Category:NRC Preliminary Notification of Event/Occurrence
MONTHYEARPNO-III-23-002B, Prairie Island Update to PNO-III-23-002 Declaration of an Unusual Event Following a Turbine Generator and Reactor Trip Due to Fault on Unit 2 Generator Main Transformer2023-06-0808 June 2023 PNO-III-23-002B Prairie Island Update to PNO-III-23-002 Declaration of an Unusual Event Following a Turbine Generator and Reactor Trip Due to Fault on Unit 2 Generator Main Transformer PNO-III-23-002, Prairie Island Nuclear Power Station Declaration of an Unusual Event Following a Turbine Generator and Reactor Trip Due to Fault on Unit 2 Generator Main Transformer2023-06-0101 June 2023 PNO-III-23-002 - Prairie Island Nuclear Power Station Declaration of an Unusual Event Following a Turbine Generator and Reactor Trip Due to Fault on Unit 2 Generator Main Transformer PNO-III-15-011, Prairie Island Nuclear Plant: Shutdown of Unit 2 and Notice of Unusual Event2015-12-18018 December 2015 PNO-III-15-011 - Prairie Island Nuclear Plant: Shutdown of Unit 2 and Notice of Unusual Event PNO-III-15-008, Prairie Island Unit 2 Shutdown Due to Trip of Main Power Turbine2015-06-0909 June 2015 PNO-III-15-008: Prairie Island Unit 2 Shutdown Due to Trip of Main Power Turbine PNO-III-15-003, A: Update: Shutdown of Prairie Island Unit 2 Due to Loss of Instrument Air to Containment Building2015-03-26026 March 2015 PNO-III-15-003A: Update: Shutdown of Prairie Island Unit 2 Due to Loss of Instrument Air to Containment Building ML15069A1852015-03-10010 March 2015 PNO-III-15-003 Prairie Island Nuclear Plant: Shutdown of Prairie Island Unit 2 Due to Loss of Instrument Air to Containment Building and Notification of Unusual Event PNO-III-15-001, A: Update: Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage2015-02-17017 February 2015 PNO-III-15-001A: Update: Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage ML15028A0232015-01-27027 January 2015 PNO-III-15-001 - Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage PNO-III-14-012, A Update: Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage2014-12-29029 December 2014 PNO-III-14-012A Update: Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage ML14346A4682014-12-12012 December 2014 PNO-III-14-012 Shutdown of Prairie Island Unit 1 Due to Increasing Trend in Reactor Coolant System Leakage PNO-III-12-014, Notification of Unusual Event at Prairie Island Nuclear Generating Plant2012-11-0101 November 2012 PNO-III-12-014, Notification of Unusual Event at Prairie Island Nuclear Generating Plant ML12234A6382012-08-20020 August 2012 Update to Prairie Island Unit 1 Unplanned Shutdown Due to Both Emergency Diesel Generators Being Declared Inoperable ML12229A3572012-08-16016 August 2012 PNO-lll-12-008 - Prairie Island, Unit 1 Unplanned Shutdown Due to Both Emergency Diesel Generators Being Declared Inoperable PNO-III-11-013, A, Prairie Island Unit 2 Unplanned Shutdown for Greater than 72 Hours (Update)2011-10-20020 October 2011 PNO-III-11-013A, Prairie Island Unit 2 Unplanned Shutdown for Greater than 72 Hours (Update) ML1127804832011-10-0505 October 2011 PNO-III-11-013 - Prairie Island Unit 2 Unplanned Shutdown for Greater than 72 Hours PNO-III-10-002, Prairie Island Units 1 and 2, Fire in a Nonsafety-Related Diesel Generator2010-01-21021 January 2010 PNO-III-10-002, Prairie Island Units 1 and 2, Fire in a Nonsafety-Related Diesel Generator PNO-III-09-003, Prairie Island - Unplanned Unit 1 Shutdown Greater than 72 Hours2009-05-20020 May 2009 PNO-III-09-003: Prairie Island - Unplanned Unit 1 Shutdown Greater than 72 Hours PNO-III-08-007, A - Prairie Island, Unplanned Unit 1 Shutdown Greater than 72 Hours (Update)/ Notification of Unusual Event Due to a Release of a Toxic Gas Deemed Detrimental to Normal Operation of the Plant2008-08-0404 August 2008 PNO-III-08-007A - Prairie Island, Unplanned Unit 1 Shutdown Greater than 72 Hours (Update)/ Notification of Unusual Event Due to a Release of a Toxic Gas Deemed Detrimental to Normal Operation of the Plant ML0821408742008-08-0101 August 2008 PNO-III-08-007, Prairie Island Unit 1, Unplanned Unit 1 Shutdown Greater than 72 Hours/Special Inspection PNO-III-07-016, Prairie Island, Unplanned Unit 1 Shutdown Greater than 72 Hours2007-12-26026 December 2007 PNO-III-07-016: Prairie Island, Unplanned Unit 1 Shutdown Greater than 72 Hours PNO-III-07-005, Prairie Island Non-Credible Bomb Threat2007-03-20020 March 2007 PNO-III-07-005 - Prairie Island Non-Credible Bomb Threat PNO-III-06-003, Prairie Island Technical Specification Required Shutdown of Unit 2 for Greater than 72 Hours2006-02-0606 February 2006 PNO-III-06-003, Prairie Island Technical Specification Required Shutdown of Unit 2 for Greater than 72 Hours PNO-III-05-009, Technical Specification Required Shutdown of Prairie Island Unit 2 for Greater than 72 Hours2005-04-20020 April 2005 PNO-III-05-009, Technical Specification Required Shutdown of Prairie Island Unit 2 for Greater than 72 Hours 2023-06-08
[Table view] |
PRELIMINARY NOTIFICATION March 26, 2015 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE-PNO-III-15-003A This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information may not yet be fully verified or evaluated by the Region III staff.
Facility Licensee Emergency Classification Prairie Island Nuclear Plant Notification of Unusual Event Northern States Power Co. Alert Welch, MN Site Area Emergency Docket: 50-306 General Emergency License: DPR-60 X Not Applicable
SUBJECT:
UPDATE: SHUTDOWN OF PRAIRIE ISLAND UNIT 2 DUE TO LOSS OF INSTRUMENT AIR TO CONTAINMENT BUILDING Prairie Island Unit 2 was shut down on March 5, 2015, after a valve supplying instrument air to the containment building failed. Instrument air is used to operate many of the valves and components in the plant. Without instrument air, the plant was directed to be shut down by procedure.
During the shutdown process steam and water were released into the containment from a relief tank due to the activation of a rupture disk, an expected result given the loss of instrument air to the containment. Several thousand gallons of water drained into the Unit 2 containment building. This water was collected in the containment sump and was not released to the environment. After the shutdown, licensee staff and the NRC resident inspectors observed that the water had caused no significant damage to plant equipment. There was no risk to the public health and safety from this event.
On March 25, 2015, Prairie Island Unit 2 was restarted following completion of repairs to the failed valve and the pressure relief tank. The Resident Inspectors were on site and monitored portions of the startup activities.
This preliminary notification is issued for information only and no further action by the staff is anticipated. State officials have been informed.
The information presented herein has been discussed with the licensee, and is current as of 11:40 am CDT, on March 26, 2015.
ADAMS Accession Number: ML15085A284 CONTACT: Kenneth Riemer 630-829-9628 Kenneth.Riemer@nrc.gov