- s SNUPPS Standardized Nuclear Unit Power Mant System 5 Choke Cherry Road Nicholas A. Petrick R vI tend 20850 Executive Director March 10, 1983 SLNRC 83- 0014 FILE: 0541 SUBJ: Revision Eleven to SNUPPS FSAR Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatcry Commission Washington, D.C. 20555 Docket Nos: STN 50-482 and STN 50-483

References:

1) SLNRC 82-047, dated December 3,1982
2) SLNRC 83-004, dated February 2,1983
3) SLNRC 83-005, dated February 2,1983
4) SLNRC 83-006, dated February 2,1983 5 .SLNRC 82-003, dated August 4,1982 6 NUREG-0830, Callaway Safety Evaluation Report 7 NUREG-0881 Wolf Creek Safety Evaluation Report

Dear Mr. Denton:

Forwarded herewith are seventy-five (75) copies of Revision 11 of the Standardized Nuclear Unit Power Plant System (SNUPPS) FSAR.

This revision will be incorporated into the applications of the above dockets by amendments submitted by Kansas Gas and Electric Company and Union Electric Company.

This revision includes SNUPPS FSAR modifications based on the information previously transmitted in references 1, 2, 3 and 4.

The revision contains the information necessary to resolve, in whole or part, issues identified in references 6 and 7 as follows:

8303150503 830310 [

PDR ADOCK 05000482 1 K PDR A

SLNRC 83-Paga Two FSAR SECTION ISSUE Appendix 3A, Regulatory Ref. 6, Confinnatory 2 Guide 1.121 Ref. 7, Confinnatory B.2 7.4.3 Ref. 6, Confinnatory 9 Ref. 7, Confinnatory B.10 Q420.3 Ref. 6, Confinnatory 13 Ref. 7, Confinnatory B.14 Table 1.7 Ref. 6, Confirmatory 14,16,18,20,22 Ref. 7, Confirmatory B.15,B.17,B.19, B.21,B.23 Figure 8.3-1 Ref. 6, Confina.itory 19 Ref. 7, Confinnatory B.20 11.5.2.3.2.4 Ref. 6, Confinnatory 28, II.F.1 Attachment 3 Ref. 7, Confinnatory B.28, II.F.1 Attachment 3 Section 10.4 of the FSAR has been modified to show the addition of a motor driven feedwater pump to the main feedwater system.

In addition, Section 9.1.4 has been modified to describe the use of the spent fuel cask handling crane for maintenance and surveillance activities in the Fuel Building. The SNUPPS Heavy Loads Report (Reference 5) will be updated later to include this information.

The revision also includes minor updates and corrections of several FSAR sections.

Very truly yours, k-eN-w Nicholas A. Petrick MHF/bds/lb29

Attachment:

Revision 11 to SNUPPS FSAR cc: G. L. Koester KGE D. T. McPhee KCPL D. F. Schnell UE J. H. Neisler USNRC/ CAL H. W. Roberds USNRC/WC

.