NL-08-0746, Notification of Deviation from BWRVIP-76

From kanterella
Jump to navigation Jump to search

Notification of Deviation from BWRVIP-76
ML081400658
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 05/19/2008
From: David Jones
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-08-0746, TAC MD6369
Download: ML081400658 (2)


Text

David H. Jones Southern Nuclear Vice President Operating Company. Inc.

Engineering 40 Inverness Center Parkway Birmingham. Alabama 35242 Tel 205.992.5984 Fax 205.992.0341 SOUTHERNA May 19, 2008 COMPANY Energy to Serve lOurWorlJSN.

Docket No.: 50-321 NL-08-0746 U. S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Unit 1 Notification of Deviation from BWRVIP-76 Ladies and Gentlemen:

In accordance with an agreement with the Boiling Water Reactor Vessel Improvement Program (BWRVIP), participating licensees will notify the NRC staff within 45 days of a decision by the licensee to not fully implement the approved guidance. Plant Hatch-Unit 1 will not fUlly implement the subject guidance with respect to examination of horizontal welds on the Core Shroud contained in BWRVIP-76.

During the Plant Hatch-Unit 1 Refueling Outage 22, upper support arms at two of the four core shroud stabilizer locations were found with indications, one at 135 degrees and one at 225 degrees. Southern Nuclear Operating Company (SNC) resolved those indications by performing examination and evaluation of core shroud horizontal welds which determined that sufficient shroud horizontal weld ligament was present and acceptable for at least a cycle of operation. SNC then submitted a shroud stabilizer modification design that would have replaced the four upper supports with an improved design. This design was intended for implementation during the Plant Hatch-Unit 1 Refueling Outage 23 and was approved by the NRC staff by safety evaluation (TAC NO. MD6396).

As documented in SNC NL-08-0350, dated March 8, 2008, two of the four upper supports were not replaced and permission was requested to postpone the replacement until the Plant Hatch-Unit 1 Refueling Outage 24. The two locations (225 degrees and 45 degrees) were successfully reassembled. However, the location at azimuth 225 degrees contained the indication previously identified during Plant Hatch-Unit 1 Refueling Outage 22. The indication was visually reexamined and was evaluated to have grown at approximately half the rate assumed for the comparable evaluation following Plant Hatch-Unit 1 Refueling Outage 22. Additionally, the 45 degree location was visually examined with no indications recorded. An evaluation established that the 225 degree upper support will not become a loose part during the next fuel cycle. Shroud horizontal weld ultrasonic examinations were employed that established the structural integrity of the shroud for the additional fuel cycle.

U. S. Nuclear Regulatory Commission NL-08-0746 Page 2 Core Shroud BWRVIP Inspection and Evaluation Guidelines (BWRVIP-76) specify an inspection scope of 100 percent of the accessible horizontal welds.

Examination of 100 percent of.the accessible areas of the horizontal welds was not performed for the following reasons:

  • justifying a long term interval for re-inspection was not the objective;
  • the limited availability of inspection equipment and qualified personnel;
  • the emergent nature of the examinations.

Based on the criteria in BWRVIP-76 Appendix 0, an ultrasonic examination scope was determined to ensure the remaining ligament needed for an additional operating cycle existed on welds H1 through H7. Examination results were applied to flaw evaluations to provide assurance that the horizontal welds will provide the necessary structural support until the shroud stabilizer modification can be completed during the Plant Hatch-Unit 1 Refueling Outage 24.

The deviation from the BWRVIP guidelines has been prepared. reviewed, and approved in accordance with SNC internal procedures. The review provides assurance that there are no safety implications or reliability concerns with the deviations. The shroud and shroud stabilizer recovery efforts and results, including this deviation, were discussed in various teleconferences between SNC, NRC NRR, and NRC Region II.

This letter contains no NRC commitments. If you have any questions, please advise.

O. H. Jones Vice President - Engineering OHJ/PAH/daj cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. O. R. Madison, Vice President - Hatch RTYPE: CHA02.004 U. S. Nuclear Regulatorv Commission Mr. L. A. Reyes, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Hatch Mr. J. A. Hickey, Senior Resident Inspector - Hatch