Entergy'S Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - 1.5..
ML13260A144
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 09/12/2013
From: Ventosa J
Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-13-118
Download: ML13260A144 (3)


Text

Enterqy Nuclear Northeast

--En tergy Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 John A Ventosa Site Vice President NL-13-118 September 12, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738

SUBJECT:

Entergy's Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - 1.5 Year Response for CEUS Sites Indian Point Unit Nos. 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64

REFERENCES:

1. NRC letter to Entergy, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident, dated March 12, 2012 (ML12053A340).
2. NRC Letter, Endorsement of EPRI Final Draft Report 1025287, "Seismic Evaluation Guidance," dated February 15, 2013 (ML12319A074)
3. EPRI Report 1025287, Seismic Evaluation Guidance: Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1:

Seismic (ML12333A170)

4. NEI Letter to NRC, Proposed Path Forward for NTTF Recommendation 2.1: Seismic Reevaluations, dated April 9, 2013 4u -

NL-13-118 Docket Nos. 50-247 and 50-286 Page 2 of 3

5. NRC Letter, EPRI Final Draft Report XXXXXX (now 300200704),

"Seismic Evaluation Guidance: Augmented Approach for the Resolution of Near-Term Task Force Recommendation 2.1:

Seismic," as an Acceptable Alternative to the March 12, 2012, Information Request for Seismic Reevaluations, dated May 7, 2013 (ML13106A331)

6. Entergy letter to NRC, Response to NRC Request For Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated April 29, 2013 (NL-13-069)

Dear Sir or Madam:

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference 1 to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 1 of Reference 1 requested each addressee in the Central and Eastern United iStates (CEUS) to submit a written response consistent with the requested seismic hazard evaluation information (items 1 through 7) by September 12, 2013. On February 15, 2013, NRC issued Reference 2, endorsing the Reference 3 industry guidance for responding to Reference 1. Section 4 of Reference 3 identifies the detailed information to be included in the seismic hazard evaluation submittals.

On April 9, 2013, NEI submitted Reference 4 to NRC, requesting NRC agreement to delay submittal of some of the CEUS seismic hazard evaluation information so that an update to the EPRI (2004, 2006) ground motion attenuation model could be completed and used to develop that information. NEI proposed that descriptions of subsurface materials and properties and base case velocity profiles (items 3a and 3b in Section 4 of Reference 3) be submitted to NRC by September 12, 2013, with the remaining seismic hazard and screening information submitted to NRC by March 31, 2014. In Reference 5, NRC agreed with this recommendation. Reference 6 contained Entergy's commitment to follow the approach described in Reference 4.

The requested descriptions of subsurface materials and properties and base case velocity profiles for Indian Point Energy Center provided by EPRI is:

"The basic information used to evaluate the site geologic profile at the Indian Point site is taken from Ref. 1. The basis for this profile information is given in Ref. 1. The site geologic profile indicates that hard rock (shear-wave velocity exceeding 9200 ft/sec) underlies the site. As a result, the Indian Point site was treated as a hard-rock site and no site amplification factors were calculated for the site.

References

1. Entergy Corp. (2012). Site Geologic Report for Indian Point No. 2 and Indian Point No. 3 Nuclear Power Plants,informal report transmitted July, 2012, to Electric Power Research Institute."

NL-13-118 Docket Nos. 50-247 and 50-286 Page 3 of 3 The Site Geologic Report for Indian Point No. 2 and Indian Point No. 3 Power Plants was developed based on information contained in the FSARs, augmented with results from work performed in conjunction with the ISFSI concrete pad installation. The rocks in the vicinity of the Indian Point generating stations belong to three geologic provinces, the Hudson Highlands, the Manhattan Prong and the Newark Basin. Rocks that outcrop within the provinces range in age from Precambrian through Triassic or Jurassic.

There are no new commitments identified in this submittal. If you have any questions concerning the content of this letter, please contact Mr. Robert Walpole, Manager, Licensing at (9,14) 254-6710.

I declare under penalty of perjury that the foregoing is true and correct. Executed on September .. , 2013.

Respectfully, JAV/sp cc: Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 NRC Resident Inspectors Office Mr. Francis J. Murray, Jr., President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service