Entergy Enterav Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Fred Dacimo Site Vice President Tel 914 734 6700 September 26, 2005 Re: Indian Point Unit 2 Docket No. 50-247 NL-05-1 08 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-Pl-17 Washington, DC 20555-0001
Subject:
Clarification to RAI regarding Fuel Storage Building Single-Failure-Proof Gantry Crane
Reference:
- 1. Entergy letter dated April 12, 2005, "Reply to RAI regarding Amendment Application for Fuel Storage Building Gantry Crane' (NL-05-030)
Dear Sir/Madam:
Entergy Nuclear Operations (Entergy), Inc. is providing a clarification to the referenced response to the NRC request for additional information (RAI) regarding the proposed license amendment request for new Fuel Storage Building Single-Failure-Proof Gantry Crane for Indian Point Unit 2. The purpose of this clarification is to remove the first two sentences of the second paragraph from Reference 1 (Attachment 1 to NL-05-030, Question 2 Response), and replace with the following:
The new Gantry Crane movements are controlled by a series of limit and proximity switches. The protection provided by these switches is as follows:
There are no new commitments identified in this submittal. If you have any questions regarding this matter, please contact Mr. Patric Conroy, Manager, Licensing at (914) 734-6668.
(Db
rid 1;
NL-05-1 08 Docket No. 50-247 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on the c2laoh day of September, 2005.
Fred R. Dacimo Site Vice President Indian Point Energy Center cc: