Fermi 2 6400 North Dixie Hlwy., Newport, hil 48166 Detroit Edison Generic Letter 97-02 January 12, 2004 NRC-04-0003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555

Reference:

Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43

Subject:

Monthly Operating Status Report for December 2003 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for December 2003. This report includes the Operating Data Report and Summary of Unit Shutdowns identified in NRC Generic Letter 97-02 and Fermi 2 Technical Specification 5.6.4.

Should you have any questions or require additional information, please contact me at (734) 586-4258.

Sincerely, Norman A. Peterson Manager - Nuclear Licensing Enclosure cc: R. J. Aben, Jr.

H. K. Chemoff J. E. Dyer M. A. Ring M. V. Yudasz, Jr.

NRC Resident Office Region III I~hU A DTE Energy Company

OPERATING DATA REPORT DOCKET NO. 50-341 UNIT NAME Fermi 2 .

DATE Janua6v 12,2004 COMPLETED BY Kevin Burke TELEPHONE (734)

. 586-5148 REPORTING PERIOD: December 2003

1. Design Electrical Rating (MWe-Net) 1,150.00
2. Maximum Dependable Capacity (Mwe-Net) 1089.00 This Month Year-to-Date Cumulative
3. Number of Hours the Reactor Was Critical 744.0 7,614 107,896
4. Number of Hours Generator On-line 744.0 7.480 104,009
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWH) 831.137 8,127,822 104,623,568 UNIT SHUTDOWNS No. Date Type Duration Reason (1) Method of Cause and F: Forced (Hours) Shutting Corrective Action S: Scheduled Down (2) Comments N/A

SUMMARY

One planned downpower commenced on December 5, 2003, by reducing load to 60 percent for Turbine Bypass Valve Testing, Scram Time Testing, and Rod Pattern Adjustment. The unit was returned to full power on December 6, 2003.

(1) Reason: (2) Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training and License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Text

Fermi 2 6400 North Dixie Hlwy., Newport, hil 48166 Detroit Edison Generic Letter 97-02 January 12, 2004 NRC-04-0003 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555

Reference:

Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43

Subject:

Monthly Operating Status Report for December 2003 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for December 2003. This report includes the Operating Data Report and Summary of Unit Shutdowns identified in NRC Generic Letter 97-02 and Fermi 2 Technical Specification 5.6.4.

Should you have any questions or require additional information, please contact me at (734) 586-4258.

Sincerely, Norman A. Peterson Manager - Nuclear Licensing Enclosure cc: R. J. Aben, Jr.

H. K. Chemoff J. E. Dyer M. A. Ring M. V. Yudasz, Jr.

NRC Resident Office Region III I~hU A DTE Energy Company

OPERATING DATA REPORT DOCKET NO. 50-341 UNIT NAME Fermi 2 .

DATE Janua6v 12,2004 COMPLETED BY Kevin Burke TELEPHONE (734)

. 586-5148 REPORTING PERIOD: December 2003

1. Design Electrical Rating (MWe-Net) 1,150.00
2. Maximum Dependable Capacity (Mwe-Net) 1089.00 This Month Year-to-Date Cumulative
3. Number of Hours the Reactor Was Critical 744.0 7,614 107,896
4. Number of Hours Generator On-line 744.0 7.480 104,009
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWH) 831.137 8,127,822 104,623,568 UNIT SHUTDOWNS No. Date Type Duration Reason (1) Method of Cause and F: Forced (Hours) Shutting Corrective Action S: Scheduled Down (2) Comments N/A

SUMMARY

One planned downpower commenced on December 5, 2003, by reducing load to 60 percent for Turbine Bypass Valve Testing, Scram Time Testing, and Rod Pattern Adjustment. The unit was returned to full power on December 6, 2003.

(1) Reason: (2) Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training and License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)