N oEl Committed to Nuclear Excellenjt~ Duane Arnold Energy Center Operated by Nuclear Management Company, LLC August 12, 2004 NG-04-0494 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 DUANE ARNOLD ENERGY CENTER DOCKET 50-331 LICENSE No. DPR-49 MONTHLY OPERATING REPORT Please find enclosed the Duane Arnold Energy Center (DAEC) Monthly Operating Report. The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: 'Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.

This letter makes no new commitments or changes to any existing commitments.

Sincerely, Mark A. lPeifer Site Vice President, Duane Arnold Energy Center NucI6ear Management Company,- LLC

Enclosure:

(1)

CC Administrator, Region ll, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC

.. , 47'4 3277 DAEC Road ' Palo, lowa 52324-9785 Telephone: 319.851.7611

ENCLOSURE I MONTHLY OPERATING REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE August 3, 2004 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING July 2004 PERIOD:

1. Design Electrical Rating (MWe) 581.40
2. Maximum Dependable Capacity 565.50 (MWe-Net)

This Month! Yr-to-Date Cumulative

3. Number of Hours the Reactor was 744.00 5,039.57 206,717.84 Critical
4. Number of Hours Generator On-line 744.00 5017.23 202,302.75
5. Reserve Shutdown Hours 0.00 0.00 192.80
6. Net Electrical Energy Generated 425,362.30 2,895,994.00 94,851,269.68 (MWHrs)

UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shuttin gAction No. Date Scheduled (Hours) Reason 1 Down Comments

'Reason: 2 Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic TriplScram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Page 1 of 2

NARRATIVE

SUMMARY

There were no departures from full power operation during the month of July except for weather related capacity losses.

Page 2 of 2

Text

N oEl Committed to Nuclear Excellenjt~ Duane Arnold Energy Center Operated by Nuclear Management Company, LLC August 12, 2004 NG-04-0494 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 DUANE ARNOLD ENERGY CENTER DOCKET 50-331 LICENSE No. DPR-49 MONTHLY OPERATING REPORT Please find enclosed the Duane Arnold Energy Center (DAEC) Monthly Operating Report. The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: 'Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.

This letter makes no new commitments or changes to any existing commitments.

Sincerely, Mark A. lPeifer Site Vice President, Duane Arnold Energy Center NucI6ear Management Company,- LLC

Enclosure:

(1)

CC Administrator, Region ll, USNRC Project Manager, DAEC, USNRC Resident Inspector, DAEC, USNRC

.. , 47'4 3277 DAEC Road ' Palo, lowa 52324-9785 Telephone: 319.851.7611

ENCLOSURE I MONTHLY OPERATING REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE August 3, 2004 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING July 2004 PERIOD:

1. Design Electrical Rating (MWe) 581.40
2. Maximum Dependable Capacity 565.50 (MWe-Net)

This Month! Yr-to-Date Cumulative

3. Number of Hours the Reactor was 744.00 5,039.57 206,717.84 Critical
4. Number of Hours Generator On-line 744.00 5017.23 202,302.75
5. Reserve Shutdown Hours 0.00 0.00 192.80
6. Net Electrical Energy Generated 425,362.30 2,895,994.00 94,851,269.68 (MWHrs)

UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shuttin gAction No. Date Scheduled (Hours) Reason 1 Down Comments

'Reason: 2 Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic TriplScram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Page 1 of 2

NARRATIVE

SUMMARY

There were no departures from full power operation during the month of July except for weather related capacity losses.