NRC-96-0013, Forwards Fermi 2 Self-Assessment Plan SWS Operational Performance Insp (Swsopi), as follow-up to & 951214 Meeting.Functional Area Assessment Checklist Also Encl
| ML20100B873 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 01/24/1996 |
| From: | Gipson D DETROIT EDISON CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML20100B879 | List: |
| References | |
| CON-NRC-96-0013, CON-NRC-96-13 NUDOCS 9601290173 | |
| Download: ML20100B873 (2) | |
Text
l Drugtze R. Giptsn Seneot Vice President Nuclear Generaton Detroit re,,nm 6400 North Dixie Highway Edison ~(313)5865249 January 24,1996 NRC-96-0013 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D.C. 20555
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) NRC Letter to Detroit Edison," Documentation Request to Suppon the Fermi Service Water System Operational Performance Inspection (SWSOPI)," dated August 8,1995 1
- 3) Detroit Edison Letter to NRC, NRC-95-0087,"SWSOPI i
I Request For Reduced Scope Inspection", dated September 15, 1995
Subject:
SWSOPI Reauest For Reduced Scope Insoection. Self-Assessment Final Plan. Team Member Resumes. and Functional Area Checklists The August 8,1995, notice ofinspection letter (Reference 2) discussed the NRC's intent to perform a Service Water System Operational Performance Inspection (SWSOPI) at Detroit Edison's Fermi 2 plant in January of 1996. The letter also discussed a process which utilizes the results of licensee self-assessments conducted in accordance with guidance provided in NRC Inspection Procedure 40501 and for conducting a limited scope, in-depth inspection as an alternative to a full-scope NRC inspection.
In lieu of the full-scope NRC inspection, Detroit Edison proposed to perform a self-assessment of the Fermi 2 Emergency Service Water Systems and the drywell cooling interface portions of the General Service Water System (Reference 3). In addition, on December 14,1995, Fermi 2 personnel met with Region III NRC personnel to review the proposed scope of the Fermi 2 service water systems self-assessment, to provide a copy of the draft self-assessment plan, and to discuss the proposed self-assessment as it fits in with the overall i
Fermi 2 program to improve service water system maintainability and operational flexibility.
9601290173 960124 i
ADOCK0500g1 DR
\\
i
NRC-96-0013-January 24,1996 Page 2 This letter is a follow-up letter to Reference 3 and the December 14,1995, meeting to provide the final service water system self-assessment plan and the proposed functional area detailed self-assessment checklist. The resumes of the proposed self-assessment team members are being sent directly to Patricia Lougheed of NRC Region III.
Pending NRC approval, the actual self-assessment is proposed to start on February 26,1996.
If you have any further questions regarding this letter, please contact Ken Riches, Compliance Engineer at (313) 586-5529.
I Sincerely,
Enclosures:
1.
SWSOPI Self-Assessment Plan 2.
Functional Area Assessment Checklist cc:
T. G. Colburn M. Jordan I!. J. Miller F. Vegel Region III
_