NRC-88-0010, Monthly Operating Rept for Dec 1987

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Dec 1987
ML20147D895
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/31/1987
From: Anthony P, Orser W
DETROIT EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CON-NRC-88-0010, CON-NRC-88-10 NUDOCS 8801200348
Download: ML20147D895 (4)


Text

_ _ _ _ _ _ - _ _ _ _ _ _ _ _

OPERATING DATA REPORT COMPLETED BY P. M. Anthony DOCKET NO. 50-341 DATE January 15, 1988 TELEPHONE M )586-1617 OPERATING STATl]

i

1. UNIT NAME: Fermi 2 l Notes REPORTING PERIOD: December, 1987 l
2. l 3 LICENSED THERMAL POWER (MWt): 3292 I *To be deternined i 1154 l
4. NAMEPLATE RATING (GROSS MWe): l I

S. DESIGN ELECT RATING (Net MWe): 1093 I

  • l
6. MAX DEPENDABLE CAP (GROSS MWe): l
  • l l 7 MAX DEPENDABLE CAP (Net MWE):
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: None 9 POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net): 819.7
10. REASONS FOR RESTRICTION, IF ANY: Fermi 2 is in the startup test phase and is currently authorized to operate at power levels below 75% of rated th_ernal power.

THIS MONTH YR TO DATE CUMULATIVE

11. HRS IN REPORTING PERIOD 744 8760 24384
12. HRS REACTOR WAS CRITICAL 738.9 5147 5 6017.3 0 0 0
13. REACTOR RESERVE SHUTDOWN HRS
14. HOURS GENERATOR ON-LINE _

738.9 4084.2 4213 7 0 0 0

15. UNIT RESERVE SHUTDOWN HOURS _
16. GROSS THrRMAL ENERGY GEN (MWH) 1,515,768 5,988,912 6,212,160 479,050 1,573,593_ 1,584,043
17. GROSS ELECT ENERGY GEN (MWH)
18. NET ELECT ENERGY GEN (MWH) 452,683 1,547,226 1,366,842 N/A N/A N/A
19. UNIT SERVICE FACTOR _
20. UNIT AVAILABILITY FACTOR N/A N/A N/A
21. UNIT CAP FACTOR (USING MDC NET) N/A N/A N/A
22. UNIT CAP FACTOR (USING DER NET) N/A N/A N/A N/A N/A N/A
23. UNIT FORCED OUTAGE RATE
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURAT JN OF EAC.J There is a LLRT outage scheduled for March 1988. The outage will last forty five days.
25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CBITICALITY 06/20/85 06/21/85 INITIAL ELECTRIC!TY 10/01/86 09/21/86 COMMERCIAL OPERATION 8801200348 871231 -} t l' Af PDR ADOCK 05000341 'lt R DCD

~*

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-341 UNIT FERMI 2 DATE January 15, 1988 COMPLETED BY P. M. Anthony TELEPHONE (313) 586-1617 Nonth December, 1987 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGP DAILY POWER LEVEL (NWe-Net) (MWe-Net) 1 441 17 710 2 441 18 697 +

3 444 19 688 4 433 20 737 5' 438 _

21 718 6 442 22 760 7 441 23 541 8 432 24 583 i

9 512 25 722 I 10 626 26 711 4

11 594 27 779 12 551 28 752 13 567 29 706  :

14 608 30 747 15 691 31 779 16 691 1

[

i i

UNIT SPCJ1 DOWNS AND POWEN NEDUCIIONS DOCMET NO. 50-341 DATE January 15, l'387 UNIT NAME Feret 2 COMPLETED By P. M. Anthony TELEPHONE (313)S66-1617 REPORT MONTH December 1987 I i i I I I i l I I i l I l l  ! l METHOD OF l LER l Sv5 l COMP l CAUSE & CORRECTIVE I l NO. l DATE l TYPE ! OUR l REASON l SMUTTING DOWN l NO. 1 CODE l CODE l ACTION TO PREVENT l l l l (1) l (HRS)] (2) l THE REACTOR l l (4) l (5) l RECURRENCE l 1 i i I l l (3) l 1 l l 1 i l l l l 1  ! I i  !

I 1 1 I I I I I I I

! 87-18 l 12/31/87 l F l 5.13 l G l 3 187-056 l SJ l FIT During the Installation of a l 1 l l l l 8

l l l l Temporary modification. a lead I j j [ ] l l l [ l l grounded in error caused a false l l l l l l l l l l l demand signal for Increased Fecd- 1 l l l l l l l l l l water flow. This resulted in m

[ ] l l l l l l l l High Reactor Water Level. Turbine l l g l l l l l l l Control valve Fast Closure and l l 1 l l l l l l Reactor Trip. The Persunnel i l l l l l l l l l l involvwo .wre counseled. {

! 1 I I I  ! 1 1 I l __l (1) F: FORCED (2) REASON: ( 3 ) METHOD: (4) ENHIBIT G- INSTRUCTIONS S: SCHEDULED A - EQUIPMENT FAILURE fEXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE CR TES: 2 - MANUAL SCRAM ENTRV SHEETS FOR LICENSEE C - REFUELING 3 - AUTOMATIC SCRAM EVENT REPORT (LER) FILE D - REGULATORY RESTRICTION 4 - CONTINUED (NUREG-0161)

E - OPERATOR TRAINING & LICENSE EXAMINATION 5 - REDUCED LOAD F - ADMINISTRATIVE 9 - OTMER G.- OPERATIONAL ERROR (EMPLAIN)

H - OTHER (EXPLAIN) (5) EXHIBIT 1 - SAME SOURCE

  • 9 O

' 4- E'uMm S. OrSee Ec*da'IEf$xni Re. ouide 1.16 v.:

~~

Detrol,t r.,m ea30 Nar*h Due H,gh*ay Nuclear lQ IVO Ne port. M.cnigan 491f4 P 3 566'53* Operatsons January 15, 1998 NCC-88-0010

. S. Nuclear Regulatory Commission

<ttention: Document Control Desk Washington, D.C. 20555

Reference:

Fermi 2 NRC Dochet No. 50-341 NRC Jperating License Nu. NPF-43

Subject:

Monthly Operating. Status Report f,o r %e,ceber. 1987 Enclosed for your information and use is the Termi 2 Honthly Operating Status Report for December, 1987. This report Ircludee the Operating Data Report, A*/ e r a g e Dr. il y Unit Power Level, and ti Summary of Unit 3butdowos and Power Reductions identitied in NRC Regulatory Guide 1.16 and Fermi 2 Technical S pec if ic a tio n 6. 9.1. 6 If you have any questions, please contact Patricia Anthony at (313) 586-1617.

Sincerely)

W.

' fuW S. Orser Vice President Nuclear Operations Enclosure cc A. B. Davie J. R. Eckert E. G. Greenman D. R. Hahn W. G. Rogers J. J. Stefano f,

II