MEMORANDUM TO:
Robert Sun, Chief Environmental Project Management Branch 2 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards FROM:
Patrick Donohue, Project Manager Environmental Project Management Branch 2 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards
SUBJECT:
SUMMARY
OF MEETING ON FEBRUARY 19, 2026, WITH HOLTEC DECOMMISSIONING INTERNATIONAL TO DISCUSS NATIONAL HISTORIC PRESERVATION ACT SECTION 106 CONSULTATION AND MEMORANDUM OF AGREEMENT SCHEDULE FOR THE OYSTER CREEK NUCLEAR GENERATING STATION LICENSE TERMINATION PLAN The U.S. Nuclear Regulatory Commission (NRC) staff conducted a meeting with Holtec Decommissioning International (HDI), the licensee, on February 19, 2026, concerning the National Historic Preservation Act (NHPA) Section 106 consultation for the Oyster Creek Nuclear Generating Station license termination plan (LTP). Attendees included staff from the NRC, staff from HDI, and staff from HDIs consultants, Enercon and SEARCH.
The purpose of this meeting was to discuss HDIs draft forms and maps for the New Jersey State Historic Preservation Office (NJ SHPO) and to go over a schedule for NHPA Section 106 consultation and potential Memorandum of Agreement (MOA). Ahead of the meeting, the NRC staff were able to review HDIs shared drafts of the supplemental information requested by the NJ SHPO in their January 15, 2026, letter (Agencywide Documents Access and Management System Accession No. ML26026A103). The NRC staff discussed various edits to be made to those forms and maps, including making the maps clearer and adding dates to the table of site buildings. An outstanding item that arose from this discussion was whether the NJ SHPO would need HDI to update the boundary on the historic district overlay form requested by the NJ SHPO. The NRC staff agreed to find out from the NJ SHPO and relay that information promptly.
CONTACT:
Patrick S. Donohue, NMSS/REFS (310) 415-5237 March 2, 2026 Signed by Donohue, Patric on 03/02/26
R. Sun 2
The meeting continued with the NRC staff presenting a draft schedule for the completion of an MOA to resolve adverse effects. The schedule, enclosed here, was discussed with a focus on HDIs roles and responsibilities. The NRC staff emphasized the aggressive design of the schedule, highlighting that delays early in the schedule could result in cascading impacts and additional delay. The NRC team also pointed out that the LTP approval could not be issued until the MOA was signed, emphasizing the need to stay within the schedule.
The meeting concluded with planning for future meetings and going over the action items.
Foremost of which was for the NRC staff to find out from the NJ SHPO the extent of the historic district boundary as it related to the required overlay form. The NRC staff, HDI, and the consultants then discussed the path forward for submitting the final version of the supplement to the architectural survey report once NRC staff receive clarity from the NJ SHPO.
Docket No. 50-219
Enclosure:
As stated
R. Sun 3
LIST OF ATTENDEES:
U.S. Nuclear Regulatory Commission Patrick Donohue Beau Goldstein Marlayna Doell Ted Smith Robert Sun Holtec Decommissioning International Steven Johnson John Murphy William Noval Benjamin Reynolds Ed OBrien Sarah Roberts Enercon Steven Walker SEARCH Angelique Theriot Bryan Herling Bill Werner
R. Sun 4
SUBJECT:
SUMMARY
OF MEETING ON FEBRUARY 19, 2026, WITH HOLTEC DECOMMISSIONING INTERNATIONAL TO DISCUSS NATIONAL HISTORIC PRESERVATION ACT SECTION 106 CONSULTATION AND MEMORANDUM OF AGREEMENT SCHEDULE FOR THE OYSTER CREEK NUCLEAR GENERATING STATION LICENSE TERMINATION PLAN DATED:
DISTRIBUTION:
Public PDonohue, NMSS/REFS BGoldstein, NMSS/REFS TSmith, NMSS/REFS RSun, NMSS/REFS MDoell, NRR/DORL Steven Johnston S.Johnston@Holtec.com ADAMS Accession Number: ML26054A048
- via email OFFICIAL RECORD COPY OFFICE NMSS/REFS NMSS/REFS NRR/DORL NMSS/REFS NMSS/REFS NAME PDonohue AWalker-Smith MDoell RSun PDonohue DATE 02/23/2026 02/23/2026 02/23/2026 02/25/2026 03/02/2026 March 2, 2026
Enclosure Oyster Creek Nuclear Generating Station License Termination Plan, Lacey and Ocean Townships, New Jersey Holtec Decommissioning International National Historic Preservation Act Section 106 Resolution of Adverse Effects Timeline No.
Milestone Responsible Party Duration (days)
Completion Date 1
NRC to determine if we are staying with substitution or will proceed with S106 compliance separate from NEPA.
NRC parallel When relevant 2
HDI shares supplementary info with NRC through SharePoint for preliminary review.
HDI 8
2/19/26 3
NRC reviews and preliminarily approves SharePoint materials.
NRC 5
2/23/26 4
NRC begins preparing draft MOA.
NRC parallel ASAP (Feb 2026) 5 Applicant submits supplemental architectural survey forms and maps to NRC on the docket.
Applicant to note if anything will be non-public or sensitive HDI 2
2/25/26 6
NRC sends letters to consulting parties revising determination of eligibility and effect, including supplemental documentation from applicant.
Note that sensitive information in forms and maps would need to be redacted.
SHPO has 30 days to respond, but has said they would expedite this review.
NRC 5
3/2/26 7
NJ SHPO concurs with determination of eligibility and effect and approves supplemental architectural survey report. ACHP and Tribes provide comments.
There could be some back-and-forth on the supplemental architectural survey report, but that should not hold up next steps.
NJ SHPO,
- ACHP, Tribes 10 3/12/26 8
OGC reviews draft MOA.
NRC OGC parallel March 2026 9
NRC shares preliminary draft MOA with SHPO and HDI to get their buy-in.
Could involve some back-and-forth, but will ideally be done via meetings.
NRC, SHPO, HDI When OGC is done 3/23/26 target 10 NRC updates draft EA with draft MOA details.
NRC 8
3/31/26 11 NRC sends letters making the draft MOA and the draft historic and cultural section of the EA public.
NRC 3
4/3/26 12 NJ SHPO (and any other consulting parties) provides comments on the draft EA and MOA.
NJ SHPO 14 4/17/2026 13 Back-and-forth with consulting parties on draft EA H&C section and MOA details. May require additional letters.
Recipients would have 10-14 days to respond if additional letters are needed.
NJ SHPO, HDI 14 5/1/26 14 Resolve draft EA and MOA comments.
NRC parallel 5/1/26 15 Prepare final EA and MOA.
NRC 4
5/5/26
2 16 OGC approval.
NRC OGC 14 5/19/26 17 Circulate Final MOA for signature.
NRC 1
5/20/26 18 NRC, SHPO, and applicant sign the MOA.
NRC, NJ SHPO, HDI 14 6/3/26 19 File executed MOA with ACHP.
NRC 7
6/10/26 20 Steps to finalize EA, incorporating the signed MOA.
NRC parallel 6/10/26 21 NRC sends letters to consulting parties with signed MOA and final EA, announcing availability.
NRC 1 (prep parallel) 6/11/26 Assumes expeditious and acceptable submittals from HDI.
Assumes maximum responsiveness from HDI.
Assumes expeditious responses from consulting parties (much less than the 30 days statutorily allowed).
Assumes no other parties choose to join the consultation.
Assumes NRC OGC can support the proposed schedule.
Assumes minimal and simple MOA comments (from both NRC OGC and consulting parties), and expeditious resolution of comments.