NG-04-0378, May 2004 Monthly Operating Report for Duane Arnold
| ML041740728 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 06/11/2004 |
| From: | Peifer M Nuclear Management Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, NG-04-0378, TS 5.6.4 | |
| Download: ML041740728 (3) | |
Text
i&
Nuxeln Committed to Nuclear Duane Arnold Energy Center Operated by Nuclear Management Company, LLC June 11, 2004 NG-04-0378 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station 0-PI -17 Washington, DC 20555-0001 DUANE ARNOLD ENERGY CENTER DOCKET 50-331 LICENSE No. DPR-49 MONTHLY OPERATING REPORT Please find enclosed the Duane Arnold Energy Center Monthly Operating Report.
The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: "Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.
This letter makes no new commitments or changes to any existing commitments.
Sincerely, Site Vice President, Duane Arnold Energy Center_
CC Regional Administrator, USNRC, Region III Project Manager, USNRC, NRR NRC Resident Inspector (DAEC)
Enclosure:
OPERATING DATA REPORT
'. I.
3277 DAEC Road
- Palo, Iowa 52324-9785 Telephone: 319.851.7611
a - {
June 11, 2004 Enclosure to NG-04-0378 Page 1 of 2 OPERATING DATA REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE June 4,2004 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING May 2004 PERIOD:
- 1. -Design Electrical Rating (MWe) 581.40
- 2. Maximum Dependable Capacity 565.50 (MWe-Net)
This Month} Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was 744.00 3.575.57 205.253.84 Critical
- 4. Number of Hours Generator On-line 744.00 3.553.23 200.838.75
- 5. Reserve Shutdown Hours 0.00 0.00 192.80
- 6. Net Electrical Energy Generated 430.021.40 2.058.372.30 94,013.647.98 (MWHrs)
UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shutting Action No. Date Scheduled (Hours) Reason I Down Comments 2 Method:
'Reason:
A Equipment Failure (Explain) I Manual B Maintenance or Test 2 Manual TriplScram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
June 11,2004 Enclosure to NG-04-0378 Page 2 of 2 NARRATIVE
SUMMARY
There were no departures from full power operation during the month of May.
Text
i&
Nuxeln Committed to Nuclear Duane Arnold Energy Center Operated by Nuclear Management Company, LLC June 11, 2004 NG-04-0378 TS 5.6.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station 0-PI -17 Washington, DC 20555-0001 DUANE ARNOLD ENERGY CENTER DOCKET 50-331 LICENSE No. DPR-49 MONTHLY OPERATING REPORT Please find enclosed the Duane Arnold Energy Center Monthly Operating Report.
The report has been prepared in accordance with the guidelines of NRC Generic Letter 97-02: "Revised Contents Of The Monthly Operating Report," and distribution has been made in accordance with DAEC Technical Specifications, Section 5.6.4.
This letter makes no new commitments or changes to any existing commitments.
Sincerely, Site Vice President, Duane Arnold Energy Center_
CC Regional Administrator, USNRC, Region III Project Manager, USNRC, NRR NRC Resident Inspector (DAEC)
Enclosure:
OPERATING DATA REPORT
'. I.
3277 DAEC Road
- Palo, Iowa 52324-9785 Telephone: 319.851.7611
a - {
June 11, 2004 Enclosure to NG-04-0378 Page 1 of 2 OPERATING DATA REPORT DOCKET NO. 50-331 UNIT NAME Duane Arnold DATE June 4,2004 COMPLETED BY Mike Fairchild TELEPHONE (319) 851-7642 REPORTING May 2004 PERIOD:
- 1. -Design Electrical Rating (MWe) 581.40
- 2. Maximum Dependable Capacity 565.50 (MWe-Net)
This Month} Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was 744.00 3.575.57 205.253.84 Critical
- 4. Number of Hours Generator On-line 744.00 3.553.23 200.838.75
- 5. Reserve Shutdown Hours 0.00 0.00 192.80
- 6. Net Electrical Energy Generated 430.021.40 2.058.372.30 94,013.647.98 (MWHrs)
UNIT SHUTDOWNS Type Method F: Forced of Cause & Corrective S: Duration Shutting Action No. Date Scheduled (Hours) Reason I Down Comments 2 Method:
'Reason:
A Equipment Failure (Explain) I Manual B Maintenance or Test 2 Manual TriplScram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
June 11,2004 Enclosure to NG-04-0378 Page 2 of 2 NARRATIVE
SUMMARY
There were no departures from full power operation during the month of May.