NRC Inspection Manual 0609/Appendix L

From kanterella
Jump to navigation Jump to search

text

Appendix L

B.5.b Significance Determination Process

1.0 OBJECTIVE

The objective of this SDP is to accommodate all potential more than minor inspection

findings associated with the development and implementation of guidance and

strategies intended to maintain or restore core cooling, containment, and spent fuel pool

cooling capabilities under the circumstances associated with loss of large areas of the

plant due to explosions or fire as required by Section B.5.b of the Interim Compensatory

Measures (ICM) Order, EA-02-026, dated February 25, 2002, the license conditions

imposed during the implementation of B.5.b, and 10 CFR 50.54(hh)(2) for findings after

March 31, 2010.

2.0 ENTRY CONDITIONS

Each issue entering the SDP process must first be screened to determine its

documentation threshold (i.e. if more than minor in significance) using Inspection

Manual Chapter (IMC) 0612, Appendix B, “Initial Screening.” Issues screened as minor

are not subjected to further SDP screening.

3.0 DEFINITIONS

B.5.b event – a beyond design basis loss of a large area of a reactor plant due to fires

or explosions initiated by a terrorist threat as stated in Attachment 2 to order EA-02-026.

Unrecoverable – an unavailable mitigating strategy is unrecoverable if licensee actions

could neither reasonably correct nor compensate for the conditions creating the

unavailability in time during a B.5.b event for the mitigating strategy to achieve its

objective. The time limit is the time allowed by NEI 06-12, Revision 2, for establishment

of the strategy where applicable, or a reasonable time.

Unavailability – a mitigating strategy is unavailable if its hardware or components are

not functional and ready for intended use, or personnel training and procedures are

inadequate, as described in the licensee submittal and SER supporting the B.5.b

license condition.

Note: These strategies for each operating reactor licensee were reviewed by the

staff who issued a safety evaluation report (SER) to document the commitments

to implement these strategies. The site specific responses delineating each

licensee’s commitment and the SERs are available through the B.5.b Community

of Practice. These responses are not available to the public due to the highly

sensitive nature for plant security contained in these responses.

Issue Date: 12/24/09 L-1 0609, App. L

4.0 GUIDANCE

Record the performance deficiency and factually describe known observations

associated with the deficiency in Table 1 - SDP Screening Worksheet for B.5.b.

Evaluation of the listed attributes may be informative in determining the significance of

the finding. Consider only attributes which relate directly to the significance of the

finding and document the basis for the consideration. If Table 1 is used to document a

performance deficiency and the factual description of the condition, the table will be

properly labeled as Official Use Only – Security Related Information.

TABLE 1 – SDP Screening Worksheet for B.5.b

Inspection Report #

Performance Deficiency (concise

statement clearly stating the deficient licensee

performance)

Factual Description of

Condition (facts about the condition that

resulted from the performance deficiency

without hypothetical failures included)

Systems/Trains Degraded by

Condition or Programmatic

Weakness (list the Hardware, Procedures

or Training)

Extent of Condition (describe what

other strategies are directly affected by the

deficiency)

Exposure Time (Period of time the

performance deficiency existed; and if

opportunity to identify the finding during such

period was missed (operating experience,

licensee=s programs such as surveillance

testing)

Recovery (The likelihood that the

licensee=s recovery actions would successfully

mitigate the performance deficiency)

Cornerstone (For findings that affect

core cooling select Mitigating Systems. For

findings that affect the containment or spent

fuel pool select Barrier Integrity)

____ Mitigating Systems ____ Barrier Integrity

The examples provided for each level of significance in Table 2 – Significance

Characterization, serve as guidance in determining the appropriate characterization for

findings; however, they are neither exhaustive nor controlling. The characterization of

each finding is dependent on the circumstances of the issue defined in Table 1. In

addition, these examples do not create new requirements. Each is intended to illustrate

the significance that the NRC places on a particular type of finding. Each potential

finding must be considered on its own merits to ensure that its significance is

characterized at the level best suited to the circumstances using qualitative engineering

judgment and regulatory oversight experience in each case. This is necessary because

the examples provided are intentionally limited to deter a mechanistic approach or

unreasoned conclusion. With this in mind, the entire spectrum of characterizations

should be considered with the particular finding placed in context in consideration of its

particular circumstances.

Issue Date: 12/24/09 L-2 0609, App. L

Issue Date: 12/24/09 L-3 0609, App. L

TABLE 2 – Significance Characterization

GREEN Unrecoverable unavailability of any individual mitigating strategy.

WHITE 1. Unrecoverable unavailability of multiple mitigating strategies such that SFP

cooling, injection to RPV, or injection to SGs cannot occur, or

2. Unrecoverable unavailability of on-site, self powered, portable pumping

capability, or

3. Substantial inability to perform Command and Control Enhancements.

Examples:

- Unrecoverable unavailability of injection to the reactor vessel or steam generators

(concurrent unavailability of low pressure pumping/depressurization strategies and

unavailability of manual operation of RCIC/Isolation Condenser or turbine (or

diesel) driven AFW)

- Unrecoverable unavailability of SFP internal strategy, SFP external fill strategy,

AND SFP external spray strategy

- Substantial inability to perform Command and Control Enhancements

YELLOW A failure to substantially establish mitigating strategies in one or more of the

following overall mitigating strategies areas:

- Fire fighting response strategies

- Operations to mitigate reactor core fuel damage including command and control

and actions to minimize release

- Operations to mitigate Spent Fuel Pool fuel damage including command and

control and actions to minimize release

RED In an actual B.5.b event, a substantial failure of mitigating strategies to function as

intended (i.e. achieve the strategies’ objectives) in one or more of the following

overall mitigating strategies areas:

- Fire fighting response strategies

- Operations to mitigate reactor core fuel damage including command and control

and actions to minimize release

- Operations to mitigate Spent Fuel Pool fuel damage including command and

control and actions to minimize release

ATTACHMENT 1 – Revision History for IMC 0609 Appendix L

Commitment

Tracking

Number

Issue

Date

Description of Change Training

Needed

Training

Completion

Date

Comment

Resolution

Accession

Number

N/A 12/24/09

CN 09-032

Researched commitments for 4 years and found

none. This Appendix to the IMC 0609,

“Significance Determination Process”

incorporates the lessons learned from the

performance of Temporary Instruction (TI)

2515/171 on Verification of Site Specification

Implementation of B.5.b Phase 2 & 3 Mitigation

Strategies and provides the framework for

determining the significance of B.5.b findings.

None N/A N/A

Issue Date: 12/24/09 Att1-1 0609 App. L, Att. 1