NRC 2003-0061, June 2003 Monthly Operating Report for Point Beach Units 1 & 2
| ML032040208 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 07/11/2003 |
| From: | Cayia A Nuclear Management Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, NRC 2003-0061 | |
| Download: ML032040208 (5) | |
Text
Committed to Nuclear Excellene Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2003-0061 GL 97-02 July 11, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 DOCKETS 50-266 AND 50-301 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 MONTHLY OPERATING REPORTS Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of June 2003.
Sincerely, Attachment cc: J. D. Loock, PSCW NRC Regional Administrator NRC Resident Inspector NRC Project Manager
, '2q 6590 Nuclear Road
- Two Rivers, Wisconsin 54241 Telephone: 920.755.2321
OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 07/02/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD June - 2003
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,343.0 235,942.4
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 4,343.0 232,401.5
- 5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 846.9
- 6. NET ELECTRICAL ENERGY (MWH) 366,566.5 2,215,812.5 107,767,121.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 7/02/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: June 2003 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUT1ING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F Administrative 5. Other (Explain)
G. Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit I average daily power for the month of June was 509.1 MWe.
Fish intrusion on 6/30/2003, reduced power to 95%
There was one LER on Unit I in the month of June, LER 266/2003-001 Degraded Grid Voltage Relays.
OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 07/02/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD June - 2003
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 518.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,297.0 230,050.1
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 4,255.4 227,021.1
- 5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 302.2
- 6. NET ELECTRICAL ENERGY (MWH) 368,435.5 2,153,594.5 106,941,398.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 7/02/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: June 2003 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSEICORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) I Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F Administrative 5. Other (Explain)
G .Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 2 average daily power for the month of June was 511.8 MWe.
Fish Intrusion on 6/30, reduced power to 91%
There was one LER on Unit 2 in the month of June, LER 266/2003-001 Degraded Grid Voltage Relays
Text
Committed to Nuclear Excellene Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2003-0061 GL 97-02 July 11, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 DOCKETS 50-266 AND 50-301 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 MONTHLY OPERATING REPORTS Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of June 2003.
Sincerely, Attachment cc: J. D. Loock, PSCW NRC Regional Administrator NRC Resident Inspector NRC Project Manager
, '2q 6590 Nuclear Road
- Two Rivers, Wisconsin 54241 Telephone: 920.755.2321
OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 07/02/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD June - 2003
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,343.0 235,942.4
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 4,343.0 232,401.5
- 5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 846.9
- 6. NET ELECTRICAL ENERGY (MWH) 366,566.5 2,215,812.5 107,767,121.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 7/02/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: June 2003 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUT1ING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F Administrative 5. Other (Explain)
G. Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit I average daily power for the month of June was 509.1 MWe.
Fish intrusion on 6/30/2003, reduced power to 95%
There was one LER on Unit I in the month of June, LER 266/2003-001 Degraded Grid Voltage Relays.
OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 07/02/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD June - 2003
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 518.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,297.0 230,050.1
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 4,255.4 227,021.1
- 5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 302.2
- 6. NET ELECTRICAL ENERGY (MWH) 368,435.5 2,153,594.5 106,941,398.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 7/02/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: June 2003 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSEICORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) I Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F Administrative 5. Other (Explain)
G .Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 2 average daily power for the month of June was 511.8 MWe.
Fish Intrusion on 6/30, reduced power to 91%
There was one LER on Unit 2 in the month of June, LER 266/2003-001 Degraded Grid Voltage Relays