PNO-II-95-047, on 950802,plant Declared Unusual Event Due to Two Gpm Leak from 1A2 RCP Seal to Containment Sump.Unit 1 Shut Down in Mode 3 Preparing for Restart After Hurricane Erin Passed
| ML17228B233 | |
| Person / Time | |
|---|---|
| Site: | Saint Lucie |
| Issue date: | 08/03/1995 |
| From: | Schin R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| References | |
| PNO-II-95-047, PNO-II-95-47, NUDOCS 9508100062 | |
| Download: ML17228B233 (3) | |
I ~L~MA A I REGULAT ROM5IMMH'MT8uTBIGMTIO STEM
( RIDS )
4 ACCESSION NBR:9508100062 DOC.DATE: 95/08/03 NOTARIZED: NO FACIL:50-335 St. Lucie Plant, Unit 1, Florida Power
& Light Co.
AUTH.NAME AUTHOR AFFILIATION SCHINPR.
Region 2 (Post 820201)
RECIP.NAME RECIPIENT AFFILIATION DOCKET 05000335
SUBJECT:
PNO-II-95-047:on 950802,plant declared unusual event due to two GPM leak from 1A2 RCP seal to containment sump. Unit 1 shut down in Mode 3 preparing for restart after Hurricane Erin passed.
DISTRIBUTION CODE:
IE34D COPIES RECEIVED:LTR +ENCL g SIZE:
TITLE: Preliminary Notification-Occurrence/Non-Routine Event/Safeguards Even NOTES:
RECIPIENT ID CODE/NAME COPIES LTTR ENCL RECIPIENT ID CODE/NAME COPIES LTTR ENCL INTERNAL: ACRS NRR/DISP/PIPB NUDOCS-ABSTRACT RES/DRA RES/DSR DEPY RES/FMPAS RGN2 PILE 01 EXTERNAL: LITCO BRYCEgJ H
NRC PDR 1
E eENTER 1
NRR/DOTS/TERB 1
OE DIR 1
RES/DSIR/EIB 1
RES/DST 1
RES/RPHEB 1
NOAC NUDOCS FULL TXT NOTE TOALL "RIDS RECIPIEiiS:.
PLEASE HELP US TO REDUCE 'WASTE! COiNTACTTHE DOCUMENTCOYTROL DESK ROOhI Pl.37 IEXT F04.2083
> TO ELlhIIYATEYOUR NAME FROhI DISTRIBUTIONLISTS FOR DOCUh!ENTS YOU DON.'T NEED!
0 TOTAL NUMBER OF COPIES REQUIRED:
LTTR 1
ENCL 17 August 3,
1995 PRELIMINARY NOTIRICATIO OR EVVÃT OR UNUSUAL OCCURRENCE PNO-II-95-047 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance.
The information is as initially received without verification or evaluation, and is basically all that is known by Region II staff in Atlanta, Georgia on this date.
~Pacilic.t Florida Power 8 Light Co.
Saint Lucie 1 Hutchinson Island, Florida Dockets:
50-335 Licensee Emer enc Cla sification X Notification of Unusual Event Alert Site Area Emergency General Emergency Not Applicable
Subject:
STARTUP OF ST.
LUCIE UNIT 1 POSTPONED TO REPAIR PUMP SEAL On August 2, 1995, at 9:25 p.m.
(EDT) St. Lucie Unit 1 declared an Unusual Event due to a 2
GPM leak from the 1A2 reactor coolant pump seal to the containment, sump.
(See Event Number 29153.) Unit 1 is being cooled down to Mode 5 and depressurized for repairs.
At the time of this event, Unit 1 was shut down in Mode 3 preparing for restart after Hurricane Erin had passed.
The licensee estimates the outage duration to be about seven days.
The NRC resident inspectors are following the event.
The State of Florida has been notified of this event.
The NRC received notification of this event at 9:.58., p.m..(EDT). on.
August 2 by phone call to the NRC duty officer.
41 This information is current as of 9:30 a.m.
on August 3, 1995.
Contact:
R.
SCHIN (404)331-5561 9508100062 950803 PDR XSE PNQ-II-95-047 PDR D(
August 3,
1995 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-II-95-047 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance.
The information is as initially received without verification or evaluation, and is basically all that is known by Region II staff in Atlanta, Georgia on this date.
~Facility Florida Power 5 Light Co.
Saint Lucie 1
Hutchinson Island, Florida Dockets:
50-335 Licensee Emer enc Classification X Notification of Unusual Event Alert Site Area Emergency General Emergency Not Applicable
Subject:
STARTUP OF ST.
LUCIE UNIT 1 POSTPONED TO REPAIR PUMP SEAL On August 2, 1995, at 9:25 p.m.
(EDT) St.
Lucie Unit 1 declared an Unusual Event due to a 2
GPM leak from the lA2 reactor coolant pump seal to the containment sump.
(See Event Number 29153.) Unit 1 is being cooled down to Mode 5 and depressurized for repairs.
At the time of this
- event, Unit 1 was shut down in Mode 3 preparing for restart after Hurricane Erin had passed.
The licensee estimates the outage duration to be about seven days.
The NRC resident inspectors are following the event.
The State of Florida has been notified of this event.
The NRC received notification of this event at 9:58 p.m.
(EDT) on August 2 by phone call to the NRC duty officer.
This information is current as of 9:30 a.m.
on August 3, 1995.
Contact:
R.
SCHIN (404)331-5561