Letter Sequence Supplement |
---|
EPID:L-2017-LLA-0421, ITAAC Closure Verification Evaluation Form (Vef) 5149 for ITAAC 3.2.00.01c.ii (Index No. 742) for Vogtle Unit 4 (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML18019A3622018-01-25025 January 2018 (LAR 17-037) Acceptance Letter Project stage: Acceptance Review ML18066A7172018-03-0707 March 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-1) Project stage: RAI ND-18-0417, Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process2018-04-0606 April 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2 Departure Evaluation Process Project stage: Supplement ML18102B6832018-04-12012 April 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-3) Project stage: RAI ML18113A7802018-04-23023 April 2018 COL Docs - RAI Transmittal for Vogtle 3 & 4 LAR 17-037 (RAI LAR 17-037-4) Project stage: RAI ML18121A4372018-05-0101 May 2018 COL Docs - RAI Transmittal for Vogtle 3 and 4 LAR 17-037 (RAI LAR 17-037-5, -6, -7, and -8) Project stage: RAI ML18128A3692018-05-0808 May 2018 COL Docs - RAI Transmittal for Vogtle 3 and 4 LAR 17-037 (RAI LAR 17-037-9) Project stage: RAI ND-18-0608, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S2)2018-05-11011 May 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S2) Project stage: Supplement ND-18-0646, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3)2018-06-18018 June 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S3) Project stage: Supplement ND-18-0830, Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01c.ii (Index Number 742)2018-06-27027 June 2018 Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01c.ii (Index Number 742) Project stage: Request ND-18-0831, Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01d (Index Number 743)2018-06-28028 June 2018 Unit 4 - ITAAC Closure Notification on Completion of ITAAC 3.2.00.01d (Index Number 743) Project stage: Request ML18200A1682018-07-19019 July 2018 ITAAC Closure Verification Evaluation Form (Vef) 4369 for ITAAC 3.2.00.01d (Index No. 743) for Vogtle Unit 3 Project stage: Request ML18200A1672018-07-19019 July 2018 ITAAC Closure Verification Evaluation Form (Vef) 5149 for ITAAC 3.2.00.01c.ii (Index No. 742) for Vogtle Unit 4 Project stage: Request ND-18-1006, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S4)2018-08-0303 August 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S4) Project stage: Supplement ND-18-1067, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S5)2018-08-10010 August 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S5) Project stage: Supplement ML18256A4002018-09-0707 September 2018, 12 September 2018, 20 September 2018, 26 September 2018 Non-Concurrence Process NCP-2018-008, Vogtle Units 3 and 4, License Amendment Request 17-037, Changes to Tier 2* Departure Evaluation Process Project stage: Request ND-18-1180, Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S6)2018-09-13013 September 2018 Supplement to Request for License Amendment and Exemption: Changes to Tier 2* Departure Evaluation Process (LAR-17-037S6) Project stage: Supplement ML18235A0322018-09-20020 September 2018 Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 17-037 Project stage: Other ML18207A2622018-09-20020 September 2018 Safety Evaluation - Vogtle Electric Generating Plant, Units 3 and 4 LAR 17-037 Project stage: Approval ML18235A0362018-09-20020 September 2018 Attachment to Amendment No. 141 - VEGP Unit 4 LAR 17-037 Project stage: Acceptance Review ML18235A0352018-09-20020 September 2018 Amendment No. 141 - Vogtle Electric Generating Plant, Unit 4 LAR 17-037 Project stage: Other ML18235A0342018-09-20020 September 2018 Attachment to Amendment No. 142 - VEGP Unit 3 LAR 17-037 Project stage: Acceptance Review ML18235A0292018-09-20020 September 2018 Issuance of Amendments 142 and 141 and Granting of Exemptions Changes to the Tier 2* Departure Evaluation Process (LAR 17-037) Project stage: Request ML18235A0302018-09-20020 September 2018 Cover Letter - Vogtle LAR 17-037 - Issuance of Amendments 142 and 141 and Granting of Exemptions Re Changes to the Tier 2* Departure Evaluation Process Project stage: Approval ML18235A0312018-09-20020 September 2018 Exemption - Vogtle Electric Generating Plant - Unit 3 LAR 17-037 Project stage: Other ML18235A0332018-09-20020 September 2018 Amendment 142 - Vogtle Electric Generating Plant, Unit 3 LAR 17-037 Project stage: Other 2018-06-18
[Table View] |
|
---|
Category:Letter type:ND
MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, (Vegp), Unit 4 - Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 (Vegp), Unit 4 - Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, (Vegp), Unit 4 - Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 (Vegp), Unit 4 - Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 (Vegp), Units 3 and 4 - Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 (Vegp), Unit 4, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 (Vegp), Unit 3 - Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0581, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) 2024-04-26
[Table view] |
Text
Southern Nuclear Operating Company, Inc.
3535 Colonnade Parkway Birmingham, AL 35243 August 10, 2018 Docket Nos.: 52-025 ND-18-1067 52-026 10 CFR 50.90 10 CFR 52.7 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Supplement to Request for License Amendment and Exemption:
Changes to Tier 2* Departure Evaluation Process (LAR-17-037S5)
Ladies and Gentlemen:
Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) requested an amendment to the combined licenses (COLs) for Vogtle Electric Generating Plant (VEGP) Units 3 and 4 (License Numbers NPF-91 and NPF-92, respectively) by SNC letter ND-17-1726, dated December 21, 2017 [ADAMS Accession Number ML17355A416],
to apply the existing departure evaluation process for Tier 2 departures to the evaluation of certain Tier 2* departures. This license amendment request (LAR)17-037 was supplemented by SNC letters ND-18-0417 (LAR-17-037S1), dated April 6, 2018 [ML18096B328], ND-18-0608 (LAR-17-037S2), dated May 11, 2018 [ML18131A263], ND-18-0646 (LAR-17-037S3), dated June 18, 2018 [ML18169A431], and ND-18-1006 (LAR-17-037S4), dated August 3, 2018
[ML18215A461]. By letter ND-17-1726, SNC also requested an exemption from certain change requirements in 10 CFR Part 52, Appendix D, consistent with the requested license amendment.
SNC letter ND-17-1726 included eight enclosures, identified as Enclosures 1 through 8. provided a reviewers aid to demonstrate the application of the Tier 2* departure evaluation process proposed by LAR-17-037 to a previously proposed change to Tier 2* material.
Enclosures 1 through 8 were updated and re-issued as Enclosures 1U through 8U to SNC letter ND-18-1006 to incorporate changes that were required by the supplemental information provided in Supplements 2 through 4 of LAR-17-037. It was subsequently identified that the information provided in Enclosure 6U is duplicative of the more detailed change description and justification provided in the updated LAR in Enclosure 1U and elsewhere in LAR-17-037, as supplemented, and accordingly, this reviewers aid should not be considered in the review of this licensing request. Therefore, this supplement to LAR-17-037 removes the information provided as ND 1006, Enclosure 6U, Updated Reviewers Aid: Tier 2* Departure Example Not Requiring Prior NRC Approval. It is SNCs understanding that the removal of this reviewers aid will not impact the NRC staffs review of the technical and regulatory content of LAR-17-037, as this information was only provided to facilitate the staffs understanding of the process proposed by the LAR.
The information provided in this LAR supplement does not impact the scope, technical content, or conclusions of the Significant Hazards Consideration Determination or the Environmental Considerations of the original LAR-17-037 provided in Enclosure 1 of SNC letter ND-17-1726.
U.S. Nuclear Regulatory Commission ND-18-1067 Page 2 of 4 This letter contains no regulatory commitments. This letter has been reviewed and determined not to contain security-related information.
In accordance with 10 CFR 50.91, SNC is notifying the State of Georgia of this LAR supplement by transmitting a copy of this letter and its enclosure to the designated State Official.
Should you have any questions, please contact Mr. Wesley Sparkman at (205) 992-5061.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 1Oth of August 2018.
Respectfully submitted, Amy Aughtman Licensing Manager, Regulatory Affairs Southern Nuclear Operating Company
U.S. Nuclear Regulatory Commission ND-18-1067 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski Mr. D. G. Bost Mr. M. D. Meier Mr. D. H. Jones Mr. J. B. Klecha Mr. G. Chick Mr. D. L. McKinney Mr. T. W. Yelverton Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. E. W. Rasmussen Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Ms. P. Reister Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. T.E. Chandler Ms. P. Braxton Mr. T. Brimfield Mr. C. J. Even Mr. A. Lerch State of Georgia Mr. R. Dunn
U.S. Nuclear Regulatory Commission ND-18-1067 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani Mr. C. Churchman Mr. M. Corletti Mr. M. L. Clyde Ms. L. Iller Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. R. Grumbir, APOG NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light