|
---|
Category:License-Monthly Operating Report
MONTHYEARNL-05-045, March 2005 Monthly Operating Report for Indian Point Units, 2 and 32005-04-15015 April 2005 March 2005 Monthly Operating Report for Indian Point Units, 2 and 3 NL-05-028, February 2005 Monthly Operating Report for Indian Point Units 2 and 32005-03-15015 March 2005 February 2005 Monthly Operating Report for Indian Point Units 2 and 3 NL-05-018, January 2005 Monthly Operating Report for Indian Point Unit 2 and 32005-02-15015 February 2005 January 2005 Monthly Operating Report for Indian Point Unit 2 and 3 NL-05-005, December 2004 Monthly Operating Report for Indian Point, Units 2 & 32005-01-15015 January 2005 December 2004 Monthly Operating Report for Indian Point, Units 2 & 3 NL-04-152, November 2004 Monthly Operating Report, Indian Point Units 2 and 32004-12-15015 December 2004 November 2004 Monthly Operating Report, Indian Point Units 2 and 3 NL-04-142, October 2004 Monthly Operating Report for Indian Point Unit Nos 2 and 32004-11-15015 November 2004 October 2004 Monthly Operating Report for Indian Point Unit Nos 2 and 3 NL-04-128, September 2004 Monthly Operating Report for Indian Point Units 2 & 32004-10-14014 October 2004 September 2004 Monthly Operating Report for Indian Point Units 2 & 3 NL-04-113, August 2004 Monthly Operating Report for Indian Point Unit 2 and 32004-09-10010 September 2004 August 2004 Monthly Operating Report for Indian Point Unit 2 and 3 NL-04-099, July 2004 Monthly Operating Report for Indian Point Units 2 and 32004-08-13013 August 2004 July 2004 Monthly Operating Report for Indian Point Units 2 and 3 NL-04-083, June 2004 Monthly Operating Report for Indian Point Units 2 and 32004-07-14014 July 2004 June 2004 Monthly Operating Report for Indian Point Units 2 and 3 NL-04-053, April 2004 Monthly Operating Report for Indian Point Units 2 and 32004-05-13013 May 2004 April 2004 Monthly Operating Report for Indian Point Units 2 and 3 NL-04-035, March 2004 Monthly Operating Report for Indian Point, Units 2 & 32004-04-12012 April 2004 March 2004 Monthly Operating Report for Indian Point, Units 2 & 3 NL-04-024, February 2004 Monthly Operating Report for Indian Point Units 2 and 32004-03-12012 March 2004 February 2004 Monthly Operating Report for Indian Point Units 2 and 3 NL-04-017, January 2004 Monthly Operating Report for Indian Point Units 2 & 32004-02-12012 February 2004 January 2004 Monthly Operating Report for Indian Point Units 2 & 3 NL-04-004, December 2003 Monthly Operating Report for Indian Point, Units 2 and 32004-01-15015 January 2004 December 2003 Monthly Operating Report for Indian Point, Units 2 and 3 NL-03-185, November 2003 Monthly Operating Report for Indian Point, Unit 32003-12-15015 December 2003 November 2003 Monthly Operating Report for Indian Point, Unit 3 NL-03-184, November 2003 Monthly Operating Report for Indian Point, Unit 22003-12-15015 December 2003 November 2003 Monthly Operating Report for Indian Point, Unit 2 NL-03-175, October 2003 Monthly Operating Report for Indian Point Unit 22003-11-13013 November 2003 October 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-176, October 2003 Monthly Operating Report for Indian Point 32003-11-13013 November 2003 October 2003 Monthly Operating Report for Indian Point 3 NL-03-162, September 2003 Monthly Operating Report for Indian Point Unit 32003-10-15015 October 2003 September 2003 Monthly Operating Report for Indian Point Unit 3 NL-03-161, September 2003 Monthly Operating Report for Indian Point 22003-10-15015 October 2003 September 2003 Monthly Operating Report for Indian Point 2 NL-03-143, August 2003 Monthly Operating Report for Indian Point Unit 22003-09-12012 September 2003 August 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-144, August 2003 Monthly Operating Report for Indian Point, Unit 32003-09-12012 September 2003 August 2003 Monthly Operating Report for Indian Point, Unit 3 NL-03-132, July 2003 Monthly Operating Report for Indian Point, Unit 32003-08-12012 August 2003 July 2003 Monthly Operating Report for Indian Point, Unit 3 NL-03-131, July 2003 Monthly Operating Report for Indian Point Unit 22003-08-12012 August 2003 July 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-121, June 2003 Monthly Operating Report for Indian Point 3 Nuclear Power Plant2003-07-15015 July 2003 June 2003 Monthly Operating Report for Indian Point 3 Nuclear Power Plant NL-03-120, June 2003 Monthly Operating Report for Indian Point Unit 22003-07-15015 July 2003 June 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-101, May 2003 Monthly Operating Report for Indian Point Unit 22003-06-12012 June 2003 May 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-100, May 2003 Monthly Operating Report for Indian Point 32003-06-12012 June 2003 May 2003 Monthly Operating Report for Indian Point 3 ML0313900202003-05-15015 May 2003 April 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-083, April 2003 Monthly Operating Report for Indian Point 32003-05-15015 May 2003 April 2003 Monthly Operating Report for Indian Point 3 NL-03-062, March 2003 Monthly Operating Report for Indian Point Unit No. 22003-04-15015 April 2003 March 2003 Monthly Operating Report for Indian Point Unit No. 2 NL-03-063, March 2003 Monthly Operating Report for Indian Point 3 Nuclear Power Plant2003-04-15015 April 2003 March 2003 Monthly Operating Report for Indian Point 3 Nuclear Power Plant NL-03-045, February 2003 Monthly Operating Report for Indian Point Unit 22003-03-13013 March 2003 February 2003 Monthly Operating Report for Indian Point Unit 2 NL-03-046, February 2003 Monthly Operating Report for Indian Point 32003-03-13013 March 2003 February 2003 Monthly Operating Report for Indian Point 3 NL-03-028, January 2003 Monthly Operating Report for Indian Point 32003-02-14014 February 2003 January 2003 Monthly Operating Report for Indian Point 3 NL-03-027, January 2003 Monthly Operating Report for Indian Point, Unit 22003-02-14014 February 2003 January 2003 Monthly Operating Report for Indian Point, Unit 2 NL-03-010, December 2002 Monthly Operating Report for Indian Point Unit 22003-01-15015 January 2003 December 2002 Monthly Operating Report for Indian Point Unit 2 NL-03-011, December 2002 Monthly Operating Report for Indian Point 32003-01-15015 January 2003 December 2002 Monthly Operating Report for Indian Point 3 ML0236505202002-12-13013 December 2002 November 2002 Monthly Operating Report for Indian Point 3 ML0235203372002-12-13013 December 2002 November 2002 Monthly Operating Report for Indian Point Unit 3 NL-02-159, November 2002 Monthly Operating Report for Indian Point Unit 22002-12-12012 December 2002 November 2002 Monthly Operating Report for Indian Point Unit 2 NL-02-144, October 2002 Monthly Operating Report for Indian Point Unit No.22002-11-14014 November 2002 October 2002 Monthly Operating Report for Indian Point Unit No.2 NL-02-134, September 2002 Monthly Operating Report for Indian Point Unit 22002-10-15015 October 2002 September 2002 Monthly Operating Report for Indian Point Unit 2 ML0229100412002-10-11011 October 2002 September 2002 Monthly Operating Report for Indian Point 3 ML0231804322002-10-0707 October 2002 October 2002 Monthly Operating Report for Indian Point 3 ML0226203452002-09-12012 September 2002 August 2002 Monthly Operating Report for Indian Point Unit 3 NL-02-120, August 2002 Monthly Operating Report for Indian Point Unit 22002-09-12012 September 2002 August 2002 Monthly Operating Report for Indian Point Unit 2 NL-02-109, July 2002 Monthly Operating Report for Indian Point Unit 22002-08-15015 August 2002 July 2002 Monthly Operating Report for Indian Point Unit 2 ML0224001702002-08-0808 August 2002 July 2002 Monthly Operating Report for Indian Point 3 2005-04-15
[Table view] |
Text
Entergy Nuclear Northeast Ente E t-v.cierE itns. Inc P Pr X ;
5,te August 15, 2002 Re: Indian Point Unit No. 2 Docket No. 50-247 NL-02-109 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station O-P1 -17 Washington, DC 20555-0001
Subject:
Monthly Operating Report - July 2002
Dear Sir:
Enclosed is the Monthly Operating Report for Indian Point Unit No. 2 for July 2002.
There are no commitments contained in this letter.
Should you have any questions regarding this matter, please contact Mr. John McCann, Manager, Licensing, Indian Point Energy Center (914) 734-5074.
Sin r f1d Dacimo Vice President - Operations Indian Point 2 Enclosure cc: Mr. Hubert J. Miller Regional Administrator - Region I US Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1498 Senior Resident Inspector US Nuclear Regulatory Commission Indian Point Unit 2 P0 Box 38 Buchanan, NY 10511 Mr. Paul Eddy State of New York Department of Public Service 3 Empire Plaza Albany, NY 12223
NL-02-109 Enclosure Page 1 of 4 OPERATING DATA REPORT DOCKET NO. 50-247 DATE August 6, 2002 COMPLETED BY K. Krieger TELEPHONE (914)734-5146 OPERATING STATUS
- 1. Unit Name: INDIAN POINT UNIT No. 2 Notes
- 2. Reporting Period: July-2002
- 3. Licensed Thermal Power ( MWt): 3071.4
- 4. Nameplate Rating ( Gross Mwe): 1008
- 5. Design Electrical Rating ( Net Mwe): 986
- 6. Maximum Dependable Capacity ( Gross Mwe): 965
- 7. Maximum Dependable Capacity (Net Mwe ): 931
- 8. If Changes Occur in Capacity Ratings ( Items Number 3 Through 7 ) Since Last Report, Give Reasons:
- 9. Power Level To Which Restricted, If Any ( Net Mwe):
- 10. Reasons For Restrictions , If Any:
This Month Yr.-to-Date Cumulative
- 11. Hours In Reporting Period 744 5,087 246,192
- 12. Number Of Hours Reactor Was Critical 744 5,087 171,587.75
- 13. Reactor Reserve Shutdown Hours 0 0 4,566.64
- 14. Hours Generator On-Line 744 5,087 167,728.05
- 15. Unit Reserve Shutdown Hours 0 0 0
- 16. Gross Thermal Energy Generated ( MWH) 2,277,308 15,531,273 472,043,676
- 17. Gross Electrical Energy Generated ( MWH) 736,455 5,125,728 147,372,618
- 18. Net Electrical Energy Generated ( MWH) 711,109 4,954,765 141,177,687
- 19. Unit Service Factor 100.0 100.0 68.1
- 20. Unit Availability Factor 100.0 100.0 68.1
- 21. Unit Capacity Factor ( Using MDC Net) 102.7 103.6 64.2
- 22. Unit Capacity Factor ( Using DER Net) 96.9 98.8 62.1
- 23. Unit Forced Outage Rate 0 0 14.0
- 24. Shutdowns Scheduled Over Next 6 Months ( Type , Date , and Duration Of Each ) :
Refueling and maintenance outage scheduled for October 26, 2002 for a duration of approximately 35 days.
- 25. If Shut Down At End Of Report Period, Estimated Date Of Startup:
- 26. Units In Test Status ( Prior to Commercial Operation ) : Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A (9/77)
NL-02-109 Enclosure Page 2 of 4 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-247 UNIT I.P. Unit #2 DATE August 6, 2002 COMPLETED BY K. Krieger TELEPHONE (914)734-5146 MONTH July-2002 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 964 17 957 2 964 18 961 3 960 19 944 4 958 20 955 5 959 21 954 6 961 22 953 7 962 23 954 8 960 24 954 9 961 25 951 10 960 26 949 11 958 27 949 12 959 28 950 13 952 29 946 14 961 30 948 15 959 31 947 16 959 INSTRUCTIONS On this format , list the average daily unit power level in Mwe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-247 UNIT I.P. Unit #2 DATE August 6, 2002 COMPLETED BY K. Krieger REPORT MONTH July-2002 TELEPHONE (914)734-5146
-- "0 o Licensee 0 U No. Date "0 ' : Event E Cause & Corrective Action to Prevent Recurrence Q 04 Report## a NONU NONE -- - - ---
I 2 3 4 F: Forced Reason: Method : Exibit G - Instructions S : Scheduled A - Equipment Failure ( Explain) I - Manual for Preparation of Data B - Maintenance or Test 2 - Manual Scram Entry Sheets for Licensee C - Refueling 3 - Automatic Scram Event Report ( LER ) File ( NUREG-0161)
D - Regulatory Restriction 4 - Other (Explain )
E - Operator Training & License Examination 5 F - Administrative Exibit I - Same Source G - Operational Error (Explain)
H - Other ( Explain) 0 (9/77)
NL-02-109 Enclosure Page 4 of 4
SUMMARY
OF OPERATING EXPERIENCE July 2002 Unit 2 operated at full power for the entire month of July 2002.
Major Safety Related Maintenance DATE W.O # SYSTEM COMPONENT COMPLETED WORK PERFORMED IP2-02-24105 IE N-35 7/2/2002 Replaced intermediate range channel power suppiy.