ND-19-1529, ITAAC Closure Notification on Completion of 2.5.02.08b.i (Index Number 542)

From kanterella
(Redirected from ND-19-1529)
Jump to navigation Jump to search
ITAAC Closure Notification on Completion of 2.5.02.08b.i (Index Number 542)
ML19357A040
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 12/20/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-19-1529
Download: ML19357A040 (6)


Text

Southern Nuclear Michael J. Yox Regulatory Affairs Director 7825 River Road Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 DEC 2 0 2019 Docket No.: 52-025 ND-19-1529 10CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of 2.5.02.08b.i Flndex Number 5421 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC)of the completion of Vogtle Electric Generating Plant(VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria(ITAAC)Item 2.5.02.08b.i [Index Number 542]. This ITAAC confirms the Protection and Safety Monitoring System (PMS) provides for the transfer of control capability from the Main Control Room to the Remote Shutdown Room using multiple transfer switches. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of 2.5.02.08b.i [Index Number 542]

MJY/RAS/sfr

U.S. Nuclear Regulatory Commission ND-19-1529 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE; VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. S. Smith Mr. C. Santos Oqfethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen

U.S. Nuclear Regulatory Commission ND-19-1529 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Eiectric Company. LLC Dr. L. OrianI (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, TetraTech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-19-1529 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-1529 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of 2.5.02.08b.i [Index Number 542]

U.S. Nuclear Regulatory Commission ND-19-1529 Enclosure Page 2 of 3 ITAAC Statement Desian Commitment 8.b) The RMS provides for the transfer of control capability from the MCR to the RSW using multiple transfer switches. Each individual transfer switch Is associated with only a single safety-related group or with nonsafety-related control capability.

Inspections. Tests. Analvses i) An inspection will be performed to verify that a transfer switch exists for each safety-related division and the nonsafety-related control capability.

Acceptance Criteria i) A transfer switch exists for each safety-related division and the nonsafety-related control capability.

ITAAC Determination Basis Multiple ITAAC are performed to ensure that the Protection and Safety Monitoring System (PMS) provides for the transfer of control capability from the Main Control Room (MCR)to the Remote Shutdown Workstation (RSW) using multiple transfer switches. Each individual transfer switch is associated with only a single safety-related group or with nonsafety-related control capability. The subject ITAAC requires that an inspection be performed to verify that a transfer switch exists for each safety-related division and the nonsafety-related control capability.

The PMS and Plant Control System (PLS)transfer switches were installed in accordance with approved drawings and specifications released by engineering for construction. An inspection was performed to verify that a transfer switch exists for each safety-related division and the nonsafety-related control capability. The inspection was performed in accordance with SV3-OCS-ITR-800542(Reference 1), which requires performance of visual observations to compare the installed equipment to the approved drawings. The inspection results are also documented in SV3-OCS-ITR-800542 which serves as the Principal Closure Document supporting the ITAAC 2.5.02.08b.i Completion Package (Reference 2). The inspection report confirms that a transfer switch exists for each safety related division and the nonsafety-related control capability.

Principal Closure Document SV3-OCS-ITR-800542 is available for NRC inspection as part of the ITAAC 2.5.02.08b.i Completion Package.

ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented In the ITAAC Completion Package for ITAAC 2.5.02.08b.i (Reference 2) and available for NRC review.

U.S. Nuclear Regulatory Commission ND-19-1529 Enclosure Page 3 of 3 ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRG that ITAAC 2.5.02.08b.i was performed for VEGP Unit 3 and that the prescribed acceptance criteria are met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References favailable for NRG inspection)

1. SV3-OCS-ITR-800542,"Unit 3 MCR/RSR Transfer Panel Installation: ITAAC 2.5.02.08b.i," Revision 0
2. 2.5.02.08b.i-U3-CP-Rev 0,"ITAAC 2.5.02.08b.i Completion Package," Revision 0
3. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"