Summary Report2023-08-16016 August 2023 Ventilated Storage Cask Inspection Summary Report PNP 2023-023, Special Report – High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report – High Range Noble Gas Monitor Inoperable PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report PNP 2023-007, And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 And Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance PNP 2022-031, License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements2022-09-14014 September 2022 License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2022-025, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 182022-09-12012 September 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 18 PNP 2022-032, 2022 Evacuation Time Estimate Report2022-09-0707 September 2022 2022 Evacuation Time Estimate Report PNP 2022-023, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 172022-08-15015 August 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 17 PNP 2022-014, Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 342022-07-13013 July 2022 Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 34 PNP 2022-016, License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-07-12012 July 2022 License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-017, Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E2022-07-11011 July 2022 Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals PNP 2022-010, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2022-06-13013 June 2022 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel PNP 2022-011, Termination of the Emergency Response Data System (Eros) Link2022-06-13013 June 2022 Termination of the Emergency Response Data System (Eros) Link 2024-08-02
[Table view] |
Text
,.
~ Entergy Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Tel 269 764 2000 Anthony J. Vitale Site Vice President PNP 2012-014 February 1, 2012 U. S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Commitment Revision Letter Palisades Nuclear Plant Docket 50-255 License No. DPR-20
References:
- 1. Entergy Nuclear Operations, Inc. letter dated December 20,2010, Updated Palisades Reactor Vessel Pressurized Thermal Shock Evaluation (Accession No. ML110060692)
- 2. NRC letter dated December 7,2011, Updated Reactor Pressure Vessel Pressurized Thermal Shock Evaluation for Palisades Nuclear Plant (TAC No. ME5263), (Accession No. ML112870050)
Dear Sir or Madam:
By letter dated December 20, 2010, Entergy Nuclear Operations, Inc. (ENO) submitted an updated Palisades reactor vessel pressurized thermal shock (PTS) evaluation (Reference 1). The PTS evaluation concluded that limiting welds would not reach the 10 CFR 50.61 PTS screening criterion limit until April 2017. The updated reactor vessel PTS evaluation was approved by the NRC in a letter dated December 7,2011 (Reference 2).
In the December 20, 2010 letter, ENO committed to perform a volumetric inspection of the reactor vessel beltline region welds during the 2012 refueling outage. ENO also committed to submit a revised PTS evaluation under 10 CFR 50.61 a, including an evaluation of near-surface flaws from the volumetric examination, no less than three years before reactor vessel limiting axial welds are projected to reach the 10 CFR 50.61 PTS screening criterion limit.
ENO now plans to perform the volumetric inspection of the reactor vessel beltline region welds during the 2013 refueling outage. Performing the volumetric inspection during the 2013 refueling outage will support submittal of the revised PTS evaluation under 10 CFR 50.61 a at least three years prior to reaching the PTS screening criterion limit.
Document Control Desk PNP 2012-014 Page 2 Summary of Commitments This letter contains no new commitments and one revision to existing commitments.
Commitment made by letter of December 20, 2010:
Entergy Nuclear Operations, Inc. (ENO) will perform a volumetric inspection of the reactor vessel beltline region welds during the 2012 refueling outage.
Revised commitment:
Entergy Nuclear Operations, Inc. (ENO) will perform a volumetric inspection of the reactor vessel beltline region welds during the 2013 refueling outage.