NL-02-109, July 2002 Monthly Operating Report for Indian Point Unit 2

From kanterella
(Redirected from NL-02-109)
Jump to navigation Jump to search
July 2002 Monthly Operating Report for Indian Point Unit 2
ML022320625
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 08/15/2002
From: Dacimo F
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-02-109
Download: ML022320625 (5)


Text

Entergy Nuclear Northeast Ente E t-v.cierE itns. Inc P Pr X ;

5,te August 15, 2002 Re: Indian Point Unit No. 2 Docket No. 50-247 NL-02-109 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station O-P1 -17 Washington, DC 20555-0001

Subject:

Monthly Operating Report - July 2002

Dear Sir:

Enclosed is the Monthly Operating Report for Indian Point Unit No. 2 for July 2002.

There are no commitments contained in this letter.

Should you have any questions regarding this matter, please contact Mr. John McCann, Manager, Licensing, Indian Point Energy Center (914) 734-5074.

Sin r f1d Dacimo Vice President - Operations Indian Point 2 Enclosure cc: Mr. Hubert J. Miller Regional Administrator - Region I US Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1498 Senior Resident Inspector US Nuclear Regulatory Commission Indian Point Unit 2 P0 Box 38 Buchanan, NY 10511 Mr. Paul Eddy State of New York Department of Public Service 3 Empire Plaza Albany, NY 12223

NL-02-109 Enclosure Page 1 of 4 OPERATING DATA REPORT DOCKET NO. 50-247 DATE August 6, 2002 COMPLETED BY K. Krieger TELEPHONE (914)734-5146 OPERATING STATUS

1. Unit Name: INDIAN POINT UNIT No. 2 Notes
2. Reporting Period: July-2002
3. Licensed Thermal Power ( MWt): 3071.4
4. Nameplate Rating ( Gross Mwe): 1008
5. Design Electrical Rating ( Net Mwe): 986
6. Maximum Dependable Capacity ( Gross Mwe): 965
7. Maximum Dependable Capacity (Net Mwe ): 931
8. If Changes Occur in Capacity Ratings ( Items Number 3 Through 7 ) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any ( Net Mwe):
10. Reasons For Restrictions , If Any:

This Month Yr.-to-Date Cumulative

11. Hours In Reporting Period 744 5,087 246,192
12. Number Of Hours Reactor Was Critical 744 5,087 171,587.75
13. Reactor Reserve Shutdown Hours 0 0 4,566.64
14. Hours Generator On-Line 744 5,087 167,728.05
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated ( MWH) 2,277,308 15,531,273 472,043,676
17. Gross Electrical Energy Generated ( MWH) 736,455 5,125,728 147,372,618
18. Net Electrical Energy Generated ( MWH) 711,109 4,954,765 141,177,687
19. Unit Service Factor 100.0 100.0 68.1
20. Unit Availability Factor 100.0 100.0 68.1
21. Unit Capacity Factor ( Using MDC Net) 102.7 103.6 64.2
22. Unit Capacity Factor ( Using DER Net) 96.9 98.8 62.1
23. Unit Forced Outage Rate 0 0 14.0
24. Shutdowns Scheduled Over Next 6 Months ( Type , Date , and Duration Of Each ) :

Refueling and maintenance outage scheduled for October 26, 2002 for a duration of approximately 35 days.

25. If Shut Down At End Of Report Period, Estimated Date Of Startup:
26. Units In Test Status ( Prior to Commercial Operation ) : Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A (9/77)

NL-02-109 Enclosure Page 2 of 4 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-247 UNIT I.P. Unit #2 DATE August 6, 2002 COMPLETED BY K. Krieger TELEPHONE (914)734-5146 MONTH July-2002 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 964 17 957 2 964 18 961 3 960 19 944 4 958 20 955 5 959 21 954 6 961 22 953 7 962 23 954 8 960 24 954 9 961 25 951 10 960 26 949 11 958 27 949 12 959 28 950 13 952 29 946 14 961 30 948 15 959 31 947 16 959 INSTRUCTIONS On this format , list the average daily unit power level in Mwe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

(9/77)

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-247 UNIT I.P. Unit #2 DATE August 6, 2002 COMPLETED BY K. Krieger REPORT MONTH July-2002 TELEPHONE (914)734-5146

-- "0 o Licensee 0 U No. Date "0 '  : Event E Cause & Corrective Action to Prevent Recurrence Q 04 Report## a NONU NONE -- - - ---

I 2 3 4 F: Forced Reason: Method : Exibit G - Instructions S : Scheduled A - Equipment Failure ( Explain) I - Manual for Preparation of Data B - Maintenance or Test 2 - Manual Scram Entry Sheets for Licensee C - Refueling 3 - Automatic Scram Event Report ( LER ) File ( NUREG-0161)

D - Regulatory Restriction 4 - Other (Explain )

E - Operator Training & License Examination 5 F - Administrative Exibit I - Same Source G - Operational Error (Explain)

H - Other ( Explain) 0 (9/77)

NL-02-109 Enclosure Page 4 of 4

SUMMARY

OF OPERATING EXPERIENCE July 2002 Unit 2 operated at full power for the entire month of July 2002.

Major Safety Related Maintenance DATE W.O # SYSTEM COMPONENT COMPLETED WORK PERFORMED IP2-02-24105 IE N-35 7/2/2002 Replaced intermediate range channel power suppiy.