NRC-02-0042, April 2002 Monthly Operating Report for Fermi 2

From kanterella
Jump to navigation Jump to search
April 2002 Monthly Operating Report for Fermi 2
ML021430300
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 05/08/2002
From: Peterson N
Detroit Edison
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-02-0042
Download: ML021430300 (4)


Text

Fermi 2 6400 North Dixie Hwy., Newport, MI 48166 Detroit Edison Reg. Guide 1.16 May 8, 2002 NRC-02-0042 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555

Reference:

Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43

Subject:

Monthly Operating Status Report for April 2002 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for April 2002. This report includes the Operating Data Report, Average Daily Unit Power Level, and the Summary of Unit Shutdowns and Power Reductions identified in NRC Regulatory Guide 1.16 and Fermi 2 Technical Specification 5.6.4.

Should you have any questions or require additional information, please contact me at (734) 586-4258.

Sincerely, Norman K. Peterson Manager - Nuclear Licensing Enclosures cc: J. E. Dyer T. J. Kim M. A. Ring M. V. Yudasz, Jr.

NRC Resident Office Region III A DTE Energy Company

OPERATING DATA REPORT DOCKET NO. 50-341 DATE May 8, 2002 COMPLETED BY Kevin Burke TELEPHONE (734) 586-5148 OPERATING STATUS

1.

Unit name: Fermi 2

2.

Reporting period: April 2002

3.

Licensed thermal power (MWt): 3430

4.

Nameplate rating (Gross MWe): 1217

5.

Design elect rating (Net MWe): 1150

6.

Max dependable cap (Gross MWe): 1140

7.

Max dependable cap (Net MWe): 1089

8.

If changes occur in capacity ratings (Items number 3 through 7) since last report, give reasons:

N/A

9.

Power level to which restricted, if any (MWe Net):

10.

Reasons for restrictions, if any:

N/A N/A THIS MONTH Hours in reporting period Hours reactor was critical Reactor reserve shutdown hours Hours generator on-line Unit reserve shutdown hours Gross thermal energy gen (MWH)

Gross elect energy gen (MWH)

Net elect energy gen (MWH)

Unit service factor Unit availability factor Unit cap factor (using MDC Net)

Unit cap factor (using DER Net)

Unit forced outage rate 719 719 0

719 0

2,312,568 781,140 749,798 100.0%

100.0%

95.8%

90.7%

0.0%

YEAR TO DATE 0

0 9,356,976 3,168,960 3,039,776 100.0%

100.0%

97.0%

91.8%

0.0%

CUMULATIVE 125,077 94,515 0

90,777 0

286,127,387 94,362,357 90,231,196 72.6%

72.6%

74.6% (1) 69.9% (1) 16.4%

24.

Shutdowns scheduled over next 6 months (Type, Date, Duration of each): N/A

25.

If shutdown at end of report period, estimated date of startup: N/A

26.

Units in test status (prior to commercial operation): N/A Notes: (1) Calculated using weighted averages to reflect variations in rating (MDC and DER) from initial commercial operation.

11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.

23.

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-341 UNIT Fermi 2 DATE May 8,2002 COMPLETED BY Kevin Burke TELEPHONE (734) 586-5148 Month April 2002 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER POWER LEVEL LEVEL (MWe-Net)

(MWe-Net) 1 556 16 1097 2

559 17 1095 3

560 18 1099 4

655 19 1099 5

1113 20 1118 6

1122 21 1123 7

1121 22 1124 8

1116 23 1124 9

1113 24 1118 10 1115 25 1117 11 1121 26 1122 12 1108 27 1119 13 1117 28 1112 14 1119 29 1096 15 1100 30 1043

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO:

UNIT NAME:

DATE:

50-341 Fermi 2 May 8, 2002 COMPLETED BY:

TELEPHONE:

Kevin Burke (734) 586-5148 REPORT MONTH April 2002 No. (6)

Date TYPE Dur (Hrs) (7)

Reason (2)

Method of LER Sys Code (4)

Comp Cause and Corrective Action to (1) shutting down No.

Code (5)

Prevent Recurrence reactor or reducing power (3)

R02-04 04/01/02 F

0 A

9 N/A AD MG Reactor Recirculation Motor Generator set tripped due to field ground at exciter brush gear.

(2)

REASON:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operations Training and License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

(3)

METHOD:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 - Reduced Load 9 - Other (4)

Instructions for preparation of data entry sheets for Licensee Event Report (LER) file (NUREG 1022)

(5)

Same Source as (4)

(6)

R - Prefix indicates power reduction.

S - Prefix indicated plant shutdown.

(7)

Duration of reductions reported as zero per Regulatory Guide 1.16, Revision 4.

(1)

F: Forced S: Scheduled