NRC 2002-0106, November 2002 Monthly Operating Report for Point Beach Nuclear Plant, Units 1 & 2
| ML023540353 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 12/10/2002 |
| From: | Cayia A Nuclear Management Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, NRC 2002-0106 | |
| Download: ML023540353 (6) | |
Text
Nuclear Management Company, LLC Point Beach Nuclear Plant NMC Committed to Nuclear Excelle -> 66 10 Nuclear Road Two Rivers, WI 54241 NRC 2002-0106 GL 97-02 December 10, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:
Dockets 50-266 And 50-301 Point Beach Nuclear Plant, Units 1 And 2 Monthly Operating Reports Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of November 2002.
Sincerely, Jo 7 Site Vice President KML Attachment cc: J. D. Loock, PSCW NRC Region III NRC Senior Resident Inspector NRC Project Manager
Docket 50-266 and 50-301 NRC-2002-0106 ATTACHMENT 1 Letter from A. J. Cayia (NMC)
To Document Control Desk (NRC)
Re: Monthly Operating Reports
OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 12/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD November - 2002
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 510.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 7,245.6 230,855.4
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 7,220.5 227,314.5
- 5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 846.9
- 6. NET ELECTRICAL ENERGY (MWH) 363,682.0 3,601,571.0 105,177,091.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 12/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: November 2002 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) I Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)
G. Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 1 average daily power for the month of November was 505.1 MWe.
Licensee Event Reports (LERs) submitted to the NRC in November:
LER 266/2002-002-00 Unit 1 A-Train Reactor Protection Cable Routed in B-Train Cable Trays
OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 12/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD November - 2002
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 512.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 7,227.4 225,009.1
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 7,191.6 222,021.7
- 5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 302.2
- 6. NET ELECTRICAL ENERGY (MWH) 370,672.0 3,623,857.0 104,407,365.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 12/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: November 2002 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)
G .Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 2 average daily power for the month of October was 514.8 MWe.
There were no Licensee Event Reports (LERs) submitted to the NRC November:
Text
Nuclear Management Company, LLC Point Beach Nuclear Plant NMC Committed to Nuclear Excelle -> 66 10 Nuclear Road Two Rivers, WI 54241 NRC 2002-0106 GL 97-02 December 10, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:
Dockets 50-266 And 50-301 Point Beach Nuclear Plant, Units 1 And 2 Monthly Operating Reports Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of November 2002.
Sincerely, Jo 7 Site Vice President KML Attachment cc: J. D. Loock, PSCW NRC Region III NRC Senior Resident Inspector NRC Project Manager
Docket 50-266 and 50-301 NRC-2002-0106 ATTACHMENT 1 Letter from A. J. Cayia (NMC)
To Document Control Desk (NRC)
Re: Monthly Operating Reports
OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 12/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD November - 2002
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 510.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 7,245.6 230,855.4
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 7,220.5 227,314.5
- 5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 846.9
- 6. NET ELECTRICAL ENERGY (MWH) 363,682.0 3,601,571.0 105,177,091.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 12/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: November 2002 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) I Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)
G. Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 1 average daily power for the month of November was 505.1 MWe.
Licensee Event Reports (LERs) submitted to the NRC in November:
LER 266/2002-002-00 Unit 1 A-Train Reactor Protection Cable Routed in B-Train Cable Trays
OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 12/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD November - 2002
- 1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 512.0 MONTH YEAR TO DATE CUMULATIVE
- 3. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 7,227.4 225,009.1
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 720.0 7,191.6 222,021.7
- 5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 302.2
- 6. NET ELECTRICAL ENERGY (MWH) 370,672.0 3,623,857.0 104,407,365.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 12/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: November 2002 (Month/Year)
NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)
G .Operational Error (Explain) H .Other (Explain)
SUMMARY
Unit 2 average daily power for the month of October was 514.8 MWe.
There were no Licensee Event Reports (LERs) submitted to the NRC November: